1/54
Comprehensive practice flashcards reviewing core Lean Six Sigma concepts, DMAIC tools, probability distributions, hypothesis testing, control charts, process maps, and value stream mapping.
A Six Sigma process is statistically defined as producing no more than __________ defects per million opportunities (DPMO).
3.4
The 3.4 DPMO metric incorporates a standard __________ long-term process shift established by Motorola.
1.5σ
In terms of percentage accuracy, a Six Sigma process produces defect-free product __________ percent of the time.
99.99966
The statistical roots of process control date back to the development of the normal curve in the 19th century by __________.
Carl Friedrich Gauss
The scholar and engineer considered the father of control charts who first closely linked sigma level and quality was __________.
Walter Shewhart
W. Edwards Deming popularized the continuous improvement cycle known as the __________ cycle.
PDCA (or plan-do-check-act)
In the Toyota Production System, the principle that demands a process stop immediately as soon as errors are detected is called __________.
jidoka
The continuous improvement tool from Lean that translates loosely from Japanese to "change for the better" is __________.
Kaizen
The foundational Rummler-Brache model created by a matrix of three performance levels and three performance dimensions is the __________.
Nine Boxes Model
According to Taiichi Ohno, producing an item too fast, at the wrong time, or in excess quantity is the waste of __________.
overproduction
While waste of motion involves unnecessary movements of employees, waste of __________ refers to the unnecessary physical movement of goods, materials, or outputs.
conveyance (or transportation)
Non-value-added tasks that fail to directly add value but are currently essential or obligatory to business operations are classified as __________ muda.
Type I
The sequential Japanese steps of the 5S methodology are Sort (Seiri), Straighten (Seiton), Shine (Seiso), Standardize (Seiketsu), and Sustain (__________).
Shitsuke
When calculating the standard deviation (s) from sample data, the sum of squared differences from the sample mean is divided by __________ before taking the square root.
N−1
The Pareto principle, stating that 20 percent of causes lead to 80 percent of effects, was first applied to quality management by __________.
Joseph Juran
A survey rating scale commonly used in Voice of the Customer campaigns that converts responses into a 5-point numerical ranking is the __________.
Likert Scale
The Six Sigma quality metric calculated by dividing the total number of defects discovered by the total number of sampled units is __________.
Defects per Unit (DPU)
Unlike First Time Yield (FTY), Rolled Throughput Yield (RTY) provides a true probability of a defect-free unit by accounting for __________.
rework (and scrap)
Six Sigma models a process problem as a mathematical function represented by the formula __________.
Y=f(X) (or y=f(x))
The brainstorming tool where team members ask a succession of why questions to uncover the root cause of a defect is the __________.
5 Whys
When a project team gradually expands beyond original boundaries, pursues infinite perfections, or takes on unmanageable tasks, the project is suffering from __________.
scope creep
In a high-level SIPOC diagram, the acronym stands for Suppliers, Inputs, Process, Outputs, and __________.
Customers
Resources such as specialized machinery, power, or tools that do not become part of the output but are required for a process to operate are classified on a SIPOC as __________.
enablers
ISO 9000 defines quality as the degree to which a set of inherent characteristics fulfills __________.
requirements
A diagramming tool that systematically converts broad Voice of the Customer needs into specific drivers and measurable requirements is a(n) __________.
CTQ tree (Critical to Quality tree)
The total Cost of Quality (CoQ) equation combines the Cost of Poor Quality (CoPQ) with Prevention Costs and __________ Costs.
Appraisal
In a process performing at a true Six Sigma level, the total Cost of Quality is typically expected to drop to less than __________ percent of sales.
1
In a Failure Modes and Effects Analysis (FMEA), the Risk Priority Number (RPN) is calculated as SEV×OCC× __________.
DET (Detection)
To ensure adequate measurement resolution, the 10-bucket rule requires that a gage detect changes at __________ of the expected parameter tolerance.
one-tenth (or 0.1)
In Gage R&R analysis, the ability of multiple appraisers to obtain the same measurement when assessing the same part with the same gage is called __________.
reproducibility
On a standard box plot, the top of the box represents the __________ percentile, while the bottom of the box represents the 25th percentile.
75th
In linear regression analysis, the coefficient of determination measuring the percentage of variation in y explained by changes in x is denoted as __________.
r2 (or R-squared)
The theorem stating that the distribution of sample means approaches a normal curve as sample size increases, regardless of the underlying distribution, is the __________.
Central Limit Theorem
In hypothesis testing, a Type I error occurs when the null hypothesis is __________ even though it is true.
rejected
If the calculated p-value from a statistical hypothesis test is less than the chosen alpha (α), the decision is to __________ the null hypothesis.
reject
The null hypothesis (H0) evaluated in a One-Way ANOVA test states that all population means are __________.
equal
The process capability index (Cpk) is mathematically calculated by dividing the process sigma level by __________.
3
In statistical process control, many organizations target a process capability (Cpk) of 2.0, while the minimal acceptable capability is __________.
1.5 (or 1.33 for 4-sigma)
A process control or design mechanism designed to mistake-proof an activity so that errors cannot easily occur is called a(n) __________.
poka yoke
In SPC control chart evaluation, Test 1 signals a special cause when a single point is located more than __________ standard deviations from the center line.
3.00 (or 3)

In standard flowcharting, the rectangle shape shown in the image represents a(n) __________ step.
process (or action)

In process mapping symbology, the hexagon shape shown in the image represents a(n) __________ step.
preparation

The rounded oblong pill shape shown in the image is a(n) __________ shape, used to mark the beginning or end of a process.
terminator

In process mapping symbology, the trapezoid shape shown in the image represents a(n) __________ step.
manual operation

In Value Stream Mapping, the factory shape shown in the image represents __________.
Outside Sources (suppliers or customers)

In Value Stream Mapping, the wide outlined arrow symbol shown in the image represents __________.
Finished Goods to Customer

In Value Stream Mapping, the icon shown in the image represents material transportation by __________.
forklift

In Value Stream Mapping, the symbol displaying a card with a clipped corner shown in the image represents a(n) __________.
Production Kanban

The continuous probability distribution shown in the image, characterized by a constant horizontal density over a specified interval, is a(n) __________ distribution.
Uniform

The continuous distribution plot shown in the image, defined strictly by lower, mode, and upper bounds, is a(n) __________ distribution.
Triangular

On the control chart diagram shown in the image, Zone A corresponds to the region located between __________ and 3 standard deviations from the center line.
2
In Design of Experiments (DOE), two factors demonstrate zero interaction when their trend lines on an interaction plot are __________.
parallel
While a p-chart tracks the proportion defective across variable subgroup sizes, a(n) __________ chart tracks the number of nonconforming items using a constant subgroup size.
np-chart
A c-chart monitors the count of defects using a constant subgroup size, whereas a(n) __________ chart monitors the count of defects per unit across variable subgroup sizes.
u-chart
In a responsibility RACI matrix, the letter "A" designates the functional role that is ultimately __________ for the activity.
Accountable