Vocabulary terms, operational definitions, numerical criteria, and structural codes extracted directly from the 2021 International Building Code (IBC) practice questions and official answer key for Building Plans Examiners.

Last updated 12:04 AM on 9/29/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

121 Terms

1
New cards

Stationary Generator Systems Standard

UL 2200

2
New cards

Group B Occupancy (Assembly Exception)

An assembly building with an occupant load of less than 5050 persons.

3
New cards

Semiconductor Fabrication Facility Power Requirements

Must be provided with emergency power.

4
New cards

Dwelling Unit Minimum Temperature Capability

Must be capable of maintaining a minimum temperature of 68∘F68^{\circ}\text{F}.

5
New cards

Group A-4 Automatic Sprinkler Threshold

Required when the fire area has an occupant load of 300300 or more.

6
New cards

Ready Access

The required access type for Class II standpipe hose connections.

7
New cards

Parapet Wall Requirement

A protective wall requirement applied to exterior walls of a building.

8
New cards

Construction Document Retention Period

Must be retained for not less than 180 days180\,\text{days} from completion of the project.

9
New cards

Underground Buildings Power Requirements

Must be equipped with both emergency and standby power.

10
New cards

High-Rise Building Power Requirements

Must be provided with both emergency and standby power.

11
New cards

Group I-2 Maximum Sleeping Room Travel Distance

The maximum travel distance from a sleeping room to an exit access door is 50 ft50\,\text{ft}.

12
New cards

Aircraft Control Tower Automatic Sprinkler Requirement

Required when there is an occupied floor located more than 35 ft35\,\text{ft} above the lowest fire department access level.

13
New cards

High-Rise Tower Stairway Separation Distance

The minimum distance between exit stairways in a high-rise tower is 30 ft30\,\text{ft}.

14
New cards

Group I-1 Commercial Cooking Fire Extinguisher Distance

A fire extinguisher must be installed within 30 ft30\,\text{ft} of commercial cooking equipment.

15
New cards

Chimney Cricket / Saddle Requirement Threshold

Must be installed on the ridge side of any chimney with a width greater than 30 in30\,\text{in}.

16
New cards

Group H-2 Fire Wall Rating

4 hours4\,\text{hours}

17
New cards

Permit Application Extension Period

The building official may grant an extension of up to 90 days90\,\text{days} on a permit application.

18
New cards

Group H Exterior Wall Rating (< 5 ft Separation)

Exterior walls in a Group H occupancy with a fire separation distance of less than 5 ft5\,\text{ft} must have a fire resistance rating of 3 hours3\,\text{hours}.

19
New cards

Type IV Construction

Construction type characterized by exterior walls of noncombustible materials and interior elements of solid or laminated wood.

20
New cards

Foam Plastic Insulation Maximum Smoke Developed Index

450450

21
New cards

Group H-2 Occupancy

Classification used for buildings and structures containing materials that pose a deflagration hazard.

22
New cards

Handrail Height Limits

Must be located between 34 in34\,\text{in} and 38 in38\,\text{in} vertically above the finished floor or stair tread nosing.

23
New cards

Group R

Occupancy classification designated for residential groups.

24
New cards

Foam Plastic Insulation Maximum Flame Spread Index

7575

25
New cards

Polyethylene Vapor Retarder Lap Joint Minimum

Joints for poly vapor retarders under concrete slabs directly on the ground must be lapped not less than 6 in6\,\text{in}.

26
New cards

Live Load

A variable or transient load imposed by the intended use and occupancy within a structure.

27
New cards

Construction Barrier Minimum Height

8 ft8\,\text{ft}

28
New cards

Structural Glass Veneer Maximum Single Piece Area

10 sq ft10\,\text{sq ft} (10 ft10\,\text{ft})

29
New cards

Sloped Glazing Screen Distance

Screens required for sloped glazing must be located within 4 in4\,\text{in} of the glass.

30
New cards

Public Parking Garage Vehicle Barrier Threshold

Vehicle barriers are required where there is a change in elevation of 1 ft1\,\text{ft} or more.

31
New cards

Metal Roof Shingle Valley Flashing Centerline Distance

Valley flashing must extend not less than 8 in8\,\text{in} from the centerline.

32
New cards

Louvered Window Maximum Length

48 in48\,\text{in}

33
New cards

Interior Door Maximum Opening Force

Must not exceed 5 lbs5\,\text{lbs} of force.

34
New cards

Official Plan Approval Stamp Phrase

"Reviewed for code compliance"

35
New cards

Braced Wall Line

A straight line through the building plan that represents the location of lateral resistance provided by wall bracing.

36
New cards

Ramp Handrail Threshold Rise

Ramps require handrails when the rise exceeds 6 in6\,\text{in}.

37
New cards

Fire Damper

A listed device installed in ducts and air transfer openings designed to close automatically upon detection of heat and resist the passage of flame.

38
New cards

Group A-3

Assembly occupancy designation for spaces such as libraries and places of worship without spectating.

39
New cards

Marquee Maximum Height

9 ft9\,\text{ft} when projecting less than two-thirds of the distance from the lot line to the curb line.

40
New cards

Group I

Occupancy classification designated for institutional facilities.

41
New cards

Group F

Occupancy classification designated for factory and industrial uses.

42
New cards

Dead Load

A permanent structural load comprised of the weight of fixed assets, structural framing, and permanent building materials.

43
New cards

Fireplace Combustible Clearance

Requires a minimum 2 in2\,\text{in} airspace clearance between combustible materials and the fireplace structure.

44
New cards

Stretcher Elevator Minimum Dimensions

24 in24\,\text{in} by 84 in84\,\text{in}

45
New cards

Step Projection Limit into Public Right of Way

Steps shall not project more than 12 in12\,\text{in} into the public right-of-way.

46
New cards

Shallow Foundation Footing Minimum Depth

12 in12\,\text{in} below undisturbed ground surface.

47
New cards

Slab-on-Ground Minimum Thickness

312 in3\frac{1}{2}\,\text{in} (3.5 in3.5\,\text{in})

48
New cards

Group R-1 Fire Wall Rating

3 hours3\,\text{hours}

49
New cards

Type II Construction

Building construction type in which exterior walls and interior structural elements are constructed of noncombustible materials.

50
New cards

Incidental Use Area Limit

Incidental uses shall not occupy more than 10%10\% (10 percent10\,\text{percent}) of the building area.

51
New cards

Group F-2

Occupancy classification designated for low-hazard factory industrial uses.

52
New cards

Transient Occupancy

Occupancy of a dwelling unit or sleeping unit for a duration of not more than 30 days30\,\text{days}.

53
New cards

Awning Vertical Clearance Projection Limit

Awnings projecting into the public right-of-way shall not be less than 7 ft7\,\text{ft} vertically above the walkway.

54
New cards

Construction Site Walkway Live Load Capacity

Must be capable of withstanding a design live load of not less than 150 psf150\,\text{psf}.

55
New cards

Masonry Hearth Minimum Thickness

4 in4\,\text{in}

56
New cards

Handrail Uniform Linear Load Capacity

50 lbs/ft50\,\text{lbs/ft} (50 lbs50\,\text{lbs})

57
New cards

Chimney Wall Minimum Thickness

4 in4\,\text{in}

58
New cards

Group A Occupancy Standpipe Requirement (Non-Sprinklered)

A Class I standpipe system is required in non-sprinklered Group A buildings with an occupant load exceeding 10001000.

59
New cards

Parapet Wall Exception Area Threshold

Parapets are not required on buildings having an area of not more than 1000 sq ft1000\,\text{sq ft}.

60
New cards

Type I-A Tank Support Volume Threshold

Tanks with a capacity of 500 gal500\,\text{gal} or more must be supported by Type I-A construction.

61
New cards

Agricultural Facilities Risk Category

Category I

62
New cards

Draft Stop

A material, device, or construction installed to restrict the movement of air within open spaces of concealed building components such as crawl spaces, floor/ceiling assemblies, and attics.

63
New cards

Group A-2 Nightclub Lavatory Ratio

11 lavatory per 7575 occupants.

64
New cards

Mezzanine Clear Height Requirement

The clear height above and below a mezzanine floor assembly shall be no less than 7 ft7\,\text{ft}.

65
New cards

Vehicle Barrier Concentrated Load Capacity

6000 lbs6000\,\text{lbs}

66
New cards

Group A-5

Occupancy designation for outdoor assembly areas such as stadiums and grandstands.

67
New cards

Fire Pump Barrier Protection Rating

Fire pumps must be protected by a fire barrier rated for 2 hours2\,\text{hours}.

68
New cards

Group H-5

Occupancy classification designated for semiconductor fabrication facilities.

69
New cards

Parapet Uppermost Noncombustible Face Distance

Must have noncombustible faces for the uppermost distance of 18 in18\,\text{in}.

70
New cards

Group H-1

Occupancy classification for buildings containing materials that present a high detonation or explosive hazard.

71
New cards

Exterior Plaster Weep Screen Minimum Thickness

0.019 in0.019\,\text{in}

72
New cards

Asphalt Felt Water Barrier Grade

No. 15 asphalt felt.

73
New cards

Group A-1

Occupancy classification for assembly spaces with fixed seating intended for the viewing of performing arts or motion pictures (e.g., theaters).

74
New cards

Open Valley Flashing Minimum Width (Asphalt Shingles)

24 in24\,\text{in} wide.

75
New cards

Group I-3 Fire Alarm Type

A manual fire alarm system designed to alert staff.

76
New cards

Area of Refuge Wheelchair Space Dimensions

30 in30\,\text{in} by 52 in52\,\text{in}

77
New cards

Stair Riser Maximum Height

7 in7\,\text{in}

78
New cards

Class A Interior Finish Flame Spread Index

00 to 2525

79
New cards

Temporary Membrane Structure Maximum Service Life

Not more than 180 days180\,\text{days}

80
New cards

Court

An open, uncovered space bounded on two or more sides by the exterior walls of a building or structure, open to the sky.

81
New cards

Smoke Barrier Fire Resistance Rating

1 hour1\,\text{hour}

82
New cards

Covered Mall Open Space Surrounding Requirement

An open space of no less than 60 ft60\,\text{ft} surrounding the covered mall building.

83
New cards

Thin Exterior Glass Veneer Minimum Thickness

0.344 in0.344\,\text{in}

84
New cards

Attic Access Minimum Opening Dimensions

20 in20\,\text{in} by 30 in30\,\text{in}

85
New cards

Dwelling Unit Minimum Corridor Width

36 in36\,\text{in}

86
New cards

Exit Passageway

An exit component that is separated from other interior spaces of a building by fire-resistance-rated construction and provides a protected path of egress travel in a horizontal direction.

87
New cards

Group H

Occupancy classification for high-hazard uses.

88
New cards

Group S

Occupancy classification for storage uses.

89
New cards

Crawl Space Minimum Opening Size

18 in18\,\text{in} by 24 in24\,\text{in}

90
New cards

Group H-3

Occupancy classification for buildings containing materials that readily support combustion or present a physical hazard.

91
New cards

Emergency Power Minimum Duration Capability

2 hours2\,\text{hours}

92
New cards

Required Exits for Occupant Load > 1000

Not less than 44 exits.

93
New cards

Slab-on-Ground Vapor Retarder Thickness

6 mil6\,\text{mil} polyethylene sheet.

94
New cards

Shallow Foundation Footing Minimum Width

12 in12\,\text{in}

95
New cards

Group I-3 Clear Door Width

Clear width of not less than 28 in28\,\text{in} for sleeping unit doors.

96
New cards

1-Hour Corridor Wall Fire Door Rating

13 hour\frac{1}{3}\,\text{hour} (20 minutes20\,\text{minutes})

97
New cards

Expansive Soil Index Criterion

Expansion Index greater than 2020 per ASTM D4829.

98
New cards

Habitable Space Minimum Room Dimension

No less than 7 ft7\,\text{ft} in any plan dimension (excluding kitchens).

99
New cards

Egress Door Maximum Threshold Height

12 in\frac{1}{2}\,\text{in} above the finished floor.

100
New cards

Group A-2 Automatic Sprinkler Threshold

Required when the fire area exceeds 5000 sq ft5000\,\text{sq ft}.