Construction Contracts, Specifications, and Execution Phase Issues

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/32

flashcard set

Earn XP

Description and Tags

Vocabulary flashcards covering construction contract types, legal principles, specifications, and project management issues during the execution phase.

Last updated 12:54 AM on 9/26/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

33 Terms

1
New cards

Acceptance Period

The specified timeframe during which a submitted bid remains valid and binding on the contractor, typically lasting 60 days60\text{ days} after closing, prior to which bids may be withdrawn or corrected.

2
New cards

Contract Agreement

The formal legal document binding the owner and contractor that integrates drawings, general and supplementary conditions, technical specifications, and addenda defining the scope of work.

3
New cards

Time Extensions

Contractual provisions allowing the original construction period duration to be extended for project delays that are not attributable to the contractor's fault.

4
New cards

Change Orders

Formal modifications to the original contract documents or project scope, governed by procedures established in the general conditions.

5
New cards

Changed Conditions

Contractor claims arising when actual physical site conditions encountered differ from those represented in contract documents or present unknown and unusual conditions.

6
New cards

Value Engineering

A mandatory incentive procedure encouraging contractors to propose innovative design or material modifications that lower costs while maintaining full required functionality.

7
New cards

Suspension, Delay, or Interruption

A directive from the owner or contracting officer temporarily halting all or part of the work, which may entitle the contractor to additional costs for demobilization, remobilization, and price escalation.

8
New cards

Liquidated Damages

An agreed monetary penalty paid by the contractor to the owner for each calendar day of unexcused delay beyond the completion date, assessed at 1/101/10 of 1%1\% per day up to a maximum cap of 10%10\% of the total contract price.

9
New cards

Progress Payment

Regular interim compensation paid to the contractor covering verified direct expenditures and fee markups for portions of work completed during a billing period.

10
New cards

Retainage

A specific percentage of earned progress payments withheld by the owner to incentivize the contractor to complete all contractual obligations satisfactorily.

11
New cards

Progress Reporting

The requirement for contractors to submit and continuously update construction progress charts comparing planned schedule metrics against actual completion percentage.

12
New cards

ACCEPTANCE AND FINAL PAYMENT

The formal project closeout completed through a joint inspection between the owner's representative and contractor, using a punch list of remaining deficiencies to finalize work and release final payments.

13
New cards

contract

An agreement of at least two parties (owner

and contractor) with purpose of creating

legal obligation between the parties and

capable of being enforced by court law.

Without a contract, technical requirements

lack enforceability

14
New cards

Elements of an Enforceable Contract

The core legal components necessary for legal enforceability: Offer, Acceptance, Consideration, Intent to Create Legal Relations, Legal Capacity, and Purpose, represented by OFFER+ACCEPTANCE+CONSIDERATION=CONTRACT\text{OFFER} + \text{ACCEPTANCE} + \text{CONSIDERATION} = \text{CONTRACT}.

15
New cards

Role of Engineers in Contracts

A dual capacity serving as project designer and contract administrator representing the owner, tasked with interpreting technical specifications, certifying payments, and determining contract compliance.

16
New cards

Lump Sum / Fixed Price Contract

A contract model where the contractor agrees to complete all construction tasks according to plans and specifications for a single predetermined total price.

17
New cards

Cost Plus a Fixed Fee (CPFF)

A cost-reimbursement contract where the owner pays all direct job costs for materials, labor, and equipment plus a negotiated fixed fee sum.

18
New cards

Cost Plus a Percentage of Cost (CPPC)

A contract type in which the contractor receives full reimbursement of direct construction costs plus a flat percentage fee based on those incurred costs.

19
New cards

Incentive Contract

A contract structured around a target cost estimate where the contractor retains a portion of cost savings if finished below target, or incurs a fee reduction if costs exceed target.

20
New cards

Design-Build Contract

A delivery method where the owner enters into a single contract with one party to handle both architectural/engineering design and construction execution.

21
New cards

Integrated Project Delivery (IPD)

A collaborative workflow contract aligning stakeholders, systems, and practices to optimize project performance and reduce overall risk across design and construction.

22
New cards

Time and Materials Contract

An agreement where compensation is based on actual labor time spent and materials used, suitable for projects with undefined or evolving scopes.

23
New cards

Unit Price Contract

A contract where total payment depends on multiplying fixed unit rates by the actual measured quantities of work items completed, common in heavy civil construction.

24
New cards

Guaranteed Maximum Price (GMP)

A cost-reimbursement contract capping total owner payments at a fixed maximum limit, requiring the contractor to absorb any cost overruns.

25
New cards

Legal Documents Section

The specification division containing administrative and bidding items such as advertisements for bids, instructions to bidders, agreement forms, and legal performance bond forms.

26
New cards

Condition Section

The specification division defining the legal contractual framework, outlining specific rights, responsibilities, and liabilities of all project participants.

27
New cards

Technical Description Section

The specification division defining specific materials, equipment standards, quality requirements, testing protocols, and construction methods across trade divisions.

28
New cards

Performance Specifications

Methodological specifications specifying required end outcomes and operational standards without prescribing exact materials or construction techniques.

29
New cards

Prescriptive Specifications

Methodological specifications detailing step-by-step instructions on materials, exact dimensions, and construction methods required.

30
New cards

Proprietary Specifications

Specifications requiring the exact use of specific manufacturer brand names, model numbers, or proprietary products.

31
New cards

Supplementary Specifications

Project-specific modifications or additions generated to amend standard or general specifications for unique conditions.

32
New cards

Substantial Completion

The point of progress, defined as 93%93\% completion, where the owner can occupy and utilize the facility while remaining minor works do not impair structural integrity.

33
New cards

Labor Cost Adjustment Formula

The contract formula for price adjustments due to mandatory minimum wage increases: Adjustment=A×B×CMinimum Wage\text{Adjustment} = \frac{A \times B \times C}{\text{Minimum Wage}}, where AA is the labor portion, BB is 70%70\% affected, and CC is the balance of remaining work.