What are the three investment decision rules for standalone projects, and how reliable is each?
NPV rule — always correct
IRR rule — can be incorrect
Payback rule — incorrect
What two topics does choosing between projects (3.2) cover?
Project selection with the NPV/IRR rules (mutually exclusive projects)
Project selection with resource constraints
Example: invest $250m today (t = 0) for $35m a year forever from t = 1. Write the NPV.
Inflows are a perpetuity, so PV0=C/r. Outflow is at t = 0, so it isn't discounted.


r = 5% → $450m
r = 10% → $100m
r = 14% → $0m
r = 15% → −$16.6m
r = 20% → −$75m
Whether NPV is positive depends on r.
NPV decision rule (for the $250m / $35m perpetuity project)
Accept if and only if NPV > 0.
Here: accept when r < 14%; reject when r > 14%.
Define the Internal Rate of Return (IRR)
The discount rate at which the NPV of a project is zero:
NPV=PV0(inflows)−PV0(outflows)=0
Find it by changing r until the NPV becomes zero.
Find the IRR of the $250m / $35m-a-year perpetuity project

What is the cost of capital?
The company’s discount rate – a measure of how expensive it is for the company to raise money from investors. The IRR is compared against it.
IRR decision rule
IRR > r (cost of capital) → accept
IRR < r (cost of capital) → reject
Show the IRR and NPV rules agreeing for the $250m / $35m project
r < 14%: NPV > 0 and IRR (14%) > r → both say accept
r > 14%: NPV < 0 and IRR (14%) < r → both say reject
When can the IRR rule disagree with the NPV rule? What should you use instead?
The IRR gives the same answer as NPV in many, not all, situations. Three pitfalls:
Delayed investments (early inflows, delayed outflows)
Multiple IRRs
Non-existent IRR
In these cases use the NPV rule.
Pitfall 1 set-up: publisher pays an author $1m now to write a book over 3 years; he gives up $0.5m income each year; r = 10%. What are the cash flows?
t = 0: +$1m (payment received)
t = 1, 2, 3: −$0.5m each (foregone income)
Foregone income is an opportunity cost, so it must be included in the NPV/IRR.
Pitfall 1 (delayed investment): NPV at 10%, IRR, and what each rule says

Why does the IRR rule fail for a delayed investment?
The cash flows are reversed: inflow first, outflows later (like borrowing). The NPV rises as r rises, so NPV > 0 only when r > IRR. The usual rule "accept if IRR > r" gets it the wrong way round.
What is the IRR on a graph of NPV against the discount rate?
The point where the NPV curve crosses the horizontal axis (NPV = 0).
Delayed investment: crosses at r = 23.38%. NPV < 0 at r = 10%; NPV > 0 to the right of the IRR.
Pitfall 2 (multiple IRRs): new deal = $0.55m at t = 0, −$0.5m at t = 1–3, +$1m at t = 4. Write the NPV.

Pitfall 2: what are the IRRs, and why is this a problem?
The NPV curve crosses the axis twice, giving two IRRs with conflicting recommendations at r = 10%:
IRR = 7.164% < 10% → reject
IRR = 33.673% > 10% → accept
The IRR rule can't decide, so use NPV. At 10% the NPV is about −$10k (the curve dips below zero between the IRRs), so reject.
What causes multiple IRRs?
Cash flows that change sign more than once (here +, −, −, −, +). Each change of sign can create another root of NPV = 0.
Pitfall 3 (non-existent IRR): the initial payment rises to $0.75m (other cash flows unchanged). What happens?
The NPV curve never crosses the horizontal axis → no solution to NPV = 0 → IRR doesn't exist
NPV is always positive → NPV rule says accept

State the payback rule
Only accept a project if its cash flows repay the initial investment within a pre-specified period.
$250m investment, $35m a year forever, payback period must be ≤ 5 years. Accept or reject?
Cash flows years 1–5 = $35m × 5 = $175m < $250m → reject. (The NPV rule accepts it whenever r < 14%, so payback gives the wrong answer.)
Four reasons the payback rule is less reliable than NPV
Ignores the time value of money
Ignores the project’s cost of capital
Ignores cash flows after the payback period
Relies on an ad-hoc decision criterion (the choice of playback period)
What are mutually exclusive projects?
Projects where investing in one necessarily excludes the other(s). In practice businesses must choose among them, rather than evaluating each independently.
Decision rules for mutually exclusive projects
Approach 1: NPV/IRR
NPV rule: choose the highest NPV
IRR rule: choose the highest IRR (can lead to the wrong decision)
Approach 2: Incremental IRR
IRR of the incremental cash flows (difference in cash flows). Can also lead to the wrong decision.
Four-store example (data): investment, year-1 CF, growth, cost of capital, NPV, IRR
Book: $300k · $63k · 3% · 8% → NPV $960k, IRR 24%
Coffee: $400k · $80k · 3% · 8% → NPV $1.2m, IRR 23%
Music: $400k · $104k · 0% · 8% → NPV $900k, IRR 26%
Electronics: $400k · $100k · 3% · 11% → NPV $850k, IRR 28%
In the four-store example, how are NPV and IRR calculated?

Four-store example: how do the NPV and IRR rules rank the projects?
NPV rule: Coffee ≽ Book ≽ Music ≽ Electronics
IRR rule: Electronics ≽ Music ≽ Book ≽ Coffee
They give opposite rankings. NPV is correct, so choose the Coffee shop.
Three differences between projects that the IRR ignores but NPV accounts for
Scale of initial investment
Timing of cash flows
Risk (cost of raising capital)
IRR problem 1 — differences in scale (Coffee vs Book)
The IRR shows the relative (%) increase in value and ignores the size of the investment. The NPV shows the absolute increase in value.
Book: higher IRR (24% vs 23%) but smaller ($300k vs $400k)
Coffee: higher NPV ($1.2m vs $960k) → choose Coffee
IRR problem 2 — differences in timing (Coffee vs Music)
Music: higher cash flows from the start ($104k, g = 0%) → IRR 26%, NPV $900k
Coffee: lower initial cash flows ($80k) but growing at g = 3% → IRR 23%, NPV $1.2m
NPV picks Coffee because it becomes better in the longer term.
IRR problem 3 — differences in risk (Coffee vs Electronics)
A project's IRR must be compared with its own cost of capital (risk).
Electronics: higher IRR (28%) but higher cost of capital (11% vs 8%) → NPV $850k
Coffee: IRR 23%, NPV $1.2m
NPV accounts for the different cost of capital for each project → choose Coffee
Projects L and S: give the cash flows and IRRs
L (4-year): −100 at t = 0, +200 at t = 4 → IRR 18.92%
S (1-year): −100 at t = 0, +125 at t = 1 → IRR 25%
L − S: 0, −125, 0, 0, +200 → incremental IRR 16.96%
Write the NPV equations for L, S and L − S

What is the incremental IRR, and how is it calculated?
The IRR of the difference in cash flows between two projects: a hypothetical project (L − S).
Subtract S's cash flows from L's in each period, then find the r where that NPV = 0.
Incremental IRR decision rule (L vs S, incremental IRR 16.96%)
Incremental IRR > r → accept L − S → choose L (L ≽ S)
Incremental IRR < r → reject L − S → choose S (L ≼ S)
So choose L if r < 16.96%, and S if r > 16.96%.
What is the crossover point?
The discount rate where the NPV curves of two projects intersect (equal NPVs). It equals the incremental IRR: 16.96% for L vs S.
Each project's own IRR is where its curve crosses the axis (L 18.92%, S 25%).
Why is the incremental IRR rule incomplete? Give the example.
It doesn't tell you whether the projects have a positive or negative NPV.
For r > 25%, both L and S have negative NPVs.
At r = 30%, the rule picks S, accepting a negative-NPV project. You should reject both.
So again, just use the NPV rule.
What is a resource constraint in project selection?
In reality, you can't always raise new capital. A limited resource (e.g. warehouse space or budget) restricts which projects can be taken together.
Warehouse example: P1 NPV £100m, 100% of space; P2 £75m, 60%; P3 £75m, 40%. Which should you choose?
P2 + P3: together they use 100% of the warehouse for a combined NPV of £150m, vs £100m for P1.
Picking the highest single NPV (P1) is suboptimal because it uses all the space.
Define the profitability index
PI = NPV / units of the constrained resource used
The resource can be space or the investment budget (how much there is to spend).
Warehouse example: calculate each project's profitability index
P1: 100 / 100 = 1
P2: 75 / 60 = 1.25
P3: 75 / 40 = 1.875
P3 gives the most value per unit of warehouse space.
Profitability index decision rule
Choose projects sequentially from the highest PI down until the constrained resource is exhausted.
Warehouse: P3 (1.875) then P2 (1.25) = 100% used → choose P2 + P3.
When does the profitability index rule not work well?
When the chosen projects don't exhaust the available resource
When there are multiple resource constraints (use linear programming instead)