Performance Domains
7 total: governance, scope, schedule, finance, stakeholders, risk, resources
*group of related processes that deliver project value
all interactive, related, interdependent
work together as one integrated system to help achieve project results
Governance
framework, functions, processes used to guide project decisions and activities. Goal to optimize project value delivery*. Helps integrate all domains
other six domains combined
can be tailored lightweight for adaptive projects, moderate for hybrid, and comprehensive for large predictive projects
structured governance often includes sponsor, PMO leader, governance board and PM
predictive projects may need stronger governance tools such as escalation paths and investment controls
effective governance needs clear metrics, warning signals and feedback mechanisms to support better decisions
**Leading indicators show early warning signs or trends before problems happen
**Lagging indicators show what already happened on the project
ex: completed deliverables, schedule variance, cost variance, resources used
Leading indicators
show early warning signs or trends before problems happen
Lagging Indicators
show what already happened on the project
Scope
defines what the project will accomplish
**should only include required work
**also includes quality, meaning project must meet both scope requirements and quality requirements
Product Scope
Describes the features, functions, and req of product, service, or result
**explains what the product does, NOT the work needed to create it
Project Scope
Describes work needed to DELIVER the product, service, or result
what project team must do to create/deliver product
Quality as a feature
means quality requirements are part of the scope, such as speed, security, reliability, ease of use
Value Breakdown Structure (VBS)
organized deliverables by the value they provide, helping the team prioritize the highest value work first
Schedule Management
work needed to plan, develop, monitor, control, project schedule
can be created at different level depending on project approach or org needs
rolling wave planning allows the team to plan high level work first, then add more details as project progresses
project schedule includes linked activities, planned dates, durations, milestones, dependencies, resources
Finance
finance performance domain focuses on how project money and financial resources are planned, used, managed, and controlled
it covers project costs, funding, budgeting, financing, value*
financial info help team compare actual performance against plan
value maximization
project should not only control costs but also deliver greatest possible value
funding
explains where the project money comes from, like internal budgets, customer contracts, grants, crowdfunding
Financial constraints
limits to how project money can be used - budget limits, funding rules, time restrictions
*capex is money used for long term assets
Opex is money used for ongoing business ops
CapEX
money used for long term assets
capitol expenditure
OpEX
is money used for ongoing business ops
operation expense
Stakeholder performance domain
focuses on identifying, engaging, analyzing, monitoring stakeholders throughout project
include sponsor, team members, customers, anyone impacted by project
can be internal or external to org
their power, interest, influence, support may change as project progresses
domain connected to communications management
Stakeholder engagement
identifying stakeholders, understanding needs, managing expectations, keeping them involved
Sponsor Engagement
critical* because sponsor supports the project, provides resources, approves key docs, help align with project strategy
Resources performance domain
focuses on how project team plans, manages, uses resources
resources include people and non people resources
PM is responsible for building, managing, motivating, encouraging/empowering team
resource manager has authority or one or more resource / helps to align resources
human resources are the project team members who have roles and respon to meet project work*
Risk performance domain
focuses on managing uncertainty and protecting project from disruption
goal is to anticipate, prepare for, respond to risks
should be proactive, not reactive
Classification
1) unknown - known (hidden fact) - knowledge exists in community but not with entity working endeavor
2) unknown- unknown (emergent risk) - knowledge doesn’t exist within sphere or influence
3) known - known (facts and requirements) - managed a part of scope, NOT risk
4) known - unknown (classic risk) - knowledge to identify probability and impact
Risk threshold
acceptable amount of variation around project objective, such as allowing cost to vary but 5 to 10 percent
Risk exposure
total potential impact of all risks on the project at a certain point in time
During planning, the project manager identified a specific risk and documented a response for it. Months later, that exact risk occurs.
What should the project manager do first?
Correct answer: Implement the response that was already planned for this risk.
Why it is correct: Because the risk was identified during planning and a response was already prepared, proactive risk management means carrying out that planned response now that the risk has occurred.
Early in a project, much of the later work is not yet well understood, but the project manager is trying to build a fully detailed schedule for the entire project right now. This is causing delays and constant rework of the schedule.
What should the project manager do?
Correct answer: Detail the near-term work now and elaborate the later work as it becomes clearer.
Why it is correct: Rolling wave planning lets the team plan high-level work first and add more detail as the project progresses. Detailing the near-term work now and elaborating later work as it becomes clearer avoids the constant rework described.