Vocabulary flashcards covering project planning and scheduling, contract claims, variations, time extensions, damages, site documentation, and measurement methods.

22 Terms

1
New cards

Gantt Chart

A visual schedule that displays activities against time, showing duration, start dates, finish dates, and overlaps so planned and actual progress can be monitored.

2
New cards

S-Curve

A graph displaying cumulative project progress or expenditure over time, comparing planned and actual curves to identify progress differences or spending deviations.

3
New cards

Physical S-Curve

An S-Curve measured in physical percentage (%\%) based on site progress, site inspection, and completed work activities to track physical progress and determine if activities are on, ahead of, or behind schedule.

4
New cards

Financial S-Curve

An S-Curve measured in monetary value (RM\text{RM}) based on financial records, progress payments, and expenditure to monitor whether spending aligns with the planned budget and financial schedule.

5
New cards

Progress Claim

A formal request for approval to apply for payment for work completed in a construction project, serving to request payment and provide evidence of work progress.

6
New cards

Progress Claim Verification

The process by which the Site Supervisor / Superintending Officer (SO) checks actual work progress against the contractor's claim to reduce payment disputes by verifying contract terms, specifications, quantity, and quality.

7
New cards

Extension of Time (EOT) Procedures

Contractual procedures triggered when a delay becomes apparent and the SO issues a warning, leading either to Path A (evaluating qualifying reasons for approval) or Path B (maintaining existing completion obligations when reasons are not accepted).

8
New cards

Certificate of Non-Completion (CNC)

A document prepared by the Superintending Officer (SO) for approval/signature when the contractor fails to complete the work within the specified time.

9
New cards

Liquidated and Ascertained Damages (LAD)

Pre-determined damages imposed on the contractor following contractual procedures when delay reasons are not accepted as qualifying under the contract.

10
New cards

Variation Order (VO)

An alteration to the scope of work in a construction contract in the form of an addition, omission, or substitution from the original scope.

11
New cards

Four Types of Variations

The categories of contract variations comprising alteration to the design, alteration to quantities, alteration to quality, and alteration to working conditions.

12
New cards

Valuation of VO (PWD 203A/2007, Clause 25)

The evaluation of client-requested modifications by the SO using existing contract rates, or using the Daywork Schedule filled in at contract signing plus 15%15\% profit if work cannot be physically measured or assessed.

13
New cards

Daywork Payment Supporting Documents

Four mandatory records required to support payment under the Daywork Schedule plus 15%15\% profit: (1) Vouchers, (2) Receipts, (3) Pay book, and (4) Verified daily daywork sheets recording labour, material, and equipment.

14
New cards

Site Diary

A daily site record covering weather conditions, number of workers, work activities and progress, materials delivered to site, machinery and equipment used, and site problems, accidents, and instructions.

15
New cards

Progress Report

A weekly or monthly documentation used to monitor overall project progress by recording work progress, delays, problems, and project status.

16
New cards

Bill of Quantities (BQ)

A document serving four key functions: cost estimation, tender preparation, progress payment assessment, and valuation of variation works.

17
New cards

Request for Information (RFI)

A document submitted to obtain required information before proceeding with work, which may affect project cost.

18
New cards

Request for Clarification (RFC)

A communication made to request clarification before proceeding with work, which usually has no direct cost implication.

19
New cards

MySMM

The Standard Method of Measurement published by the Institution of Surveyors Malaysia (ISM) for building work.

20
New cards

CIDB SMM

The Standard Method of Measurement published by the Construction Industry Development Board (CIDB) Malaysia for civil engineering work.

21
New cards

Risk Mitigation

Actions taken before and during construction to reduce project risks and minimize their impacts, incurring the cost of preventive measures.

22
New cards

Project Acceleration

Actions implemented when project time needs to be shortened to complete the project earlier, requiring additional costs for labour, equipment, and overtime.