Activity list

Master record of each unit of work: ID, verb-noun description, predecessors/successors, resources, and assumptions/constraints; each activity is sized at roughly 8–80 hours of effort

2
New cards

Work package vs. activity

Lowest WBS level describing what is delivered vs. the decomposed unit describing how the work gets done

3
New cards

Finish-to-Start (FS)

B can't begin until A ends; the most common dependency (e.g., testing after coding)

4
New cards

Start-to-Start (SS)

B can't begin until A begins (e.g., documentation once drafting begins)

5
New cards

Finish-to-Finish (FF)

B can't end until A ends (e.g., quality review closes after inspections)

6
New cards

Start-to-Finish (SF)

B can't end until A begins; rare (e.g., night shift ends when day shift starts)

7
New cards

Mandatory dependency

Hard logic; cannot be changed

8
New cards

Discretionary dependency

Soft logic based on best practice; can be changed, and is the only kind that allows overlapping activities

9
New cards

External dependency

Relationship driven by something outside the team's control (e.g., permits); carries risk

10
New cards

Precedence Diagramming Method (PDM)

Network diagram format where activities are nodes; each node shows duration, ES, EF, LS, LF, and float

11
New cards

Analogous duration estimate

Based on similar past projects; fast and cheap but least accurate, so suited to early stages

12
New cards

Parametric duration estimate

Statistical rate applied to quantity (e.g., 100 m of cable = 2 days, so 500 m = 10 days)

13
New cards

Three-point (PERT) estimate

Expected time = (O + 4M + P) ÷ 6; standard deviation = (P − O) ÷ 6

14
New cards

Duration estimate: expert judgment

Use experienced people to validate other estimates or when the work is new

15
New cards

Forward pass

Left-to-right calculation (EF = ES + duration) that yields the earliest project finish

16
New cards

Backward pass

Right-to-left calculation (LS = LF − duration) that yields the latest dates that don't delay the project

17
New cards

Total float

LS − ES (or LF − EF); slack shared along an entire path

18
New cards

Free float

ES of the successor − EF of the activity; slack belonging to one activity alone

19
New cards

Critical path

Longest path through the network; zero slack, so any delay pushes the end date

20
New cards

Crashing

Compressing the schedule by adding resources or overtime; always raises cost; main risk is diminishing returns; do the cheapest cost-per-day first

21
New cards

Fast-tracking

Compressing the schedule by overlapping activities planned in sequence; no direct cost increase; main risk is rework

22
New cards

Which activities get schedule compression?

Critical-path activities only

23
New cards

Milestone

Zero-duration event marking a point in the project (e.g., "Go-Live")

24
New cards

Gantt chart

Most common schedule format; bars plotted on a timeline

25
New cards

Schedule baseline

Approved schedule; altered only via formal change control; basis for SV and SPI