Activity list
Master record of each unit of work: ID, verb-noun description, predecessors/successors, resources, and assumptions/constraints; each activity is sized at roughly 8–80 hours of effort
Work package vs. activity
Lowest WBS level describing what is delivered vs. the decomposed unit describing how the work gets done
Finish-to-Start (FS)
B can't begin until A ends; the most common dependency (e.g., testing after coding)
Start-to-Start (SS)
B can't begin until A begins (e.g., documentation once drafting begins)
Finish-to-Finish (FF)
B can't end until A ends (e.g., quality review closes after inspections)
Start-to-Finish (SF)
B can't end until A begins; rare (e.g., night shift ends when day shift starts)
Mandatory dependency
Hard logic; cannot be changed
Discretionary dependency
Soft logic based on best practice; can be changed, and is the only kind that allows overlapping activities
External dependency
Relationship driven by something outside the team's control (e.g., permits); carries risk
Precedence Diagramming Method (PDM)
Network diagram format where activities are nodes; each node shows duration, ES, EF, LS, LF, and float
Analogous duration estimate
Based on similar past projects; fast and cheap but least accurate, so suited to early stages
Parametric duration estimate
Statistical rate applied to quantity (e.g., 100 m of cable = 2 days, so 500 m = 10 days)
Three-point (PERT) estimate
Expected time = (O + 4M + P) ÷ 6; standard deviation = (P − O) ÷ 6
Duration estimate: expert judgment
Use experienced people to validate other estimates or when the work is new
Forward pass
Left-to-right calculation (EF = ES + duration) that yields the earliest project finish
Backward pass
Right-to-left calculation (LS = LF − duration) that yields the latest dates that don't delay the project
Total float
LS − ES (or LF − EF); slack shared along an entire path
Free float
ES of the successor − EF of the activity; slack belonging to one activity alone
Critical path
Longest path through the network; zero slack, so any delay pushes the end date
Crashing
Compressing the schedule by adding resources or overtime; always raises cost; main risk is diminishing returns; do the cheapest cost-per-day first
Fast-tracking
Compressing the schedule by overlapping activities planned in sequence; no direct cost increase; main risk is rework
Which activities get schedule compression?
Critical-path activities only
Milestone
Zero-duration event marking a point in the project (e.g., "Go-Live")
Gantt chart
Most common schedule format; bars plotted on a timeline
Schedule baseline
Approved schedule; altered only via formal change control; basis for SV and SPI