178 Terms

1
New cards

Supply chain visibility, simultaneous resource consideration, and resource utilization characterize _____.

Supply chain planning

2
New cards

Knowing inventory location/status, identifying exceptions, and reducing uncertainty is called _____.

Supply chain visibility

3
New cards

Select all factors balanced through simultaneous resource consideration. (4) A) Demand B) Resource utilization C) Capacity D) Inventory turnover E) Material requirements F) Constraints G) Forecast accuracy

Demand

4
New cards

Capacity

5
New cards

Material requirements

6
New cards

Constraints

7
New cards

Select all supply chain assets jointly balanced. (4) A) Production B) Customer orders C) Raw materials D) Transportation E) Financial capital F) Storage G) Demand forecasts

Production

8
New cards

Raw materials

9
New cards

Transportation

10
New cards

Storage

11
New cards

Select all resource utilization considerations. (4) A) Production run lengths B) Capacity forecasting C) Plant/equipment resources D) Setups/changeovers E) Material sourcing contracts F) Complete trade-off assessment G) Customer segmentation

Production run lengths

12
New cards

Plant and equipment resources

13
New cards

Setups and changeovers

14
New cards

Complete trade-off assessment

15
New cards

Select all supply chain planning objectives. (4) A) Consistent internal forecasts B) Minimize all inventory regardless of demand C) Balance internal supply and demand D) Share demand/inventory information with partners E) Optimize marketing budgets F) Consistent inventory availability plans across the supply chain G) Replace forecasting with customer orders

Consistent forecasts within the firm

16
New cards

Balance supply and demand within the firm

17
New cards

Exchange demand and inventory availability information with partners

18
New cards

Develop consistent inventory availability plans throughout the supply chain

19
New cards

Forecasting unit sales by geography and product is called _____.

Demand planning

20
New cards

Developing a manufacturing plan based on resource availability is called _____.

Production planning

21
New cards

Select all production planning strategies. (3) A) Make-to-order B) Ship-to-order C) Assemble-to-order D) Plan-to-stock E) Make-to-stock F) Forecast-to-order

Make-to-order

22
New cards

Assemble-to-order

23
New cards

Make-to-stock

24
New cards

Coordinating movement/storage demand, vehicle availability, and transportation/warehousing expenses is called _____.

Logistics planning

25
New cards

Coordinating demand with the ability to produce and ship products to consumers is called _____.

Inventory deployment

26
New cards

Internal collaboration between operations and customer-facing functions to meet demand within resource constraints is _____.

Sales and Operations Planning (S&OP)

27
New cards

Select all objectives of S&OP. (5) A) Develop marketing/sales plans B) Assess material and resource availability C) Eliminate customer demand variability D) Prioritize production based on demand/resources E) Evaluate risks and thresholds F) Monitor performance and address variances G) Guarantee supplier capacity H) Replace the operating budget

Develop marketing and sales plans

28
New cards

Assess material supply and resource availability

29
New cards

Prioritize production

30
New cards

Evaluate risks and manage risk thresholds

31
New cards

Monitor plan performance and address variances

32
New cards

If you fail to plan, you plan to _____.

Fail

33
New cards

Which formula calculates period logistics requirements? A) Forecast + Orders − Promotions − Inventory + Receipts B) Forecast + Orders + Promotions − Inventory − Planned receipts C) Forecast − Orders + Promotions + Inventory − Receipts D) Forecast + Orders − Promotions + Inventory − Receipts

Forecast + Customer orders + Promotions − Inventory on hand − Planned receipts

34
New cards

Select all inputs to the unconstrained marketing plan. (8) A) Orders on hand B) Current customers C) Production capacity D) New customers E) Competition F) Storage capacity G) Margin analysis H) New products I) Transportation availability J) Pricing K) Economy L) Material requirements

Orders on hand

35
New cards

Current customers

36
New cards

New customers

37
New cards

Competition

38
New cards

Margin analysis

39
New cards

New products

40
New cards

Pricing

41
New cards

Economy

42
New cards

Select all resource planning inputs. (7) A) Inventory B) Replenishment C) Customer segmentation D) Capacity constraints E) Mix constraints F) Competitive positioning G) Material H) Transportation I) Product pricing J) Storage

Inventory

43
New cards

Replenishment

44
New cards

Capacity constraints

45
New cards

Mix constraints

46
New cards

Material

47
New cards

Transportation

48
New cards

Storage

49
New cards

Select all functional areas providing S&OP input. (4) A) Finance B) Engineering C) Marketing D) Sales E) Legal F) Operations G) Human resources

Finance

50
New cards

Marketing

51
New cards

Sales

52
New cards

Operations

53
New cards

The S&OP process begins by developing _____.

Functional input

54
New cards

After developing functional input, S&OP creates a _____.

Baseline demand forecast

55
New cards

Select all resources assessed for availability during S&OP. (5) A) Inventory B) Market share C) Capacities D) Labor E) Profit margins F) Transportation G) Storage H) Customer segmentation

Inventory

56
New cards

Capacities

57
New cards

Labor

58
New cards

Transportation

59
New cards

Storage

60
New cards

After assessing resource availability, S&OP identifies _____ and assesses _____.

Alternatives

61
New cards

Trade-offs

62
New cards

S&OP alternatives must be reviewed for their _____ implications.

Financial

63
New cards

Executives review S&OP alternatives to agree on a _____ plan.

Common

64
New cards

After executives agree on the S&OP plan, the next step is _____.

Execute the plan

65
New cards

The final S&OP process consideration is to _____.

Review results of the plan

66
New cards

How often should S&OP be executed? A) Every two weeks B) Quarterly C) Monthly D) Every six months

Monthly

67
New cards

Successful S&OP requires organizational commitment to high _____ accuracy.

Forecast

68
New cards

What planning horizon does S&OP focus on? A) 6–12 months B) 3–9 months C) 6–18 months D) 3–12 months

3–12 months

69
New cards

S&OP integrates organizational actions into _____ plan.

One

70
New cards

S&OP measures _____-to-_____ supply chain performance.

End-to-end

71
New cards

Select all practices that help S&OP work. (6) A) Clear process ownership B) Senior management decisions C) Separate plans for every department D) Monthly execution E) High forecast accuracy F) Compare S&OP forecast with operating plan/budget G) End-to-end performance measurement H) Avoid integrated planning

Clear process ownership

72
New cards

Senior management decision making

73
New cards

Monthly execution

74
New cards

High forecast accuracy

75
New cards

Compare S&OP forecast with operating plan or budget

76
New cards

End-to-end performance measurement

77
New cards

Select all S&OP external evaluation priorities. (2) A) Profitable customers B) Warehouse utilization C) Product mix priorities D) Supplier payment schedules E) Production run lengths

Profitable customers

78
New cards

Product mix priorities

79
New cards

Evaluating operations-focused/customer-facing measurements and external trends is called _____.

External evaluation

80
New cards

Select all external trends influencing strategic plans. (4) A) Technology changes B) Payroll schedules C) Customer demand trends D) Resource availability changes E) Equipment depreciation F) Competitive environment changes

Technology changes

81
New cards

Customer demand trends

82
New cards

Resource availability changes

83
New cards

Competitive environment changes

84
New cards

Select all benefits of S&OP. (5) A) Improved forecast accuracy B) Reduced supplier lead times C) Better customer service/perfect orders D) Shorter cash-to-case cycle E) Higher gross profit margins F) Reduced inventory/better capacity utilization G) Guaranteed transportation capacity H) Elimination of demand uncertainty

Increased forecast accuracy

85
New cards

Improved customer service and perfect order performance

86
New cards

Reduced cash-to-case cycle time

87
New cards

Enhanced gross profit margin

88
New cards

Reduced inventory and improved capacity utilization

89
New cards

Select all barriers to effective S&OP. (4) A) Misaligned performance measures B) Detailed demand forecasts C) Lack of demand-supply engagement D) Ignoring demand factors/supply constraints E) Insufficient executive commitment F) Cross-functional collaboration G) Clear accountability

Misaligned performance measurement systems

90
New cards

Lack of structured demand-supply engagement

91
New cards

Failure to incorporate key demand factors and supply constraints

92
New cards

Insufficient executive/senior management commitment

93
New cards

A planning system focused on components/items across networks of plants, distribution centers, and customers is _____.

Advanced Planning and Scheduling (APS)

94
New cards

APS requires network links representing _____.

Lead times

95
New cards

Select all APS system components. (4) A) Resource optimization B) Capacity planning C) Demand management D) Inventory deployment E) Resource allocation F) Production scheduling G) Resource management H) Logistics planning

Resource optimization

96
New cards

Demand management

97
New cards

Resource allocation

98
New cards

Resource management

99
New cards

Select all APS resource allocation methods. (2) A) Available-to-promise (ATP) B) Make-to-stock (MTS) C) Capable-to-promise (CTP) D) Materials requirements planning (MRP) E) Assemble-to-order (ATO)

Available-to-promise (ATP)

100
New cards

Capable-to-promise (CTP)