order of magnitude
cost estimation level based on I/O diagrams and BFDs and uses experience and published data to produce a -50%/+100% estimate
study
cost estimation level based on PFDs, bulk materials list, and preliminary equipment capacities that produces a -25%/+40% estimate
direct costs
costs associated with equipment, materials, and installation labor
indirect costs
costs associated with shipping/freight, overhead (paying project manager and finance people), and engineering (design building plans and architecture)
fixed capital investment
direct costs + indirect costs + contingency and cont
working capital
things like spare parts, inventory, chemicals, and catalysts that can quickly be converted into money
total capital investment
fixed capital investment + working capital
by process module/Guthrie-Alrich method
way to organize capital cost estimates that uses cost correlations to obtain purchased equipment cost (Cp) and estimate other costs, used for larger projects with at least three major unit operations; obtain major costs and use factors for other costs
by work classification/retrofit method
way to organize capital cost estimates that is used for small piping modifications, controls projects, equipment replacement projects; use RoT for piping and instrumentation, and factors for other equipment costs
order of magnitude cost estimate
use 0.7 power law factor or Lang factor method that multiplies the purchase price of major equipment based on plant type (for greenfield plants)
2.5 or 4.0
Fbm for equipment in retrofit project that is equipment dominated or controls dominated
operating costs
recurring costs associated with keeping a facility in operation and producing product
fixed costs
costs that are independent of production level, like insurance
variable costs
costs that are dependent on production level, like raw materials