Project Management Processes (PMBOK Focus)

0.0(0)
Studied by 0 people
call kaiCall Kai
Locked
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/50

flashcard set

Earn XP

Description and Tags

Vocabulary flashcards covering core project management concepts, contract types, ITTO tools, schedule and cost estimation formulas, risk characteristics, team leadership models, and monitoring techniques based on lecture notes.

Last updated 1:41 AM on 8/29/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

51 Terms

1
New cards

Initiate Project or Phase

The process of developing a document that formally authorizes a project or a phase, outlines project objectives, and defines the authority of the project manager.

2
New cards

Business Case

Necessary information that determines whether or not a project is worth the required investment based on business needs, market demand, or legal requirements.

3
New cards

Project Benefits Management Plan

A document describing the main benefits a project will produce once completed and detailing how those benefits will be measured.

4
New cards

RACI Chart

A common Responsibility Assignment Matrix (RAM) that defines roles as Responsible (doing work), Accountable (ensuring work is done), Consulted (providing input), and Informed (receiving updates).

5
New cards

Project Canvas

A visual tool used to outline and plan key project components, providing a quick, high-level overview for project managers and stakeholders.

6
New cards

Project Charter

An approved document signed by senior management that formally authorizes the existence of a project and gives the project manager authority to commit organizational resources.

7
New cards

Assumption Log

A project document used to record all assumptions (things perceived to be true) and potential constraints throughout the project life cycle.

8
New cards

Salience Model

A stakeholder categorization methodology that evaluates stakeholders based on their Power (authority level), Urgency (need for immediate attention), and Legitimacy (appropriateness of involvement).

9
New cards

Stakeholder Register

A project document that records identification details, assessment info, and classifications for project stakeholders.

10
New cards

Project Management Plan

The integrated, approved master document that defines how the project will be executed, monitored, controlled, and closed.

11
New cards

Fixed-Price Contract

A contract type where the price is agreed upon upfront for a clearly defined scope, placing cost risk primarily on the seller.

12
New cards

Cost-Reimbursable Contract

A contract type where the buyer pays the seller's actual costs plus a fee or profit, carrying higher cost risk for the buyer.

13
New cards

Time and Materials Contract

A hybrid contract type where the buyer pays for labor hours and materials used, offering flexibility for consulting or service work.

14
New cards

Target-Cost Contract

A contract type where buyer and seller agree on a target cost and share any cost savings or overruns based on a predetermined ratio.

15
New cards

Make-or-Buy Analysis

A technique used to evaluate whether specific work should be completed internally by the project team or purchased from external sellers.

16
New cards

Requirements Traceability Matrix

A grid that links product requirements to deliverables and project objectives, ensuring each requirement is fulfilled by project completion.

17
New cards

Project Scope Statement

A detailed document describing the project scope, product scope, major deliverables, acceptance criteria, assumptions, constraints, and explicit project exclusions.

18
New cards

Work Breakdown Structure (WBS)

A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish project objectives.

19
New cards

Work Packages

The lowest-level components of a Work Breakdown Structure (WBS) where cost and duration can be estimated and managed.

20
New cards

Precedence Diagramming Method (PDM)

A schedule construction technique where activities are represented by nodes and graphically linked by logical relationships.

21
New cards

Mandatory Dependencies

Schedule dependencies required by the nature of the work itself, also referred to as hard logic.

22
New cards

Discretionary Dependencies

Schedule dependencies established based on preference, best practices, or experience, also referred to as soft logic.

23
New cards

Analogous Estimating

An estimating technique that uses actual values or historical data from similar previous projects; fast and inexpensive but less accurate.

24
New cards

Parametric Estimating

An estimating technique that uses statistical relationships between historical data and variables (such as unit rates or square footage) to calculate effort or cost.

25
New cards

Bottom-Up Estimating

An estimating method that calculates cost or duration for individual work components and aggregates them upward; provides high accuracy but requires significant time.

26
New cards

PERT Beta Distribution

A weighted average formula used in three-point estimating that gives more weight to the most likely value: Beta=O+4M+P6\text{Beta} = \frac{O + 4M + P}{6}.

27
New cards

PERT Standard Deviation

A formula that measures variability or uncertainty in a three-point estimate: SD=PO6\text{SD} = \frac{P - O}{6}.

28
New cards

Crashing

A schedule compression technique that adds resources to activities on the critical path to shorten duration, usually increasing overall cost.

29
New cards

Fast Tracking

A schedule compression technique where activities normally performed in sequence are performed in parallel, usually increasing project risk.

30
New cards

Cost Baseline

The approved version of the time-phased budget, excluding management reserves, used as a reference to compare actual expenditure against.

31
New cards

Contingency Reserve

Budget or time allocated within the schedule or cost baseline to address identified risks with active response plans.

32
New cards

Management Reserve

Budget set aside outside the cost baseline to cover unforeseen, unknown-unknown risks, controlled directly by senior management.

33
New cards

Communication Channels Formula

A mathematical formula used to determine potential interaction channels among stakeholders: N(N1)2\frac{N(N - 1)}{2}, where NN represents the number of stakeholders.

34
New cards

Interactive Communication

Real-time, multidirectional exchange of information between two or more parties, such as meetings, phone calls, or video conferences.

35
New cards

Push Communication

Information sent directly to specific recipients without real-time interaction, such as emails, memos, status reports, and press releases.

36
New cards

Pull Communication

Information stored in a central repository for recipients to access at their own discretion, such as intranet sites or web portals.

37
New cards

Team Charter

A document that establishes clear team values, communication guidelines, decision-making rules, and operating agreements for behavior.

38
New cards

COCOMO

Constructive Cost Model; an algorithmic model used to estimate software development effort, duration, and resource requirements based on project size.

39
New cards

Individual Project Risk

An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.

40
New cards

Overall Project Risk

The combined effect of all individual project risks and systemic uncertainty on the project as a whole.

41
New cards

Risk Dormancy

A risk characteristic measuring the length of time between a risk occurrence and the discovery of its impact.

42
New cards

Risk Proximity

A risk characteristic measuring how soon a risk may impact project objectives.

43
New cards

Explicit Knowledge

Knowledge that can be easily documented, codified, stored, and shared in formats like manuals, databases, and templates.

44
New cards

Tacit Knowledge

Personal knowledge, experience, insights, and skills that are difficult to articulate or codify, usually transferred through collaboration and conversations.

45
New cards

Six Thinking Hats

A parallel problem-solving and decision-making technique that categorizes thinking into six perspectives: Blue (Process), White (Facts), Red (Emotions), Black (Risks), Yellow (Benefits), and Green (Creativity).

46
New cards

Tuckman Ladder

A model describing team development stages: Forming, Storming, Norming, Performing, and Adjourning.

47
New cards

Student Syndrome

A common schedule behavior where individuals delay starting a task until the last possible moment before a deadline.

48
New cards

Parkinson's Law

A schedule concept stating that work expands to fill the total time allocated for its completion.

49
New cards

To-Complete Performance Index (TCPI)

A calculated measure of cost efficiency required on remaining work to meet a specified budget goal: TCPI=BACEVBACAC\text{TCPI} = \frac{\text{BAC} - \text{EV}}{\text{BAC} - \text{AC}}.

50
New cards

Rule of Seven

A quality rule stating that if seven consecutive data points in a control chart fall on one side of the mean, the process should be investigated as non-random.

51
New cards

Validate Scope

The process of obtaining formal sign-off and acceptance from the customer or sponsor for completed project deliverables.