New cards

U009 / Practice 1 Q9 / When a security standard conflicts with a business objective, the situation should be resolved by: A. changing the security standar B. changing the business objectiv C. performing a risk analysi D. authorizing a risk acceptanc

Source answer: C. performing a risk analysi | Source explanation: Conflicts of this type should be based on a risk analysis of the costs and benefits of allowing or disallowing an exception to the standard. It is highly improbable that a business objective could be changed to accommodate a security standard, while risk acceptance* is a process that derives from the risk analysis.

2
New cards

U060 / Practice 1 Q172 / Who should drive the risk analysis for an organization? A. Senior management B. Security manager C. Quality manager D. Legal department

Source answer: B. Security manager | Source explanation: Although senior management should support and sponsor a risk analysis, the know-how and the management of the project will be with the security department. Quality management and the legal department will contribute to the project.

3
New cards

U062 / Practice 1 Q178; Practice 2 Q144 / Which of the following BEST describes an information security manager's role in a multidisciplinary team that will address a new regulatory requirement regarding operational risk? A. Ensure that all IT risks are identified B. Evaluate the impact of information security risks C. Demonstrate that IT mitigating controls are in place D. Suggest new IT controls to mitigate operational risk

Source answer: B. Evaluate the impact of information security risks | Source explanation: The job of the information security officer on such a team is to assess the risks to the business operation. Choice A is incorrect because information security is not limited to IT issues. Choice C is incorrect because at the time a team is formed to assess risk, it is premature to assume that any demonstration of IT controls will mitigate business operations risk. Choice D is incorrect because it is premature at the time of the formation of the team to assume that any suggestion of new IT controls will mitigate business operational risk.

4
New cards

U066 / Practice 1 Q191 / Acceptable risk is achieved when: A. residual risk is minimize B. transferred risk is minimize C. control risk is minimize D. inherent risk is minimize

REVIEW NOTE: CONCEPT CAUTION: Source key A. The target is residual risk within approved tolerance, not the smallest technically possible risk at any cost. | Source answer: A. residual risk is minimize | Source explanation: Residual risk is the risk that remains after putting into place an effective risk management program; therefore, acceptable risk is achieved when this amount is minimized. Transferred risk is risk that has been assumed by a third party and may not necessarily be equal to the minimal form of residual risk. Control risk is the risk that controls may not prevent/detect an incident with a measure of control effectiveness. Inherent risk cannot be minimized.

5
New cards

U067 / Practice 1 Q196 / After completing a full IT risk assessment, who can BEST decide which mitigating controls should be implemented? A. Senior management B. Business manager C. IT audit manager D. Information security officer (ISO)

Source answer: B. Business manager | Source explanation: The business manager will be in the best position, based on the risk assessment and mitigation proposals. to decide which controls should/could be implemented, in line with the business strategy and with budget. Senior management will have to ensure that the business manager has a clear understanding of the risk assessed but in no case will be in a position to decide on specific controls. The IT audit manager will take part in the process to identify threats and vulnerabilities, and to make recommendations for mitigations. The information security officer (ISO) could make some decisions regarding implementation of controls. However, the business manager will have a broader business view and full control over the budget and, therefore, will be in a better position to make strategic decisions.

6
New cards

U068 / Practice 1 Q201; Practice 2 Q155 / Before conducting a formal risk assessment of an organization's information resources, an information security manager should FIRST: A. map the major threats to business objective B. review available sources of risk informatio C. identify the value of the critical asset D. determine the financial impact if threats materializ

Source answer: A. map the major threats to business objective | Source explanation: Risk mapping or a macro assessment of the major threats to the organization is a simple first step before performing a risk assessment. Compiling all available sources of risk information is part of the risk assessment. Choices C and D are also components of the risk assessment process, which are performed subsequent to the threats-business mapping.

7
New cards

U070 / Practice 1 Q207 / The PRIMARY purpose of using risk analysis within a security program is to: A. justify the security expenditur B. help businesses prioritize the assets to be protecte C. inform executive management of residual risk valu D. assess exposures and plan remediatio

Source answer: D. assess exposures and plan remediatio | Source explanation: Risk analysis explores the degree to which an asset needs protecting so this can be managed effectively. Risk analysis indirectly supports the security expenditure, but justifying the security expenditure is not its primary purpose. Helping businesses prioritize the assets to be protected is an indirect benefit of risk analysis, but not its primary purpose. Informing executive management of residual risk value is not directly relevant.

8
New cards

U072 / Practice 1 Q210; Practice 2 Q166 / The BEST strategy for risk management is to: A. achieve a balance between risk and organizational goal B. reduce risk to an acceptable leve C. ensure that policy development properly considers organizational risk D. ensure that all unmitigated risks are accepted by managemen

Source answer: B. reduce risk to an acceptable leve | Source explanation: The best strategy for risk management is to reduce risk to an acceptable level, as this will take into account the organization's appetite for risk and the fact that it would not be practical to eliminate all risk. Achieving balance between risk and organizational goals is not always practical. Policy development must consider organizational risks as well as business objectives. It may be prudent to ensure that management understands and accepts risks that it is not willing to mitigate, but that is a practice and is not sufficient to l>e considered a strategy.

9
New cards

U073 / Practice 1 Q215; Practice 2 Q170 / The MOST effective use of a risk register is to: A. identify risks and assign roles and responsibilities for mitigatio B. identify threats and probabilitie C. facilitate a thorough review of all IT-related risks on a periodic basi D. record the annualized financial amount of expected losses due to risk

Source answer: C. facilitate a thorough review of all IT-related risks on a periodic basi | Source explanation: A risk register is more than a simple list—it should lie used as a tool to ensure comprehensive documentation, periodic review and formal update of all risk elements in the enterprise's IT and related organization. Identifying risks and assigning roles and responsibilities for mitigation are elements of the register. Identifying threats and probabilities are two elements that are defined in the risk matrix, as differentiated from the broader scope of content in, and purpose for, the risk register. While the annualized loss expectancy (ALE) should be included in the register, this quantification is only a single element in the overall risk analysis program.

10
New cards

U074 / Practice 1 Q216 / Which of the following would be the MOST important factor to be considered in the loss of mobile equipment with unencrypted data? A. Disclosure of personal information B. Sufficient coverage of the insurance policy for accidental losses C. Intrinsic value of the data stored on the equipment D. Replacement cost of the equipment

Source answer: C. Intrinsic value of the data stored on the equipment | Source explanation: When mobile equipment is lost or stolen, the information contained on the equipment matters most in determining the impact of the loss. The more sensitive the information, the greater the liability. If staff carries mobile equipment for business purposes, an organization must develop a clear policy as to what information should be kept on the equipment and for what purpose. Personal information is not defined in the question as the data that were lost. Insurance may be a relatively smaller issue as compared with information theft or opportunity loss, although insurance is also an important factor for a successful business. Cost of equipment would be a less important issue as compared with other choices.

11
New cards

U075 / Practice 1 Q217 / Attackers who exploit cross-site scripting vulnerabilities take advantage of: A. a lack of proper input validation control B. weak authentication controls in the web application laye C. flawed cryptographic secure sockets layer (SSL) implementations and short key length D. implicit web application trust relationship

Source answer: A. a lack of proper input validation control | Source explanation: Cross-site scripting attacks inject malformed input. Attackers who exploit weak application authentication controls can gain unauthorized access to applications and this has little to do with cross-site scripting vulnerabilities. Attackers who exploit flawed cryptographic secure sockets layer (SSI.) implementations and short key lengths can sniff network traffic and crack keys to gain unauthorized access to information. This has little to do with cross-site scripting vulnerabilities. Web application trust relationships do not relate directly to the attack.

12
New cards

U076 / Practice 1 Q219 / When performing an information risk analysis, an information security manager should FIRST: A. establish the ownership of asset B. evaluate the risks to the asset C. take an asset inventor D. categorize the asset

Source answer: C. take an asset inventor | Source explanation: Assets must be inventoried before any of the other choices can be performed.

13
New cards

U078 / Practice 1 Q221 / Previously accepted risk should be: A. re-assessed periodically since the risk can be escalated to an unacceptable level due to revised condition B. accepted permanently since management has already spent resources (time and labor) to conclude that the risk level is acceptabl C. avoided next time since risk avoidance provides the best protection to the compan D. removed from the risk log once it is accepte

Source answer: A. re-assessed periodically since the risk can be escalated to an unacceptable level due to revised condition | Source explanation: Acceptance of risk should be regularly reviewed to ensure that the rationale for the initial risk acceptance is still valid within the current business context. The rationale for initial risk acceptance may no longer be valid due to change(s) and. hence, risk cannot be accepted permanently. Risk is an inherent part of business and it is impractical and costly to eliminate all risk. Even risks that have been accepted should be monitored for changing conditions that could alter the original decision.

14
New cards

U082 / Practice 1 Q234 / After assessing and mitigating the risks of a web application, who should decide on the acceptance of residual application risks? A. Information security officer B. Chief information officer (CIO) C. Business owner D. Chief executive officer (CF.O)

Source answer: C. Business owner | Source explanation: The business owner of the application needs to understand and accept the residual application risks.

15
New cards

U083 / Practice 1 Q239 / Which of the following steps in conducting a risk assessment should be performed FIRST? A. Identity business assets B. Identify business risks C. Assess vulnerabilities D. Evaluate key controls

Source answer: A. Identity business assets | Source explanation: Risk assessment first requires one to identify the business assets that need to be protected before identifying the threats. The next step is to establish whether those threats represent business risk by identifying the likelihood and effect of occurrence, followed by assessing the vulnerabilities that may affect the security of the asset. This process establishes the control objectives against which key controls can be evaluated.

16
New cards

U084 / Practice 1 Q244 / What does a network vulnerability assessment intend to identify? A. 0-day vulnerabilities B. Malicious software and spyware C. Security design flaws D. Misconfiguration and missing updates

Source answer: D. Misconfiguration and missing updates | Source explanation: A network vulnerability assessment intends to identify known vulnerabilities based on common misconfigurations and missing updates. 0-day vulnerabilities by definition are not previously known and therefore are undetectable. Malicious software and spyware are normally addressed through antivirus and antispyware policies. Security design flaws require a deeper level of analysis.

17
New cards

U086 / Practice 1 Q249 / An organization has a process in place that involves the use of a vendor. A risk assessment was completed during the development of the process. A year after the implementation a monetary decision has been made to use a different vendor. What, if anything, should occur? A. Nothing, since a risk assessment was completed during developmen B. A vulnerability assessment should be conducte C. A new risk assessment should be performe D. The new vendor's SAS 70 type II report should be reviewe

Source answer: C. A new risk assessment should be performe | Source explanation: The risk assessment process is continual and any changes to an established process should include a new- risk assessment. While a review of the SAS 70 report and a vulnerability assessment may be components of a risk assessment, neither would constitute sufficient due diligence on its own.

18
New cards

U087 / Practice 1 Q253; Practice 2 Q209 / Which of the following BEST describes the scope of risk analysis? A. Key financial systems B. Organizational activities C. Key systems and infrastructure D. Systems subject to regulatory compliance

Source answer: B. Organizational activities | Source explanation: Risk analysis should include all organizational activities. It should not be limited to subsets of systems or just systems and infrastructure.

19
New cards

U089 / Practice 1 Q263 / Risk assessment is MOST effective when performed: A. at the beginning of security program developmen B. on a continuous basi C. while developing the business case for the security progra D. during the business change proces

Source answer: B. on a continuous basi | Source explanation: Risk assessment needs to be performed on a continuous basis because of organizational and technical changes. Risk assessment must take into account all significant changes in order to be effective.

20
New cards

U090 / Practice 1 Q264 / A company's mail server allows anonymous file transfer protocol (FTP) access which could be exploited. What process should the information security manager deploy to determine the necessity for remedial action? A. A penetration test B. A security baseline review C. A risk assessment D. A business impact analysis (BIA)

Source answer: C. A risk assessment | Source explanation: A risk assessment will identify- the business impact of such vulnerability being exploited and is, thus, the correct process. A penetration test or a security baseline review may identify the vulnerability but not the remedy. A business impact analysis (BIA) will more likely identify the impact of the loss of the mail server.

21
New cards

U095 / Practice 1 Q280; Practice 2 Q226 / A common concern with poorly written web applications is that they can allow an attacker to: A. gain control through a buffer overflo B. conduct a distributed denial of service (DoS) attac C. abuse a race conditio D. inject structured query language (SQL) statement

Source answer: D. inject structured query language (SQL) statement | Source explanation: Structured query language (SQL) injection is one of the most common and dangerous web application vulnerabilities. Buffer overflows and race conditions are very difficult to find and exploit on web applications. Distributed denial of service (DoS) attacks have nothing to do with the quality of a web application.

22
New cards

U096 / Practice 1 Q283 / Which of the following results from the risk assessment process would BEST assist risk management decision making? A. Control risk B. Inherent risk C. Risk exposure D. Residual risk

Source answer: D. Residual risk | Source explanation: Residual risk provides management with sufficient information to decide to the level of risk that an organization is willing to accept. Control risk is the risk that a control may not succeed in preventing an undesirable event. Risk exposure is the likelihood of an undesirable event occurring. Inherent risk is an important factor to be considered during the risk assessment.

23
New cards

U098 / Practice 1 Q291 / What mechanisms are used to identify deficiencies that would provide attackers with an opportunity to compromise a computer system? A. Business impact analyses B. Security gap analyses C. System performance metrics D. Incident response processes

Source answer: B. Security gap analyses | Source explanation: A security gap analysis is a process which measures all security controls in place against typically good business practice, and identifies related weaknesses. A business impact analysis is less suited to identify security deficiencies. System performance metrics may indicate security weaknesses, but that is not their primary purpose. Incident response processes exist for cases where security weaknesses are exploited.

24
New cards

U100 / Practice 1 Q295 / Which of the following would generally have the GREATEST negative impact on an organization? A. Theft of computer software B. Interruption of utility services C. Loss of customer confidence D. Internal fraud resulting in monetary loss

Source answer: C. Loss of customer confidence | Source explanation: Although the theft of software, interruption of utility services and internal frauds are all significant, the loss of customer confidence is the most damaging and could cause the business to fail.

25
New cards

U101 / Practice 1 Q299; Practice 2 Q239 / Which of the following techniques MOST clearly indicates whether specific risk-reduction controls should be implemented? A. Countermeasure cost-benefit analysis B. Penetration testing C. Frequent risk assessment programs D. Annual loss expectancy (ALE) calculation

Source answer: A. Countermeasure cost-benefit analysis | Source explanation: In a countermeasure cost-benefit analysis, the annual cost of safeguards is compared with the expected cost of loss. This can then be used to justify a specific control measure. Penetration testing may indicate the extent of a weakness but, by itself, will not establish the cost/benefit of a control. Frequent risk assessment programs will certainly establish what risk exists but will not determine the maximum cost of controls. Annual loss expectancy (ALE) is a measure which will contribute to the value of the risk but. alone, will not justify a control.

26
New cards

U103 / Practice 1 Q303; Practice 2 Q246 / Based on the information provided, which of the following situations presents the GREATEST information security risk for an organization with multiple, but small, domestic processing locations? A. Systems operation procedures are not enforced B. Change management procedures are poor C. Systems development is outsourced D. Systems capacity management is not performed

Source answer: B. Change management procedures are poor | Source explanation: The lack of change management is a severe omission and will greatly increase information security risk. Since procedures are generally nonauthoritative, their lack of enforcement is not a primary concern. Systems that are developed by third-party vendors are becoming commonplace and do not represent an increase in security risk as much as poor change management. Poor capacity management may not necessarily represent a security risk.

27
New cards

U106 / Practice 1 Q310; Practice 2 Q250 / The valuation of IT assets should be performed by: A. an IT security manage B. an independent security consultan C. the chief financial officer (CFO). D. the information owne

Source answer: D. the information owne | Source explanation: Information asset owners are in the best position to evaluate the value added by the IT asset under review within a business process, thanks to their deep knowledge of the business processes and of the functional IT requirements. An IT security manager is an expert of the IT risk assessment methodology and IT asset valuation mechanisms. However, the manager could not have a deep understanding of all the business processes of the firm. An IT security subject matter expert will take part of the process to identify threats and vulnerabilities and will collaborate with the business information asset owner to define the risk profile of the asset. A chief financial officer (CFO) will have an overall costs picture but not detailed enough to evaluate the value of each IT asset.

28
New cards

U107 / Practice 1 Q315 / A security risk assessment exercise should be repeated at regular intervals because: A. business threats are constantly changin B. omissions in earlier assessments can be addresse C. repetitive assessments allow various methodologie D. they help raise awareness on security in the busines

Source answer: A. business threats are constantly changin | Source explanation: As business objectives and methods change, the nature and relevance of threats change as well. Choice B does not, by itself, justify regular reassessment. Choice C is not necessarily true in all cases. Choice D is incorrect because there are better ways of raising security awareness than by performing a risk assessment.

29
New cards

U108 / Practice 1 Q318 / The PRIMARY reason for initiating a policy exception process is when: A. operations are too busy to compl B. the risk is justified by the benefi C. policy compliance would be difficult to enforc D. users may initially be inconvenience

Source answer: B. the risk is justified by the benefi | Source explanation: Exceptions to policy are warranted in circumstances where compliance may be difficult or impossible and the risk of noncompliance is outweighed by the benefits. Being busy is not a justification for policy exceptions, nor is the fact that compliance cannot be enforced. User inconvenience is not a reason to automatically grant exception to a policy.

30
New cards

U109 / Practice 1 Q319 / Which of the following is the MAIN reason for performing risk assessment on a continuous basis'? A. Justification of the security budget must be continually mad B. New vulnerabilities are discovered every da C. The risk environment is constantly changin D. Management needs to be continually informed about emerging risk

Source answer: C. The risk environment is constantly changin | Source explanation: The risk environment is impacted by factors such as changes in technology, and business strategy. These changes introduce new threats and vulnerabilities to the organization. As a result, risk assessment should be performed continuously. Justification of a budget should never be the main reason for performing a risk assessment. New vulnerabilities should be managed through a patch management process. Informing management about emerging risks is important, but is not the main driver for determining when a risk assessment should be performed.

31
New cards

U110 / Practice 1 Q322; Practice 2 Q254 / A risk management program should reduce risk to: A. zer B. an acceptable leve C. an acceptable percent of revenu D. an acceptable probability of occurrenc

Source answer: B. an acceptable leve | Source explanation: Risk should be reduced to an acceptable level based on the risk preference of the organization. Reducing risk to zero is impractical and could be cost-prohibitive. Tying risk to a percentage of revenue is inadvisable since there is no direct correlation between the two. Reducing the probability of risk occurrence may not always be possible, as in the ease of natural disasters. The focus should be on reducing the impact to an acceptable level to the organization, not reducing the probability of the risk.

32
New cards

U111 / Practice 1 Q323; Practice 2 Q262 / Which of the following steps should be performed FIRST in the risk assessment process? A. Staff interviews B. Threat identification C. Asset identification and valuation D. Determination of the likelihood of identified risks

Source answer: C. Asset identification and valuation | Source explanation: The first step in the risk assessment methodology is a system characterization, or identification and valuation, of all of the enterprise's assets to define the boundaries of the assessment. Interviewing is a valuable tool to determine qualitative information about an organization's objectives and tolerance for risk. Interviews are used in subsequent steps. Identification of threats comes later in the process and should not be performed prior to an inventory since many possible threats will not be applicable if there is no asset at risk. Determination of likelihood comes later in the risk assessment process.

33
New cards

U112 / Practice 1 Q326 / Which of the following groups would be in the BEST position to perform a risk analysis for a business? A. External auditors B. A peer group within a similar business C. Process owners D. A specialized management consultant

Source answer: C. Process owners | Source explanation: Process owners have the most in-depth knowledge of risks and compensating controls within their environment. External parties do not have that level of detailed knowledge on the inner workings of the business. Management consultants are expected to have the necessary skills in risk analysis techniques but are still less effective than a group with intimate knowledge of the business.

34
New cards

U115 / Practice 1 Q339 / A risk assessment should be conducted: A. once a year for each business process and subproces B. every three to six months for critical business processe C. by external parties to maintain objectivit D. annually or whenever there is a significant chang

Source answer: D. annually or whenever there is a significant chang | Source explanation: Risks are constantly changing. Choice D offers the best alternative because it takes into consideration a reasonable time frame and allows flexibility to address significant change. Conducting a risk assessment once a year is insufficient if important changes take place. Conducting a risk assessment every three-to-six months for critical processes may not be necessary, or it may not address important changes in a timely manner. It is not necessary for assessments to be performed by external parties.

35
New cards

U116 / Practice 1 Q344 / After a risk assessment study, a bank with global operations decided to continue doing business in certain regions of the world where identity theft is rampant. The information security manager should encourage the business to: A. increase its customer awareness efforts in those region B. implement monitoring techniques to detect and react to potential frau C. outsource credit card processing to a third part D. make the customer liable for losses if they fail to follow the bank's advic

Source answer: B. implement monitoring techniques to detect and react to potential frau | Source explanation: While customer awareness will help mitigate the risks, this is insufficient on its own to control fraud risk. Implementing monitoring techniques which will detect and deal with potential fraud cases is the most effective way to deal with this risk. If the bank outsources its processing, the bank still retains liability. While making the customer liable for losses is a possible approach, nevertheless, the bank needs to be seen to be proactive in managing its risks.

36
New cards

U119 / Practice 1 Q350 / Which of the following BEST indicates a successful risk management practice? A. Overall risk is quantified B. Inherent risk is eliminated C. Residual risk is minimized D. Control risk is tied to business units

REVIEW NOTE: CONCEPT CAUTION: Source key C. Interpret "minimized" in the context of acceptable residual risk and business cost, not elimination at any cost. | Source answer: C. Residual risk is minimized | Source explanation: A successful risk management practice minimizes the residual risk to the organization. Choice A is incorrect because the fact that overall risk has been quantified does not necessarily indicate the existence of a successful risk management practice. Choice B is incorrect since it is virtually impossible to eliminate inherent risk. Choice D is incorrect because, although the tying of control risks to business may improve accountability, this is not as desirable as minimizing residual risk.

37
New cards

U120 / Practice 1 Q352 / Information security managers should use risk assessment techniques to: A. justify selection of risk mitigation strategie B. maximize the return on investment (RO C. provide documentation for auditors and regulator D. quantify risks that would otherwise be subjectiv

Source answer: A. justify selection of risk mitigation strategie | Source explanation: Information security managers should use risk assessment techniques to justify and implement a risk mitigation strategy as efficiently as possible. None of the other choices accomplishes that task, although they are important components.

38
New cards

U122 / Practice 1 Q358; Practice 2 Q279 / The PRIMARY goal of a corporate risk management program is to ensure that an organization's: A. IT assets in key business functions are protecte B. business risks are addressed by preventive control C. stated objectives are achievabl D. IT facilities and systems are always availabl

Source answer: C. stated objectives are achievabl | Source explanation: Risk management's primary goal is to ensure an organization maintains the ability to achieve its objectives. Protecting IT assets is one possible goal as well as ensuring infrastructure and systems availability. However, these should be put in the perspective of achieving an organization's objectives. Preventive controls are not always possible or necessary; risk management will address issues with an appropriate mix of preventive and corrective controls.

39
New cards

U123 / Practice 1 Q360 / When performing a risk assessment, the MOST important consideration is that: A. management supports risk mitigation effort B. annual loss expectations (ALEs) have been calculated for critical asset C. assets have been identified and appropriately value D. attack motives, means and opportunities be understoo

Source answer: C. assets have been identified and appropriately value | Source explanation: Identification and valuation of assets provides the basis for risk management efforts as it relates to the criticality and sensitivity of assets. Management support is always important, but is not relevant when determining the proportionality of risk management efforts. ALE calculations are only valid if assets have first been identified and appropriately valued. Motives, means and opportunities should already be factored in as a part of a risk assessment.

40
New cards

U125 / Practice 1 Q368 / Which of the following risks would BEST be assessed using qualitative risk assessment techniques? A. Theft of purchased software B. Power outage lasting 24 hours C. Permanent decline in customer confidence D. Temporary loss of e-mail due to a virus attack

Source answer: C. Permanent decline in customer confidence | Source explanation: A permanent decline in customer confidence does not lend itself well to measurement by quantitative techniques. Qualitative techniques are more effective in evaluating things such as customer loyalty and goodwill. Theft of software, power outages and temporary loss of e-mail can be quantified into monetary amounts easier than can be assessed with quantitative techniques.

41
New cards

U126 / Practice 1 Q372 / Which two components PRIMARILY must be assessed in an effective risk analysis? A. Visibility and duration B. Likelihood and impact C. Probability and frequency D. Financial impact and duration

Source answer: B. Likelihood and impact | Source explanation: The probability or likelihood of the event and the financial impact or magnitude of the event must be assessed first. Duration refers to the length of the event; it is important in order to assess impact but is secondary. Once the likelihood is determined, the frequency is also important to determine overall impact.

42
New cards

U127 / Practice 1 Q377 / An organization has decided to implement additional security controls to treat the risks of a new process. This is an example of: A. eliminating the ris B. transferring the ris C. mitigating the ris D. accepting the ris

Source answer: C. mitigating the ris | Source explanation: Risk can never be eliminated entirely. Transferring the risk gives it away such as buying insurance so the insurance company can take the risk. Implementing additional controls is an example of mitigating risk. Doing nothing to mitigate the risk would be an example of accepting risk.

43
New cards

U132 / Practice 1 Q394 / Which of the following would be the BEST metric for the IT risk management process? A. Number of risk management action plans B. Percentage of critical assets with budgeted remedial C. Percentage of unresolved risk exposures D. Number of security incidents identified

Source answer: B. Percentage of critical assets with budgeted remedial | Source explanation: Percentage of unresolved risk exposures and the number of security incidents identified contribute to the IT risk management process, but the percentage of critical assets with budgeted remedial is the most indicative metric. Number of risk management action plans is not useful for assessing the quality of the process.

44
New cards

U141 / Practice 1 Q414 / An operating system (OS) noncritical patch to enhance system security cannot be applied because a critical application is not compatible with the change. Which of the following is the BEST solution? A. Rewrite the application to conform to the upgraded operating system B. Compensate for not installing the patch with mitigating controls C. Alter the patch to allow the application to run in a privileged state D. Run the application on a test platform; tune production to allow patch and application

Source answer: B. Compensate for not installing the patch with mitigating controls | Source explanation: Since the operating system (OS) patch will adversely impact a critical application, a mitigating control should be identified that will provide an equivalent level of security . Since the application is critical, the patch should not be applied without regard for the application; business requirements must be considered. Altering the OS patch to allow the application to run in a privileged state may create new security weaknesses. Finally, running a production application on a test platform is not an acceptable alternative since it will mean running a critical production application on a platform not subject to the same level of security controls.

45
New cards

U160 / Practice 2 Q3 / What would be the MOST significant security risks when using wireless local area network (LAN) technology? A. Man-in-the-middle attack B. Spoofing of data packets C. Rogue access point D. Session hijacking

Source answer: C. Rogue access point | Source explanation: A rogue access point masquerades as a legitimate access point The risk is that legitimate users may connect through this access point and have their traffic monitored. All other choices are not dependent on the use of a wireless local area network (LAN) technology.

46
New cards

U165 / Practice 2 Q10 / A business unit intends to deploy a new technology in a manner that places it in violation of existing information security standards. What immediate action should an information security manager take? A. Enforce the existing security standard B. Change the standard to permit the deployment C. Perform a risk analysis to quantify the risk D. Perform research to propose use of a better technology

Source answer: C. Perform a risk analysis to quantify the risk | Source explanation: Resolving conflicts of this type should be based on a sound risk analysis of the costs and benefits of allowing or disallowing an exception to the standard. A blanket decision should never be given without conducting such an analysis. Enforcing existing standards is a good practice; however, standards need to be continuously examined in light of new technologies and the risks they present. Standards should not be changed without an appropriate risk assessment.

47
New cards

U175 / Practice 2 Q54 / A risk assessment and business impact analysis (BIA) have been completed for a major proposed purchase and new process for an organization. There is disagreement between the information security manager and the business department manager who will own the process regarding the results and the assigned risk. Which of the following would be the BES T approach of the information security manager? A. Acceptance of the business manager's decision on the risk to the corporation B. Acceptance of the information security manager's decision on the risk to the corporation C. Review of the assessment with executive management for final input D. A new risk assessment and BIA are needed to resolve the disagreement

Source answer: C. Review of the assessment with executive management for final input | Source explanation: Executive management must be supportive of the process and fully understand and agree with the results since risk management decisions can often have a large financial impact and require major changes. Risk management means different things to different people, depending upon their role in the organization, so the input of executive management is important to the process.

48
New cards

U180 / Practice 2 Q70 / Acceptable levels of information security risk should be determined by: A. legal counse B. security managemen C. external auditor D. die steering committe

Source answer: D. die steering committe | Source explanation: Senior management, represented in the steering committee, has ultimate responsibility for determining what levels of risk the organization is willing to assume. Legal counsel, the external auditors and security management are not in a position to make such a decision.

49
New cards

U183 / Practice 2 Q85 / In order to highlight to management the importance of network security, the security manager should FIRST: A. develop a security architectur B. install a network intrusion detection system (NIDS) and prepare a list of attack C. develop a network security polic D. conduct a risk assessmen

Source answer: D. conduct a risk assessmen | Source explanation: A risk assessment would be most helpful to management in understanding at a very high level the threats, probabilities and existing controls. Developing a security architecture, installing a network intrusion detection system (NIDS) and preparing a list of attacks on the network and developing a network security policy would not be as effective in highlighting the importance to management and would follow only after performing a risk assessment.

50
New cards

U187 / Practice 2 Q147 / The cost of implementing a security control should not exceed the: A. annualized loss expectanc B. cost of an inciden C. asset valu D. implementation opportunity cost

REVIEW NOTE: CONCEPT CAUTION: Source key C is a simplified rule. The economic decision also depends on avoided loss, lifetime costs, business impact and mandatory obligations. | Source answer: C. asset valu | Source explanation: The cost of implementing security controls should not exceed the worth of the asset. Annualized loss expectancy represents the losses drat are expected to happen during a single calendar year. A security mechanism may cost more than this amount (or the cost of a single incident) and still be considered cost effective. Opportunity costs relate to revenue lost by forgoing the acquisition of an item or the making of a business decision.

51
New cards

U189 / Practice 2 Q160 / Risk management programs are designed to reduce risk to: A. a level that is too small to be measurabl B. the point at which the benefit exceeds the expens C. a level that the organization is willing to accep D. a rate of return that equals the current cost of capita

Source answer: C. a level that the organization is willing to accep | Source explanation: Risk should be reduced to a level that an organization is willing to accept. Reducing risk to a level too small to measure is impractical and is often cost-prohibitive. To tie risk to a specific rate of return ignores the qualitative aspects of risk that must also be considered. Depending on the risk preference of an organization, it may or may not choose to pursue risk mitigation to the point at which the benefit equals or exceeds the expense. Therefore, choice C is a more precise answer.

52
New cards

U191 / Practice 2 Q172 / The impact of losing frame relay network connectivity for 18-24 hours should be calculated using the: A. hourly billing rate charged by the carrie B. value of the data transmitted over the networ C. aggregate compensation of all affected business user D. financial losses incurred by affected business unit

Source answer: D. financial losses incurred by affected business unit | Source explanation: The bottom line on calculating the impact of a loss is what its cost will be to the organization. The other choices are all factors that contribute to the overall monetary impact.

53
New cards

U192 / Practice 2 Q175 / An information security manager has been assigned to implement more restrictive preventive controls. By doing so, the net effect will be to PRIMARILY reduce the: A. threa B. los C. vulnerabilit D. probabilit

REVIEW NOTE: AMBIGUOUS DISTINCTION: Source key C (vulnerability). Preventive controls can also reduce likelihood; the source's claim that probability is not directly affected is too categorical. | Source answer: C. vulnerabilit | Source explanation: Implementing more restrictive preventive controls mitigates vulnerabilities but not the threats. Losses and probability of occurrence may not be primarily or directly affected.

54
New cards

U193 / Practice 2 Q179 / Ongoing tracking of remediation efforts to mitigate identified risks can BEST be accomplished through the use of which of the following? A. Tree diagrams B. Venn diagrams C. Heat charts D. Bar charts

Source answer: C. Heat charts | Source explanation: Meat charts, sometimes referred to as stoplight charts, quickly and clearly show the current status of remediation efforts. Venn diagrams show the connection between sets; tree diagrams are useful for decision analysis; and bar charts show relative size.

55
New cards

U194 / Practice 2 Q186 / Risk acceptance is a component of which of the following? A. Assessment B. Mitigation C. Evaluation D. Monitoring

REVIEW NOTE: TERMINOLOGY CAUTION: Source key B uses "mitigation" broadly. In standard risk-response terminology, acceptance is a treatment/response option distinct from reducing (mitigating) risk. | Source answer: B. Mitigation | Source explanation: Risk acceptance is one of the alternatives to be considered in the risk mitigation process. Assessment and evaluation are components of the risk analysis process. Risk acceptance is not a component of monitoring.

56
New cards

U196 / Practice 2 Q196 / A risk management program would be expected to: A. remove all inherent ris B. maintain residual risk at an acceptable leve C. implement preventive controls for every threa D. reduce control risk to zer

Source answer: B. maintain residual risk at an acceptable leve | Source explanation: The object of risk management is to ensure that all residual risk is maintained at a level acceptable to the business; it is not intended to remove every identified risk or implement controls for every threat since this may not be cost-effective. Control risk, i.e., that a control may not be effective, is a component of the program but is unlikely to be reduced to zero.

57
New cards

U200 / Practice 2 Q212 / In performing a risk assessment on the impact of losing a server, the value of the server should be calculated using the: A. original cost to acquir B. cost of the software store C. annualized loss expectancy (ALE). D. cost to obtain a replacemen

Source answer: D. cost to obtain a replacemen | Source explanation: The value of the server should be based on its cost of replacement. The original cost may be significantly different from the current cost and, therefore, not as relevant. The value of the software is not at issue because it can be restored from backup media. The ALE for all risks related to the server does not represent the server's value.

58
New cards

U201 / Practice 2 Q213 / An information security manager is advised by contacts in law enforcement that there is evidence that his/ her company is being targeted by a skilled gang of hackers known to use a variety of techniques, including social engineering and network penetration. The FIRST step that the security manager should take is to: A. perform a comprehensive assessment of the organization's exposure to the hacker's technique B. initiate awareness training to counter social engineerin C. immediately advise senior management of the elevated ris D. increase monitoring activities to provide early detection of intrusio

Source answer: C. immediately advise senior management of the elevated ris | Source explanation: Information about possible significant new risks from credible sources should be provided to management along with advice on steps that need to be taken to counter the threat. The security manager should assess the risk, but senior management should be immediately advised. It may be prudent to initiate an awareness campaign subsequent to sounding the alarm if awareness training is not current. Monitoring activities should also be increased.

59
New cards

U203 / Practice 2 Q231 / Which of the following is the MOST usable deliverable of an information security risk analysis? A. Business impact analysis (BIA) report B. List of action items to mitigate risk C. Assignment of risks to process owners D. Quantification of organizational risk

Source answer: B. List of action items to mitigate risk | Source explanation: Although all of these are important, the list of action items is used to reduce or transfer the current level of risk. The other options materially contribute to the way the actions are implemented.

60
New cards

U204 / Practice 2 Q235 / A risk analysis should: A. include a benchmark of similar companies in its scop B. assume an equal degree of protection for all asset C. address the potential size and likelihood of los D. give more weight to the likelihood v E. the size of the los

REVIEW NOTE: DAMAGED OPTIONS: D and E form one split option about likelihood versus size of loss. Source key C is unaffected. | Source answer: C. address the potential size and likelihood of los | Source explanation: A risk analysis should take into account the potential size and likelihood of a loss. It could include comparisons with a group of companies of similar size. It should not assume an equal degree of protection for all assets since assets may have different risk factors. The likelihood of the loss should not receive greater emphasis than the size of the loss; a risk analysis should always address both equally.

61
New cards

U205 / Practice 2 Q242 / Which of the following is the MOST effective way to treat a risk such as a natural disaster that has a low probability and a high impact level? A. Implement countermeasure B. Eliminate the ris C. Transfer the ris D. Accept the ris

Source answer: C. Transfer the ris | Source explanation: Risks are typically transferred to insurance companies when the probability of an incident is low but the impact is high. Examples include: hurricanes, tornados and earthquakes. Implementing countermeasures may not be the most cost-effective approach to security management. Eliminating the risk may not be possible. Accepting the risk would leave the organization vulnerable to a catastrophic disaster which may cripple or ruin the organization. It would be more cost effective to pay recurring insurance costs than to be affected by a disaster from which the organization cannot financially recover.

62
New cards

U206 / Practice 2 Q249 / The PRIMARY objective of a risk management program is to: A. minimize inherent ris B. eliminate business ris C. implement effective control D. minimize residual ris

REVIEW NOTE: CONCEPT CAUTION: Source key D. Its explanation correctly narrows this to keeping residual risk at manageable/acceptable levels. | Source answer: D. minimize residual ris | Source explanation: The goal of a risk management program is to ensure that residual risk remains within manageable levels. Management of risk does not always require the removal of inherent risk nor is this always possible. A possible benefit of good risk management is to reduce insurance premiums, but this is not its primary intention. Effective controls are naturally a clear objective of a risk management program, but with the choices given, choice C is an incomplete answer.

63
New cards

U207 / Practice 2 Q252 / For risk management purposes, the value of an asset should be based on: A. original cos B. net cash flo C. net present valu D. replacement cos

REVIEW NOTE: SCOPE CAUTION: Source key D. The explanation specifically discusses physical replacement cost; information/business asset valuation can also include business impact and intangible value. | Source answer: D. replacement cos | Source explanation: The value of a physical asset should be based on its replacement cost since this is the amount that would be needed to replace the asset if it were to become damaged or destroyed. Original cost may be significantly different than the current cost of replacing the asset. Net cash flow and net present value do not accurately reflect the true value of the asset.

64
New cards

U208 / Practice 2 Q256 / The MOST effective way to incorporate risk management practices into existing production systems is through: A. policy developmen B. change managemen C. awareness trainin D. regular monitorin

Source answer: B. change managemen | Source explanation: Change is a process in which new risks can be introduced into business processes and systems. For this reason, risk management should be an integral component of the change management process. Policy development, awareness training and regular monitoring, although all worthwhile activities, are not as effective as change management.

65
New cards

U209 / Practice 2 Q261 / Which of the following is the BEST method to ensure the overall effectiveness of a risk management program? A. User assessments of changes B. Comparison of the program results with industry standards C. Assignment of risk within the organization D. Participation by all members of the organization

Source answer: D. Participation by all members of the organization | Source explanation: Effective risk management requires participation, support and acceptance by all applicable members of the organization, beginning with the executive levels. Personnel must understand their responsibilities and be trained on how to fulfill their roles.

66
New cards

U210 / Practice 2 Q264 / Because of its importance to the business, an organization wants to quickly implement a technical solution which deviates from the company's policies. An information security manager should: A. conduct a risk assessment and allow or disallow based on the outcom B. recommend a risk assessment and implementation only if the residual risks are accepte C. recommend against implementation because it violates the company's policie D. recommend revision of current polic

Source answer: B. recommend a risk assessment and implementation only if the residual risks are accepte | Source explanation: Whenever the company's policies cannot be followed, a risk assessment should be conducted to clarify the risks. It is then up to management to accept the risks or to mitigate them. Management determines the level of risk they are willing to take. Recommending revision of current policy should not be triggered by a single request.

67
New cards

U213 / Practice 2 Q282 / Which of the following risks would BEST be assessed using quantitative risk assessment techniques? A. Customer data stolen B. An electrical power outage C. A web site defaced by hackers D. Loss of the software development team

Source answer: B. An electrical power outage | Source explanation: The effect of the theft of customer data or web site defacement by hackers could lead to a permanent decline in customer confidence, which does not lend itself to measurement by quantitative techniques. Loss of a majority of the software development team could have similar unpredictable repercussions. However, the loss of electrical power for a short duration is more easily measurable and can be quantified into monetary amounts that can be assessed with quantitative techniques.

68
New cards

U214 / Practice 2 Q287 / In assessing risk, it is MOST essential to: A. provide equal coverage for all asset type B. use benchmarking data from similar organization C. consider both monetary value and likelihood of los D. focus primarily on threats and recent business losse

Source answer: C. consider both monetary value and likelihood of los | Source explanation: A risk analysis should take into account the potential financial impact and likelihood of a loss. It should not weigh all potential losses evenly, nor should it focus primarily on recent losses or losses experienced by similar firms. Although this is important supplementary information, it does not reflect the organization's real situation. Geography and other factors come into play as well.

69
New cards

U215 / Practice 2 Q292 / A successful information security management program should use which of the following to determine the amount of resources devoted to mitigating exposures? A. Risk analysis results B. Audit report findings C. Penetration test results D. Amount of IT budget available

Source answer: A. Risk analysis results | Source explanation: Risk analysis results are the most useful and complete source of information for determining the amount of resources to devote to mitigating exposures. Audit report findings may not address all risks and do not address annual loss frequency. Penetration test results provide only a limited view of exposures, while the IT budget is not tied to the exposures faced by the organization.

70
New cards

U247 / Practice 2 Q405 / Which of the following would be the MOST significant security risk in a pharmaceutical institution? A. Compromised customer information B. Unavailability of online transactions C. Theft of security tokens D. Theft of a Research and Development laptop

Source answer: D. Theft of a Research and Development laptop | Source explanation: The research and development department is usually the most sensitive area of the pharmaceutical organization, Theft of a laptop from this area could result in the disclosure of sensitive formulas and other intellectual property which could represent the greatest security breach. A pharmaceutical organization does not normally have direct contact with end customers and their transactions are not time critical: therefore, compromised customer information and unavailability of online transactions are not the most significant security risks. Theft of security tokens would not be as significant since a pin would still be required for their use.

71
New cards

U248 / Practice 2 Q410 / Which of the following events generally has the highest information security impact? A. Opening a new office B. Merging with another organization C. Relocating the data center D. Rewiring the network

Source answer: B. Merging with another organization | Source explanation: Merging with or acquiring another organization causes a major impact on an information security management function because new vulnerabilities and risks are inherited. Opening a new office, moving the data center to a new site, or rewiring a network may have information security risks, but generally comply with corporate security policy and are easier to secure.