EOQ vs Reorder point
EOQ answers HOW MUCH to order (ordering vs holding cost). Reorder point answers WHEN to order (lead time, variability, service level). Different questions.
Lead time shortens
EOQ unchanged. Reorder point falls (less lead-time demand and less safety stock).
What raises safety stock vs what doesn't
Raises: higher service level, more demand variability, longer lead time. No effect: order quantity, ordering cost.
Cycle stock vs Safety stock vs Pipeline stock
Cycle = average from ordering in batches (Q/2). Safety = buffer for demand variability during lead time. Pipeline = units in transit.
Newsvendor vs EOQ
Newsvendor = ONE order for one season or day, leftovers lose value. EOQ = repeated ordering of steady demand all year.
Underage vs Overage cost
Underage = lost profit from running out (price minus cost). Overage = cost of a leftover (cost plus disposal minus salvage).
Critical ratio above vs below 0.5
Above 0.5 = stock MORE than mean demand (running out costs more). Below 0.5 = stock LESS than the mean (leftovers cost more).
Order 20% above the EOQ
Total cost rises only slightly. The cost curve is flat near the EOQ.