Environmental Impact Assessment in the Philippines: Processes, Laws, and Criticisms

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/63

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 12:59 PM on 10/5/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

64 Terms

1
New cards

What is the purpose of an Environmental Impact Assessment (EIA)?

To achieve an environmentally sound project design and management.

2
New cards

What does the EIA process involve?

Predicting and evaluating the likely impacts of a project on the environment during construction, commissioning, operation, and abandonment.

3
New cards

What additional measures does the EIA include?

Designing appropriate preventive, mitigating, and enhancement measures to protect the environment and community welfare.

4
New cards

What is PD 1586?

The official establishment of the EIA System in the Philippines in June 1978.

5
New cards

What agency was established under the Ministry of Human Settlements to implement the EIA system in the Philippines?

National Environmental Protection Council (NEPC).

6
New cards

What does the Philippine EIS System aim to do?

Identify issues/impacts ahead that may be covered by regional environmental permits and other regulatory bodies.

7
New cards

What is a key operating principle of the Philippine EIS System?

Assessing the direct and indirect impacts of a project on the environment.

8
New cards

Who is responsible for determining and disclosing necessary data for EIA assessment?

Project Proponents.

9
New cards

What are the three general criteria guiding the review of EIA Reports by DENR-EMB?

1. Environmental considerations are integrated into overall project planning.

2. Assessment is technically sound and proposed mitigation measures are effective.

3. The review is based on accurate data provided by the proponent.

10
New cards

What is the role of the DENR-EMB in the EIA process?

To review EIA Reports based on established criteria.

11
New cards

What does the EIA process fill in terms of environmental protection?

It provides appropriate cover for environmental protection and enhancement-related actions.

12
New cards

What does the term 'cumulative impacts' refer to in EIA?

The total environmental impact of a project, including the effects of other projects and actions.

13
New cards

What is the purpose of the EIA in project planning?

To aid proponents in incorporating environmental considerations into their plans.

14
New cards

What is the role of the Environmental Management Bureau (EMB)?

To oversee the implementation of the EIA system and ensure compliance with environmental regulations.

15
New cards

What does the EIA process evaluate during a project's lifecycle?

The likely impacts on the environment during construction, operation, and abandonment.

16
New cards

What is the primary focus of the EIA process?

Prevention through an input to decision making.

17
New cards

What is one objective of the Philippine EIS System?

To avoid serious and irreversible damage to the environment.

18
New cards

What does EIA stand for?

Environmental Impact Assessment.

19
New cards

Key actor in the EIA process.

Facilitators, Regulators, Developers, or Affected Parties.

20
New cards

What document represents the environmental compliance certificate in the EIA process?

Environmental Compliance Commitment (ECC) document.

21
New cards

What is the purpose of the Certificate of Non-Coverage (CNC)?

It is issued for a non-covered project.

22
New cards

What is the first phase in the EIA process within the project cycle?

Pre-feasibility.

23
New cards

What happens during the construction and development phase of the EIA process?

Implementation of mitigation measures.

24
New cards

What is monitored during the operation and maintenance phase of the EIA process?

Environmental compliance and overall performance.

25
New cards

What is the purpose of the denial letter in the EIA process?

To explain disapproval and provide guidance for improvement.

26
New cards

Who are considered affected parties in the EIA process?

Immediate communities, non-government organizations, and people's organizations.

27
New cards

What is the role of local government agencies in the EIA process?

They act as regulators.

28
New cards

What does ECC stand for in the EIA process?

Environmental Compliance Certificate

29
New cards

What does CNC stand for in the EIA process?

Certificate of Non-Coverage

30
New cards

What role do EIA findings play in decision making?

EIA findings and recommendations are transmitted to relevant NGAs for decision making on clearances, permits, and licenses.

31
New cards

Does the issuance of ECC/CNC exempt a project from other permits?

No, it does not exempt from securing other government permits, clearances, and licenses.

32
New cards

Who has the final decision for project implementation?

The final decision lies with the Local Government Unit (LGU) or National Government Agency (NGA).

33
New cards

What are Environmentally Critical Projects (ECPs)?

Projects that may significantly affect the environment, such as heavy industries and resource extractive industries.

34
New cards

Name a type of heavy industry classified as an ECP.

Non-ferrous metal industries, iron and steel mills, or petroleum and petro-chemical industries.

35
New cards

What types of projects fall under resource extractive industries?

Forestry projects, major mining and quarrying projects, and fishery projects.

36
New cards

What are examples of infrastructure projects classified as ECPs?

Major dams, major reclamation projects, and major power plants.

37
New cards

What are Environmentally Critical Areas (ECAs)?

Areas declared by law as national parks, watershed reserves, wildlife preserves, and areas of unique historic or scientific interest.

38
New cards

What characterizes water bodies as ECAs?

Critical slopes, prime agricultural lands, and areas recharged for aquifers.

39
New cards

What conditions classify mangrove areas as ECAs?

Areas that serve as natural buffers against erosion and support local livelihoods.

40
New cards

What is the purpose of the Environmental Impact Statement (EIS)?

To study significant impacts of a project on the environment and include an Environmental Management Plan.

41
New cards

How does the Initial Environmental Examination Report (IEER) differ from an EIS?

The IEER has reduced details and depth of assessment compared to an EIS.

42
New cards

What is a Programmatic EIS (PEIS)?

A documentation of studies on environmental baseline conditions of an area, assessing the carrying capacity for impacts from co-located projects.

43
New cards

What is the classification of projects not listed in any groups?

Unclassified projects, which will be classified after evaluation.

44
New cards

What types of projects are included in Group 1 of single project groupings?

ECPs in ECAs or NECAs, including major wood processing and mining projects.

45
New cards

What are NECPs in ECAs?

Non-Environmentally Critical Projects in Environmentally Critical Areas, such as minor wood processing and infrastructure projects.

46
New cards

What is the Environmental Impact Statement (EIS)?

It is a comprehensive study of the significant impacts of a project on the environment.

47
New cards

What is the purpose of the Initial Environmental Examination Checklist (IEEC)?

To identify documents needed for new projects based on project type, location, magnitude of potential impact, and project threshold.

48
New cards

What is the Project Description Report (PDR) used for?

It is a requirement for environmental enhancement and mitigation projects to confirm the benign nature of proposed operations for issuing a Certificate of Non-Coverage (CNC).

49
New cards

What does the Environmental Performance Report and Management Plan (EPRMP) address?

It is for operating projects planning to modify or expand operations or for projects applying for an Environmental Compliance Certificate (ECC).

50
New cards

What is the purpose of the Programmatic EPRMP (PEPRMP)?

To document cumulative environmental impacts of co-located projects and propose improvements to current environmental mitigation measures.

51
New cards

How many stages are there in the Philippine EIA Process?

There are six stages: Screening, Scoping, EIA Study and Report Preparation, EIA Review and Evaluation, Decision Making, and Post-ECC Monitoring.

<p>There are six stages: Screening, Scoping, EIA Study and Report Preparation, EIA Review and Evaluation, Decision Making, and Post-ECC Monitoring.</p>
52
New cards

What is determined during the Screening stage of the EIA process?

It determines if a project is covered by the PEISS and identifies document types and requirements for approval.

53
New cards

What is the goal of the Scoping stage in the EIA process?

To identify issues/impacts and delimit the extent of baseline information needed for the EIA Study.

54
New cards

What activities are involved in the EIA Study and Report Preparation stage?

Description of the proposed project, impact identification and prediction, evaluation of significance, and development of an Environmental Management and Monitoring Plan.

55
New cards

Who evaluates the EIA during the Review and Evaluation stage?

The EIA Review Committee and DENR/EMB internal specialists.

56
New cards

What outcomes can result from the Decision Making stage of the EIA process?

Issuance of an ECC, CNC, or Denial Letter based on evaluation of EIA recommendations.

57
New cards

What is assessed during the Monitoring, Validation, Evaluation, and Audit stage?

The performance of the Proponent against the ECC and Environmental Management and Monitoring Plans.

58
New cards

What is a major criticism of the EIA process regarding costs?

Producing a complete EIA study is costly, adding to the overall project cost.

59
New cards

What is a common issue related to public participation in the EIA process?

Limited public participation can lead to insufficient consideration of cumulative environmental impacts.

60
New cards

Why is there often inadequate follow-up in the EIA process?

Due to insufficient data on monitoring and audit, the influence on decision-making is limited.

61
New cards

How does the quality of EIA reports depend on the Proponent?

The quality is dependent on the Proponent's resources and trained personnel, affecting approval timelines and recommendations.

62
New cards

What is the significance of Presidential Decree No. 1151?

It establishes the Philippine Environmental Policy.

63
New cards

What does Presidential Decree No. 1586 establish?

It establishes an Environmental Impact Statement System including other environmental management measures.

64
New cards

What is the source of the Revised Procedural Manual for DAO-03-30?

It provides guidelines for the EIA process in the Philippines.