Work Breakdown Sructure
— organizes the project.
Activity Network
— establishes the logical relationship between the work packages and activities.
Step 1 - Identify Work
Step 2 - Develop Activities
Step 3- Determine Duration
Step 4 - Identify Dependencies
Step 5 - Draw the Network
Step 6 - Calculate Network Duration
The process begins with the WBS.
Step 1 - Identify Work
Use the WBS to identify project components.
Step 2 - Develop Activities
Convert work components into schedulable activities.
Step 3- Determine Duration
Assign estimated durations.
Step 4 - Identify Dependencies
Determine which activities must precede others.
Step 5 - Draw the Network
Represent the activities and relationships graphically.
Step 6 - Calculate Network Duration
Determine the time required to move from project start to completion.