Vocabulary practice flashcards covering construction management principles, project delivery systems, contract types and documents, supervision groups, management cycles, and site issues.

36 Terms

1
New cards
<p>Design–Bid-Build (DBB)</p>

Design–Bid-Build (DBB)

A traditional project delivery method where design and construction occur sequentially under separate contracts, remaining the preferred system for Philippine public infrastructure to ensure transparency and compliance with procurement laws.

2
New cards
<p>Design–Build (DB)</p>

Design–Build (DB)

A project delivery method combining design and construction under a single contract with one firm or consortium, enabling fast-tracking where construction starts before the complete design is finalized.

3
New cards

Construction Contract

A legally binding agreement between the owner and the contractor outlining the scope of work, contract cost, project schedule, payment terms, and allocation of project risks.

4
New cards

Lump Sum Contract

A fixed-price contract that mandates the contractor to complete the entire project for a single predetermined price, offering high cost certainty when plans and specifications are fully defined.

5
New cards

Unit Price Contract

A contract where compensation is calculated from pre-established rates multiplied by the actual quantities of work measured and completed on site.

6
New cards

Cost Plus Contract

A contract under which the owner reimburses the contractor for actual construction expenses and pays an additional fee (fixed, percentage, or performance-based) for their services.

7
New cards

Guaranteed Maximum Price (GMP) Contract

A contract that sets an upper ceiling on the owner's financial liability, where the contractor guarantees that the total cost will not exceed this cap unless authorized changes occur.

8
New cards

Time and Materials (T&M) Contract

A contract where the contractor is reimbursed for actual labor hours worked, equipment utilized, and materials consumed, offering the greatest flexibility but lowest cost certainty.

9
New cards

Contract Documents

The complete collection of legal and technical documents that define the project scope, quality standards, schedule, contract price, and mutual obligations of the owner and contractor.

10
New cards

Construction Agreement

The primary legally enforceable contract between the owner and contractor that establishes the contractual relationship, identifying the parties, contract price, duration, and core responsibilities.

11
New cards

Drawings (Plans)

The graphical representations prepared by architects and engineers showing dimensions, layout, materials, and construction details needed to build the project accurately.

12
New cards

Technical Specifications

Written documents accompanying the drawings that specify the required materials, workmanship standards, installation procedures, and testing requirements.

13
New cards

Bill of Quantities (BOQ)

A detailed itemized list of all work items and their estimated quantities, used during bidding, project costing, progress billings, and cost control.

14
New cards

General Conditions

Standard contractual provisions governing contract administration, including the duties of the owner, contractor, and architect, payment procedures, supervision, warranties, insurance, and dispute resolution.

15
New cards

Special Conditions

Project-specific contract provisions that modify or supplement the General Conditions to address unique requirements such as specific environmental factors, location details, or specialized methods.

16
New cards

Addenda

Written documents issued prior to the submission of bids to clarify, modify, or correct the original bidding documents.

17
New cards

Change Order

A formal written document issued after contract award authorizing an adjustment to the scope of work, contract price, or project duration.

18
New cards

Notice to Proceed (NTP)

A formal document issued by the owner authorizing the contractor to start construction and establishing the official commencement date for the project timeline.

19
New cards

Performance Bond

A financial and legal guarantee ensuring that the contractor will complete the project in accordance with the contract terms and conditions.

20
New cards

Payment Bond

A financial protection document that guarantees subcontractors, suppliers, and laborers will be paid for their supplied materials and completed labor.

21
New cards
<p>Four Major Construction Project Constraints</p>

Four Major Construction Project Constraints

The four interconnected parameters—Time, Cost, Quality, and Safety—that a construction manager must balance simultaneously to drive project performance.

22
New cards

Critical Path

The longest connected chain of sequential project activities that determines the overall minimum time required to complete the project.

23
New cards

Architect-of-Record

The registered and licensed architect professionally liable for the overall design and for signing and sealing the project's plans, specifications, and contract documents.

24
New cards

Architect-in-Charge of Construction

The registered and licensed architect directly responsible for supervising the day-to-day construction activities on the site.

25
New cards

Construction Supervision Group (CSG)

The team acting as the owner's eyes and ears on the project site to inspect work, track quality control, evaluate issues, coordinate participants, and maintain daily records.

26
New cards
<p>Major Project Participants Relationship</p>

Major Project Participants Relationship

The simplified organizational structure defining interactions between the Owner, Construction Manager, Designer/Architect, Contractor, and the Construction Supervision Group/Site Inspectors.

27
New cards

Agency Construction Manager

A construction manager who acts strictly as an adviser and representative of the owner, bears lower construction risk, and generally does not hold direct contracts with trade contractors.

28
New cards

At-Risk Construction Manager

A construction manager who assumes greater contractual and construction risk and may hold direct subcontracts with specialty trade contractors.

29
New cards
<p>Construction Management Cycle</p>

Construction Management Cycle

A continuous leadership cycle executed by the Construction Manager consisting of six essential functions: Plan, Coordinate, Monitor, Control, Document, and Improve.

30
New cards

Republic Act No. 9184

The Government Procurement Reform Act of the Philippines that governs bidding, procurement, execution, and valid contract time extensions for public infrastructure projects.

31
New cards

Republic Act No. 11058

A Philippine law that, along with the Occupational Safety and Health Standards, mandates employers to ensure safe working conditions and provide personal protective equipment on construction sites.

32
New cards

Personal Protective Equipment (PPE)

Basic safety gear required on construction sites to protect workers from hazards, specifically including hard hats, safety vests, safety shoes, safety goggles, and gloves.

33
New cards

Daily Site Report

An organized site record maintained by the field supervision team detailing weather conditions, manpower count, equipment used, deliveries, work activities, visitors, instructions, and decisions.

34
New cards

Progress Payments

Periodic contract disbursements paid to the contractor based on verified percentages of completed and inspected work, supported by billing records and accomplishment reports.

35
New cards

Work Suspension

A temporary stoppage of site operations resulting from unsafe conditions, natural disasters, funding deficits, unresolved design issues, or pending disputes.

36
New cards

Contract Termination

The formal cancellation of a construction contract used as a last resort when a party commits a material breach, such as project abandonment, persistent poor workmanship, or unjustified delays.