1/19
Comprehensive vocabulary flashcards covering Aggregate Planning, Chase and Level strategies, Master Production Scheduling (MPS), Materials Requirement Planning (MRP), Bill of Materials (BOM), and Enterprise Resource Planning (ERP) based on Dr. Mohsin Jat's lecture on Production Planning.
Demand & Capacity Planning
The operational process of determining future production quantities and arranging the necessary labor, equipment, and material resources across various planning horizons.
Long-Term Planning
Multiyear organizational planning that focuses on high-level strategic decisions, such as facility location, product mix, product design, and supply chain network design.
Intermediate Planning
Production planning covering a horizon of 6 to 18 months (such as Aggregate Planning) that establishes output targets typically expressed in monthly product-family quantities.
Short-Term Planning
Operational planning spanning 6 months or less down to daily or hourly schedules, encompassing Master Production Scheduling (MPS), Materials Requirement Planning (MRP), and shop-floor execution systems.
Aggregate Planning
Intermediate-range planning that determines monthly or quarterly production, workforce, and inventory levels for a family or broad category of products over a horizon of approximately 12 months.
Chase Strategy
An aggregate planning strategy that matches the production rate to demand in each period using workforce adjustments, overtime, or subcontracting, with the primary objective of minimizing inventory holding costs.
Level Strategy
An aggregate planning strategy that maintains a constant production rate and workforce size throughout the planning horizon, using inventory accumulation and shortages to absorb demand fluctuations, with the primary objective of minimizing capacity change and smoothing costs.
Ending Inventory Formula
The inventory balancing relationship expressed as Ending Inventoryt=BIt+Ot−Dt−BOt−1, where BIt is beginning inventory, Ot is output, Dt is demand, and BOt−1 is prior backorders; negative values indicate current backorders.
Backorder (BOt)
Unmet customer demand occurring in period t that is not cancelled and is planned to be fulfilled in a subsequent period when additional capacity or inventory becomes available.
Disaggregation
The process of breaking down an intermediate aggregate production plan into specific individual end items and shorter time buckets (such as weekly output schedules) to construct the Master Production Schedule.
Master Production Schedule (MPS)
A formal, disaggregated short-term schedule specifying established production requirements, exact quantities, and timing for specific finished products in accordance with the aggregate plan.
Rough-Cut Capacity Planning (RCCP)
The capacity verification process used alongside the Master Production Schedule (MPS) to validate whether critical work centers, labor, and machine resources have sufficient capacity to achieve planned production.
Materials Requirement Planning (MRP)
A planning and scheduling methodology that translates the Master Production Schedule into time-phased net requirements for purchasing and producing dependent demand components, determining what is needed, how much is needed, and when it is needed.
Independent Demand
Demand for finished goods and end items that comes directly from external market demand, customer orders, or forecasts and is independent of the demand for any other product.
Dependent Demand
Demand for parts, assemblies, subcomponents, and raw materials that is directly derived from and calculated based on the production schedules of higher-level parent items or finished goods.
Bill of Materials (BOM)
A structured list specifying all raw materials, subassemblies, intermediate components, and ingredients—along with the precise quantity of each—required to manufacture one unit of a finished product.
Product Structure Tree
A hierarchical diagram illustrating the parent-component relationships and levels of assembly required to manufacture an end product, with the finished good positioned at Level 0.

MRP Explosion
The computational step in Materials Requirement Planning where higher-level assembly requirements are systematically decomposed through the Bill of Materials to calculate gross requirements for lower-level components and raw materials across time.
Planned Orders
Primary output reports generated by an MRP system that designate a time-phased schedule detailing the exact amount and timing of future manufacturing releases and purchasing orders.
Enterprise Resource Planning (ERP)
An integrated computer software system that coordinates and shares real-time data across enterprise-wide business functions—including accounting, sales, purchasing, and manufacturing—utilizing a centralized common database (e.g., SAP, Oracle).