1/30
Flashcards covering civil and architectural engineering stages of construction, site clearance, plant equipment, shallow and deep foundations, residential concrete slab workflows, and structural frame elements.
What are the three commencing tasks involved in site works and setting out?
Clearing the site
Setting out the building
Establishing a datum level
During site levelling, what key features does the land surveyor establish survey pegs for?
The land surveyor determines the original ground level and marks survey pegs for drains, pipes, cables, and the main sewage treatment plant (MSTP).
To what depth must the topsoil be sterilised during site clearing according to Building Regulations?
The top 300mm must be sterilised to contain plant life and decaying vegetation.
According to site clearance rules, what size trees must be cleared and how far beyond the site boundary must rubbish be cleared?
Trees and saplings of girth up to 300mm (measured 1m above ground level) must be removed, and rubbish cleared up to 50m beyond the periphery of the cleared area.
To what depth must the roots of trees and saplings be grubbed out during site clearance?
Roots must be removed to 600mm below ground level, 300mm below formation level, or 150mm below subgrade level, whichever is lowest, followed by backfilling, ramming, and levelling.
Why is a power shovel unsuitable for surface excavation, and what equipment is used instead?
A power shovel excavates against a vertical face or bank; for surface excavation, a skimmer is used.
How does the digging action of a backhoe differ from that of a face shovel?
A backhoe bucket works towards the chassis and is emptied by swinging away to invert the bucket, whereas a face shovel digs forward against a face away from the chassis.

What type of excavating machine is shown, featuring a long boom with a bucket suspended and operated purely by cables?
A dragline excavator (typically used for large open excavations beyond the reach of a backhoe and in open-cast mining).
For what type of excavation is a clamshell (crane-and-grab) suitable, and on which material can it not be used?
It is used for deep excavations of limited area on all soil types except rock.

Which earth-moving machine shown in the image can excavate, load, haul, and dump materials in a single cycle?
A scraper.
What controls the bucket movement in a trench digger compared to a traditional cable backhoe?
The bucket is controlled by hydraulic rams instead of cables and pulleys.
What are the five main criteria for selecting a foundation type and shape?
How do shallow foundations differ from deep foundations in their method of transferring structural load?
Shallow foundations transfer load directly to the earth at the base of the substructure column or wall, whereas deep (piled) foundations penetrate through incompetent upper soil layers to competent load-bearing strata or rock.
What are the typical mix proportions, thickness, and characteristic strength of lean concrete (blinding)?
Mix proportions: 1:3:6 (cement : sand : aggregate) by volume Thickness: 50–75mm Characteristic strength: approximately 5–10MPa
What is the function of lean concrete (blinding or mud mat)?
It provides a clean, level, and dry non-structural working platform over excavated ground and isolates the reinforcement and fresh concrete from soil contact to maintain specified cover.
Under which ground conditions are pad foundations unsuitable?
Loose sands, loose gravels, and filled areas.
When is a raft foundation preferred over pad or strip foundations?
When soils have low bearing capacity and when single column loads are heavy, spreading the structural loads over a single large base to reduce load per unit area.
What is a grade beam (beam foundation) and what does it do?
A reinforced concrete beam component that transmits load from a bearing wall into spaced foundations, such as pile caps or caissons.
What are the three main stages of driven pile installation?
In footing excavation, what is the definition of 'controlled fill'?
Fill that is required to support structures or associated pavements, and for which the engineering properties are controlled.
What requirement applies when a service pipe passes through an edge beam outside of its middle third?
The beam depth and/or reinforcement must be increased to compensate for the reduction in section capacity.
How must ground be prepared under a cast-in shower or bath drainage recess in a foundation slab?
The ground must be dug out beneath the recess so that full footing thickness is preserved.
What is the minimum overlap required when joining sheets of damp-proofing membrane (DPM)?
A minimum lap of 200mm.
What are two reasons for screeding and compacting a sand bed beneath a slab before laying the DPM?
Why is concrete cured, and how can moisture be retained during curing?
Concrete is cured to achieve its specified strength, durability, and water-tightness; it is kept moist by covering with wet hessian or spraying regularly with water.
What are the typical storey heights for car parks, residential buildings, and office buildings?
Car parks: 2.6m Residential buildings: 3.1m Office buildings: 3.6m and above
What is the typical span range between vertical supports in concrete buildings?
Generally between 5 and 12m.
What are the typical thickness ranges for reinforced concrete slabs and load-bearing walls?
Slabs: 160–250mm Walls: 150–400mm
What is the typical width range for concrete columns?
Generally 200–1000mm.

Based on the load transfer diagram, in what exact order do structural building elements transfer loads downward to the earth?
Slabs → Beams → Columns → Spread footings / foundations → Ground
What are the three core sequence steps to construct an in-situ reinforced concrete column or beam?