Flashcards covering civil and architectural engineering stages of construction, site clearance, plant equipment, shallow and deep foundations, residential concrete slab workflows, and structural frame elements.

31 Terms

1
New cards

What are the three commencing tasks involved in site works and setting out?

  1. Clearing the site

  2. Setting out the building

  3. Establishing a datum level


2
New cards

During site levelling, what key features does the land surveyor establish survey pegs for?

The land surveyor determines the original ground level and marks survey pegs for drains, pipes, cables, and the main sewage treatment plant (MSTP).

3
New cards

To what depth must the topsoil be sterilised during site clearing according to Building Regulations?

The top 300 mm300\,\text{mm} must be sterilised to contain plant life and decaying vegetation.

4
New cards

According to site clearance rules, what size trees must be cleared and how far beyond the site boundary must rubbish be cleared?

Trees and saplings of girth up to 300 mm300\,\text{mm} (measured 1 m1\,\text{m} above ground level) must be removed, and rubbish cleared up to 50 m50\,\text{m} beyond the periphery of the cleared area.

5
New cards

To what depth must the roots of trees and saplings be grubbed out during site clearance?

Roots must be removed to 600 mm600\,\text{mm} below ground level, 300 mm300\,\text{mm} below formation level, or 150 mm150\,\text{mm} below subgrade level, whichever is lowest, followed by backfilling, ramming, and levelling.

6
New cards

Why is a power shovel unsuitable for surface excavation, and what equipment is used instead?

A power shovel excavates against a vertical face or bank; for surface excavation, a skimmer is used.

7
New cards

How does the digging action of a backhoe differ from that of a face shovel?

A backhoe bucket works towards the chassis and is emptied by swinging away to invert the bucket, whereas a face shovel digs forward against a face away from the chassis.

8
New cards
<p>What type of excavating machine is shown, featuring a long boom with a bucket suspended and operated purely by cables?</p>

What type of excavating machine is shown, featuring a long boom with a bucket suspended and operated purely by cables?

A dragline excavator (typically used for large open excavations beyond the reach of a backhoe and in open-cast mining).

9
New cards

For what type of excavation is a clamshell (crane-and-grab) suitable, and on which material can it not be used?

It is used for deep excavations of limited area on all soil types except rock.

10
New cards
<p>Which earth-moving machine shown in the image can excavate, load, haul, and dump materials in a single cycle?</p>

Which earth-moving machine shown in the image can excavate, load, haul, and dump materials in a single cycle?

A scraper.

11
New cards

What controls the bucket movement in a trench digger compared to a traditional cable backhoe?

The bucket is controlled by hydraulic rams instead of cables and pulleys.

12
New cards

What are the five main criteria for selecting a foundation type and shape?

  1. Type of soil
  2. Building load
  3. Design
  4. Cost
  5. Technology
13
New cards

How do shallow foundations differ from deep foundations in their method of transferring structural load?

Shallow foundations transfer load directly to the earth at the base of the substructure column or wall, whereas deep (piled) foundations penetrate through incompetent upper soil layers to competent load-bearing strata or rock.

14
New cards

What are the typical mix proportions, thickness, and characteristic strength of lean concrete (blinding)?

Mix proportions: 1:3:61 : 3 : 6 (cement : sand : aggregate) by volume Thickness: 50–75 mm50\text{--}75\,\text{mm} Characteristic strength: approximately 5–10 MPa5\text{--}10\,\text{MPa}

15
New cards

What is the function of lean concrete (blinding or mud mat)?

It provides a clean, level, and dry non-structural working platform over excavated ground and isolates the reinforcement and fresh concrete from soil contact to maintain specified cover.

16
New cards

Under which ground conditions are pad foundations unsuitable?

Loose sands, loose gravels, and filled areas.

17
New cards

When is a raft foundation preferred over pad or strip foundations?

When soils have low bearing capacity and when single column loads are heavy, spreading the structural loads over a single large base to reduce load per unit area.

18
New cards

What is a grade beam (beam foundation) and what does it do?

A reinforced concrete beam component that transmits load from a bearing wall into spaced foundations, such as pile caps or caissons.

19
New cards

What are the three main stages of driven pile installation?

  1. Excavation: subsoil is excavated to reduce ground level for the pile cap
  2. Lifting: pile is tied by its lifting lug, lifted, and straightened
  3. Hammering: pile is driven using a drop hammer until refusal or a specified depth
20
New cards

In footing excavation, what is the definition of 'controlled fill'?

Fill that is required to support structures or associated pavements, and for which the engineering properties are controlled.

21
New cards

What requirement applies when a service pipe passes through an edge beam outside of its middle third?

The beam depth and/or reinforcement must be increased to compensate for the reduction in section capacity.

22
New cards

How must ground be prepared under a cast-in shower or bath drainage recess in a foundation slab?

The ground must be dug out beneath the recess so that full footing thickness is preserved.

23
New cards

What is the minimum overlap required when joining sheets of damp-proofing membrane (DPM)?

A minimum lap of 200 mm200\,\text{mm}.

24
New cards

What are two reasons for screeding and compacting a sand bed beneath a slab before laying the DPM?

  1. To accurately screed the ground level and establish a firm base
  2. To protect the damp-proofing membrane from being punctured by sharp rocks or subgrade during the pour
25
New cards

Why is concrete cured, and how can moisture be retained during curing?

Concrete is cured to achieve its specified strength, durability, and water-tightness; it is kept moist by covering with wet hessian or spraying regularly with water.

26
New cards

What are the typical storey heights for car parks, residential buildings, and office buildings?

Car parks: 2.6 m2.6\,\text{m} Residential buildings: 3.1 m3.1\,\text{m} Office buildings: 3.6 m3.6\,\text{m} and above

27
New cards

What is the typical span range between vertical supports in concrete buildings?

Generally between 55 and 12 m12\,\text{m}.

28
New cards

What are the typical thickness ranges for reinforced concrete slabs and load-bearing walls?

Slabs: 160–250 mm160\text{--}250\,\text{mm} Walls: 150–400 mm150\text{--}400\,\text{mm}

29
New cards

What is the typical width range for concrete columns?

Generally 200–1000 mm200\text{--}1000\,\text{mm}.

30
New cards
<p>Based on the load transfer diagram, in what exact order do structural building elements transfer loads downward to the earth?</p>

Based on the load transfer diagram, in what exact order do structural building elements transfer loads downward to the earth?

Slabs →\rightarrow Beams →\rightarrow Columns →\rightarrow Spread footings / foundations →\rightarrow Ground

31
New cards

What are the three core sequence steps to construct an in-situ reinforced concrete column or beam?

  1. Fix the steel reinforcement bars
  2. Fix the formwork
  3. Pour the concrete, allow it to cure, then strip/remove the formwork