QS ADVANCE COST ANALYSIS

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/48

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 10:06 AM on 10/19/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

49 Terms

1
New cards

Cost estimate

a prediction of the resources and money needed to complete defined work.

2
New cards

Budget

the approved amount allocated for a project or activity.

3
New cards

Actual Cost (AC)

cost already incurred for work performed.

4
New cards

Budget baseline

the approved time-phased budget used to compare performance.

5
New cards

Contract price

the amount agreed in the contract, subject to its terms and adjustments.

6
New cards

Indirect cost

cost supporting the project but not easily assigned to one work item, such as site utilities.

7
New cards

Overhead

general business or project-support expenses, depending on the estimate structure.

8
New cards

Contingency allowance

an allowance for identified uncertainty and risk; not simply extra profit

9
New cards

profit

the amount remaining for the contractor after applicable costs and expenses.

10
New cards

Bill of Quantities (BOQ)

a structured list of work items, descriptions, units, and quantities

11
New cards

Unit cost

the cost of one unit of completed work.

12
New cards

Unit rate

the price per unit used in pricing or measurement; check what it includes.

13
New cards

Resource cost

the cost of labor, materials, equipment, and other resources.

14
New cards

Cost driver

a factor that causes cost to change, such as quantity, wage rate, waste, or equipment hours.

15
New cards

Labor productivity

the amount of work produced per unit of labor input.

16
New cards

Cost variance

the difference between a reference cost and cost being compared

17
New cards

Cost overrun

spending or forecast cost exceeds the relevant budget or approved amount.

18
New cards

Cost underrun

spending or forecast cost is below the relevant budget or approved amount.

19
New cards

Forecast final cost

the latest prediction of total cost when the project is complete.

20
New cards

Estimate at Completion (EAC)

forecast of total project cost based on actual performance and remaining work.

21
New cards

Estimate to Complete (ETC)

estimated cost required to finish the remaining work.

22
New cards

Sensitivity analysis

tests how changes in one input affect the result.

23
New cards

Scenario analysis

compares results under different sets of assumptions.

24
New cards

Life-Cycle Cost Analysis (LCCA)

compares costs over an asset's life, including operation and maintenance.

25
New cards

Value engineering

a structured review to achieve required function at an appropriate life-cycle cost.

26
New cards

Prolongation cost

additional time-related cost caused by extended project duration.

27
New cards

Rework

work repeated or corrected because it did not meet requirements.

28
New cards

Cost analysis asks

Why is the cost changing, what does it mean, and what should we do?

29
New cards

Estimating output

a cost prediction based on quantities, rates, productivity, and assumptions.

30
New cards

Analysis output

an explanation, forecast, risk assessment, and recommended action.

31
New cards

Indirect/project costs

site management, temporary facilities, safety, utilities, and other support costs.

32
New cards

Company overhead

business-wide expenses allocated according to the estimating method.

33
New cards

Contingency

allowance for uncertainty and risk, managed under project rules.

34
New cards

Profit

the contractor's intended return after costs and applicable expenses.

35
New cards

Resource prices

cement, steel, fuel, equipment rental, or wages increase.

36
New cards

Productivity

crew output falls due to congestion, weather, poor planning, or skill gaps.

37
New cards

Waste and rework

incorrect installation, damage, or repeated work consumes extra resources.

38
New cards

Time

delays can extend supervision, equipment rental, temporary facilities, and financing costs.

39
New cards

EAC

total cost expected by project completion.

40
New cards

ETC

expected cost of the remaining work.

41
New cards

Cost cutting

reduces initial spending, sometimes by reducing quality or performance.

42
New cards

Value engineering

examines function, performance, safety, durability, and cost together.

43
New cards

LCCA

considers initial cost plus relevant operation, maintenance, replacement, and end-of-life costs.

44
New cards

Direct cost

cost clearly attributable to a specific work item, such as concrete, rebar, or installation labor

45
New cards

price escalation

an increase in resources over time

46
New cards

Estimating asks

How much should this work cost?

47
New cards

Quantity changes

additional scope, design revisions, or measurement errors.

48
New cards

Direct costs

materials + labor + equipment + subcontracted work tied to specific activities.

49
New cards

Forecast final cost

the latest estimate of total cost at completion