Comprehensive vocabulary flashcards covering schedule management principles, network diagramming techniques, activity duration estimation methods, critical path analysis, and PERT probabilistic calculations.
Project Schedule
A timetable that, at minimum, shows what needs to be done, start and end dates for all activities, who the resources are, and the project due date.
Project Schedule Baseline
The version of the project schedule that has been approved by the client; any modifications made after approval require the formal change control process.
Activity
A distinct, scheduled portion of work performed during the course of a project; it serves as a manageable chunk of work whose description typically begins with an actionable verb.
Duration
The total number of work periods (excluding holidays or other non-work periods) required to complete a schedule activity, typically expressed in workdays.
Project Network
A diagrammatic model consisting of circles or boxes (nodes) representing activities, and arrows (arcs) defining precedence relationships between activities.
Activity-on-Arrow (AOA)
A network diagramming method, also known as the Arrow Diagramming Method (ADM), in which arrows designate activities.
Activity-on-Node (AON)
A network diagramming method, also known as the Precedence Diagramming Method (PDM), in which nodes designate scheduled activities.
Milestone
A significant event in a project schedule with zero duration (0 days) that marks major deliverables and specific completion dates, requiring sponsor approval to change.
Path
A continuous sequence of connected activities in a project network diagram.
Predecessor Activity
An activity that logically comes before a dependent activity in a schedule.
Successor Activity
A dependent activity that logically comes after another activity in a schedule.
Finish-to-Start (FS)
The most common dependency relationship in PDM, where the predecessor activity must be completed before the successor activity can be started.
Finish-to-Finish (FF)
A dependency relationship where the predecessor activity must be completed before the successor activity can be completed.
Start-to-Start (SS)
A dependency relationship where the predecessor activity must be started before the successor activity can be started.
Start-to-Finish (SF)
The most uncommon dependency relationship in PDM, where the predecessor activity must be started before the successor activity can be completed.
Lead
The amount of time a successor activity can be advanced with respect to a predecessor activity, creating an overlap between sequential tasks.
Lag
The amount of time a successor activity will be delayed with respect to a predecessor activity, acting as required waiting time between activities.
Analogous Estimating
A duration or cost estimation method based on historical data and expert judgment from similar past projects; it is less accurate, less costly, and faster to complete.
Parametric Estimating
A method that calculates activity duration or cost using an algorithm and parameter data from past projects (Activity duration=quantity of work to be performed×labor hours).
One-Point Estimating (Bottom-Up)
An estimation method that calculates durations at the lowest Work Breakdown Structure (WBS) levels and aggregates them upward; it is the most accurate but also the most time-consuming approach.
Three-Point (PERT) Estimation
A probabilistic estimation technique that applies a weighted average of three estimates—optimistic, most likely, and pessimistic—to account for task uncertainty.
Optimistic Time Estimate (O or to)
The shortest possible length of time required to complete an activity under perfect or optimal conditions.
Most Likely Time Estimate (M or tm)
The most probable length of time required to complete an activity under normal circumstances.
Pessimistic Time Estimate (P or tp)
The longest possible length of time required to complete an activity under worst-case scenario conditions.
Critical Path Method (CPM)
A deterministic project planning method using single time estimates for each activity to identify the longest sequence of tasks and determine how to complete a project early.
Critical Path
The longest sequence of activities through the project network in terms of duration, which dictates the shortest possible project duration and has zero slack.
Forward Pass
A critical path method technique for calculating early start (ES) and early finish (EF) dates by working forward through the schedule model from the start date using the formula ES+t=EF.
Backward Pass
A critical path method technique for calculating late start (LS) and late finish (LF) dates by working backward through the schedule model from the end date using the formula LF−t=LS.
Early Start (ES)
The earliest possible point in time an activity can begin once all prior dependent activities have finished.
Early Finish (EF)
The earliest possible point in time an activity can complete, calculated as ES+t, where t is the activity duration.
Late Finish (LF)
The latest possible point in time an activity can be completed without delaying the planned project completion date.
Late Start (LS)
The latest possible point in time an activity can begin without delaying the project, calculated as LF−t.
Slack (Float)
The amount of time an activity not on the critical path can be delayed without delaying subsequent activities or the entire project, calculated as LS−ES or LF−EF.
Expected Activity Duration (EAD)
The PERT beta distribution formula used to calculate expected duration under uncertainty: EAD=6O+4M+P.
Standard Deviation (SD in PERT)
A measure of variation and uncertainty from the mean activity duration, estimated as one-sixth of the difference between pessimistic and optimistic estimates: SD=6P−O.
Variance (V in PERT)
The square of the standard deviation, calculated as V=(SD)2=(6P−O)2.