Comprehensive vocabulary flashcards covering schedule management principles, network diagramming techniques, activity duration estimation methods, critical path analysis, and PERT probabilistic calculations.

36 Terms

1
New cards

Project Schedule

A timetable that, at minimum, shows what needs to be done, start and end dates for all activities, who the resources are, and the project due date.

2
New cards

Project Schedule Baseline

The version of the project schedule that has been approved by the client; any modifications made after approval require the formal change control process.

3
New cards

Activity

A distinct, scheduled portion of work performed during the course of a project; it serves as a manageable chunk of work whose description typically begins with an actionable verb.

4
New cards

Duration

The total number of work periods (excluding holidays or other non-work periods) required to complete a schedule activity, typically expressed in workdays.

5
New cards

Project Network

A diagrammatic model consisting of circles or boxes (nodes) representing activities, and arrows (arcs) defining precedence relationships between activities.

6
New cards

Activity-on-Arrow (AOA)

A network diagramming method, also known as the Arrow Diagramming Method (ADM), in which arrows designate activities.

7
New cards

Activity-on-Node (AON)

A network diagramming method, also known as the Precedence Diagramming Method (PDM), in which nodes designate scheduled activities.

8
New cards

Milestone

A significant event in a project schedule with zero duration (00 days) that marks major deliverables and specific completion dates, requiring sponsor approval to change.

9
New cards

Path

A continuous sequence of connected activities in a project network diagram.

10
New cards

Predecessor Activity

An activity that logically comes before a dependent activity in a schedule.

11
New cards

Successor Activity

A dependent activity that logically comes after another activity in a schedule.

12
New cards

Finish-to-Start (FS)

The most common dependency relationship in PDM, where the predecessor activity must be completed before the successor activity can be started.

13
New cards

Finish-to-Finish (FF)

A dependency relationship where the predecessor activity must be completed before the successor activity can be completed.

14
New cards

Start-to-Start (SS)

A dependency relationship where the predecessor activity must be started before the successor activity can be started.

15
New cards

Start-to-Finish (SF)

The most uncommon dependency relationship in PDM, where the predecessor activity must be started before the successor activity can be completed.

16
New cards

Lead

The amount of time a successor activity can be advanced with respect to a predecessor activity, creating an overlap between sequential tasks.

17
New cards

Lag

The amount of time a successor activity will be delayed with respect to a predecessor activity, acting as required waiting time between activities.

18
New cards

Analogous Estimating

A duration or cost estimation method based on historical data and expert judgment from similar past projects; it is less accurate, less costly, and faster to complete.

19
New cards

Parametric Estimating

A method that calculates activity duration or cost using an algorithm and parameter data from past projects (Activity duration=quantity of work to be performed×labor hours\text{Activity duration} = \text{quantity of work to be performed} \times \text{labor hours}).

20
New cards

One-Point Estimating (Bottom-Up)

An estimation method that calculates durations at the lowest Work Breakdown Structure (WBS) levels and aggregates them upward; it is the most accurate but also the most time-consuming approach.

21
New cards

Three-Point (PERT) Estimation

A probabilistic estimation technique that applies a weighted average of three estimates—optimistic, most likely, and pessimistic—to account for task uncertainty.

22
New cards

Optimistic Time Estimate (OO or tot_o)

The shortest possible length of time required to complete an activity under perfect or optimal conditions.

23
New cards

Most Likely Time Estimate (MM or tmt_m)

The most probable length of time required to complete an activity under normal circumstances.

24
New cards

Pessimistic Time Estimate (PP or tpt_p)

The longest possible length of time required to complete an activity under worst-case scenario conditions.

25
New cards

Critical Path Method (CPM)

A deterministic project planning method using single time estimates for each activity to identify the longest sequence of tasks and determine how to complete a project early.

26
New cards

Critical Path

The longest sequence of activities through the project network in terms of duration, which dictates the shortest possible project duration and has zero slack.

27
New cards

Forward Pass

A critical path method technique for calculating early start (ESES) and early finish (EFEF) dates by working forward through the schedule model from the start date using the formula ES+t=EFES + t = EF.

28
New cards

Backward Pass

A critical path method technique for calculating late start (LSLS) and late finish (LFLF) dates by working backward through the schedule model from the end date using the formula LF−t=LSLF - t = LS.

29
New cards

Early Start (ESES)

The earliest possible point in time an activity can begin once all prior dependent activities have finished.

30
New cards

Early Finish (EFEF)

The earliest possible point in time an activity can complete, calculated as ES+tES + t, where tt is the activity duration.

31
New cards

Late Finish (LFLF)

The latest possible point in time an activity can be completed without delaying the planned project completion date.

32
New cards

Late Start (LSLS)

The latest possible point in time an activity can begin without delaying the project, calculated as LF−tLF - t.

33
New cards

Slack (Float)

The amount of time an activity not on the critical path can be delayed without delaying subsequent activities or the entire project, calculated as LS−ESLS - ES or LF−EFLF - EF.

34
New cards

Expected Activity Duration (EADEAD)

The PERT beta distribution formula used to calculate expected duration under uncertainty: EAD=O+4M+P6EAD = \frac{O + 4M + P}{6}.

35
New cards

Standard Deviation (SDSD in PERT)

A measure of variation and uncertainty from the mean activity duration, estimated as one-sixth of the difference between pessimistic and optimistic estimates: SD=P−O6SD = \frac{P - O}{6}.

36
New cards

Variance (VV in PERT)

The square of the standard deviation, calculated as V=(SD)2=(P−O6)2V = (SD)^2 = \left(\frac{P - O}{6}\right)^2.