CIVL4170 Risk Analysis Lecture 7&8 Notes
Lecture Overview
- Steps in Risk Management (ISO31000 Framework):
- Step 1: Establish the Context
- Step 2: Risk Identification
- Step 3: Risk Analysis
- Step 4: Risk Evaluation
- Step 5: Risk Treatment
- Focus: Risk Identification, Analysis, and Treatment (building upon Week 3's content).
Example Risk Assessment: Road Tanker Filling at a Depot
- Scenario: Assessing risks associated with filling a road tanker at a tanker depot.
- Depot Details:
- Receives petrol and diesel via underground pipeline from a local refinery.
- Pumps fuel from underground tanks into road tankers.
- Employs 20 workers in an office building.
- Has four truck loading bays, allowing simultaneous loading of four trucks.
- Equipped with spill kits at each loading bay.
- Utilizes mobile plant on-site.
- Safety Features:
- Operators present.
- Manual emergency stop button to halt flow to the loading bay.
- Overflow bunds to divert fuel into safe storage.
- Emergency clean-up equipment available.
- Unleaded Petrol:
- Solubility in Water: Nil
- Specific Gravity: 0.73-0.75
- Relative Vapour Density (air = 1): 3.5
- Vapour Pressure: 67 kPa at 37.8^\circ C
- Flash Point: -40^\circ C
- Flammability Limits: 1.4 - 7.4%
- Diesel:
- Solubility in Water: Nil
- Specific Gravity: 0.82-0.85
- Relative Vapour Density (air = 1): >1
- Vapour Pressure: <0.1 kPa at 20^\circ C
- Flash Point: >61.5^\circ C
Risk Assessment Scope Definition
- Project Name: Fuel transfer from bulk storage tank in tank farm to road tanker for transport to customer.
- Category:
- In Scope: As described above
- Out of Scope: Activities carried out on tank when out-of-service (e.g. cleaning, major refurbishment work etc). The process of loading the tanks from the ships
- People:
- Involved: Operators, maintenance teams, tanker drivers, potentially impacted on- and off-site personnel.
- Excluded: Unauthorized persons/trespassers, ship personnel.
- Locations:
- Included: Tank farm (Brisbane, Australia), plant tank bund areas, gas dispersion and blast zones, control room.
- Excluded: Areas outside bund and gas dispersion/blast zones.
- Equipment:
- Included: Tanks, piping, valves, instruments, control systems, bunds, road tankers.
- Excluded: Equipment used for tank/tanker maintenance or cleaning.
- Activities:
- Included: Filling, emptying, maintaining tanks/piping/instrumentation, on-site driving, connecting and filling road tankers.
- Excluded: Activities carried out on tank when out-of-service (e.g. cleaning, major refurbishment work etc). The process of loading the tanks from the ships
- Timeframes:
- Continuous: 24/7, 365 days/year, including shift handover considerations (typical tanker filling ~1 hour).
- Excluded: Potential major upgrades to tank, control system or site infrastructure in the future. Excludes decommissioning
- Environmental Considerations:
- Included: Brisbane climatic and environmental conditions (cyclones, heavy rain, strong winds, lightning, floods).
- Excluded: Extreme cold/snow/icing events, bushfires, earthquakes, tsunamis.
- Scenarios:
- Included: Loss of containment of liquid leading to fire/explosion, causing fatalities, environmental contamination, and asset losses.
- Excluded: Sabotage, minor injury or asset damage scenarios.
- Other Assumptions:
- Road tankers are in roadworthy condition, all people able to communicate in English, only petrol and diesel pumped into tankers.
Step 2: Risk Identification (HAZID)
- Hazard: Potential source of harm, often an energy source that, if uncontrolled, causes damage.
- Description of Hazard: Detailed information about the hazard (drop-down list).
- Description of Unwanted Event Scenario: Describes the initial loss of control or containment (the "knot" or "top event").
- Description of Causes: Details about the threats that could release the hazard.
- Description of the Consequence: The outcome or impact of an unwanted event.
Step 2: Risk Identification - Example Solutions
- Hazard Ref: Mechanical - moving vehicles or parts
- Description of Hazard: Large road tankers maneuvering onsite.
- Description of Unwanted Event Scenario: Unwanted contact between vehicle and operator.
- Causes: Driver error, driver illness, poor visibility, poor directions.
- Consequences: Operator/worker hit resulting in severe injury/fatality.
- Hazard Ref: Mechanical - moving vehicles or parts
- Description of Hazard: Large road tankers maneuvering onsite.
- Description of Unwanted Event Scenario: Uncontrolled contact between vehicle and pipework/storage tanks (major loss of containment).
- Causes: Driver error, driver illness, poor visibility, poor directions.
- Consequences: Major loss of containment of fuel.
- Hazard Ref: Mechanical - moving vehicles or parts
- Description of Hazard: Mobile road tankers connected to fixed plant.
- Description of Unwanted Event Scenario: Uncontrolled movement of vehicle during filling, disconnecting pipes (major loss of containment).
- Causes: Handbrake not applied/faulty, driver error.
- Consequences: Major loss of containment of fuel.
- Hazard Ref: Chemical - toxic, flammable/explosive
- Description of Hazard: Petrol which is flammable and explosive.
- Description of Unwanted Event Scenario: Overfilling tanker causing a major loss in containment.
- Causes: Inlet/outlet valve failure, blocked outlet pipe, faulty level sensors.
- Hazard Ref: Chemical - toxic, flammable/explosive
- Description of Hazard: Petrol which is flammable and explosive.
- Description of Unwanted Event Scenario: Leak in feed/outlet line or tank causing major loss in containment.
- Causes: Corrosion, fracking, external damage, loosened flange.
- Hazard Ref: Pressure - air, spring, liquid
- Description of Hazard: External fire or extreme temperatures.
- Description of Unwanted Event Scenario: Overpressurizing tank.
- Causes: Excessive external heat, failed pressure relief/vent equipment.
- Consequences: Vapour releases resulting in a vapour cloud explosion causing multiple fatalities/injuries, severe equipment damage and onsite environmental damage.
- Hazard Ref: Electrical - contact or arcing
- Description of Hazard: Static electricity.
- Description of Unwanted Event Scenario: Uncontrolled build-up of static electricity contacts petrol vapour.
- Causes: Incorrect material selection, poor grounding/earthing.
- Consequences: Static electricity contacts fuel vapour in top of tanker tanks causing it to explode.
- Hazard Ref: Environmental conditions – weather/climate
- Description of Hazard: Lightning Strikes.
- Description of Unwanted Event Scenario: Ignition of vapour during filling.
- Causes: Lightning strike on filling facility.
- Consequences: Explosion in tank farm, destroying tank causing potential multiple fatalities/injuries, severe equipment damage and onsite environmental damage.
- Hazard Ref: Gravity - falling or things falling
- Description of Hazard: Falling objects.
- Description of Unwanted Event Scenario: Overhead piping, fittings etc fall.
- Causes: Corrosion, wear and tear, damage, incorrect fitment.
- Consequences: Person injured when struck by objects falling from height.
- Hazard Ref: Human capability – slips, lapses, errors
- Description of Hazard: Mixing of incompatible liquids.
- Description of Unwanted Event Scenario: Petrol pumped into diesel tanker.
- Causes: Connection error, misidentification of liquid/tank.
- Consequences: Contaminated inventory that if undetected could be sold to customers causing damage to vehicles.
- Hazard Ref: N/A
- Description of Hazard: Liquid spills into bund.
- Description of Unwanted Event Scenario: Liquid Spills into bund and ignites causing a pool fire OR vaporizes to form a vapour cloud that explodes.
- Causes: n/a
- Consequences: Multiple fatalities/serious injuries, equipment damage and onsite environmental damage.
Recap Week 3
- A failed preventative (arresting) control CAN be a cause of an unwanted event, but a mitigating control CANNOT.
- A mitigating control mitigates the potential consequence AFTER the unwanted event. It does not impact the occurrence of the unwanted event.
- Example:
- Unwanted event: Person is exposed to rain
- Preventative Control: Towel
- Mitigating control: Raincoat
- Hazard descriptions should be specific, e.g., "Electrical equipment" is good but not 100% perfect and better than "Electrical energy" or "Use of equipment requiring 240V electricity"
- Unwanted event descriptions should also be specific, e.g., "Arc flash from electrical equipment or pump in confined space" is good. Could also be argued it's a consequence
- Multiple unwanted events are possible related to the use of equipment requiring 240V.
- Some hazards and unwanted event scenarios are less easy to describe.
- Brainstorming, open communication, revision, and quality checks are crucial.
- Focus is on the overall quality and spread of hazards/unwanted events, not whether one or two could have been described a bit better.
Step 3: Risk Analysis
- Determining impact and estimating likelihood gives an overall risk ranking.
Risk Ranking Matrix
- Likelihood: Rare, Unlikely, Moderate, Likely, Almost Certain
- Impact (Reputation/OH&S/Asset Damage/Environment/Legal): Minor, Moderate, Serious, Major, Catastrophic
- Matrix Example: (simplified, see slide 14 for full matrix)
- Catastrophic & Almost Certain = 50 (Unacceptable Risk)
- Minor & Rare = 2 (Broadly Acceptable)
- Risk Rating Categories:
- 15-50: High
- 10-14: Significant
- 4-9: Medium
- 1-3: Low
- Risk Acceptance Criteria:
- Unacceptable: Operations do not continue until risk is reduced.
- ALARP Band 1: Action as a high priority to reduce risk. Assign senior manager responsible.
- ALARP Band 2: Action to reduce risk where possible. Assign manager responsible to monitor and review.
- Generally Acceptable: Manage with regular monitoring and review.
- Tolerable Risk (only if risk reduction is impracticable or it's cost is grossly disproportionate to improvement gained).
Step 3: Risk Analysis - Example Solutions
- Builds upon the hazards and unwanted events identified earlier.
- Each scenario is assessed for potential impact across various categories (People, Assets, Environment, Reputation).
- An estimated likelihood is assigned to each scenario.
- The overall risk rank is then determined based on the impact and likelihood.
- Examples: (abbreviated, see slide 17/18 for full examples)
- Mechanical - moving vehicles or parts: Potential for fatality (Major Impact), Moderate Likelihood = Significant Overall Risk
- Chemical - toxic, flammable/explosive: Overfilling tanker (Catastrophic Impact), Likely Likelihood = Very High Overall Risk
- Pressure - air, spring, liquid: Overpressurising tank (Catastrophic Impact), Unlikely Likelihood = Very High Overall Risk
Step 4: Risk Evaluation
- Informed by the advice at the bottom of the Risk Ranking Matrix.
- May involve additional risk assessment tools (LOPA, Bowtie analysis).
- Evaluate your risks and consider controls required to effectively manage the risk
- Consider monitoring and review to ensure effectiveness.
Step 4: Risk Evaluation - Example Solutions
- Builds upon the risk analysis conducted in Step 3.
- Each risk is evaluated based on its overall risk rank.
- A determination is made as to whether the risk is acceptable, tolerable, or unacceptable.
- Examples: (abbreviated, see slide 20/21 for full examples)
- Mechanical - moving vehicles or parts (Significant Risk): Tolerable if actioned as a high priority and industry-recognized risk controls measures are implemented.
- Chemical - toxic, flammable/explosive (Very High Risk): Unacceptable – Operations do not to continue until risk is reduced. Risk treatment considerations should include inherently safe design and defense in depth analyses.
Step 5: Risk Treatment
- Critical step where the level of risk treatment is determined and how risks will be addressed.
- Consider inherently safer design options first.
- Specify what controls are needed.
- Ensure specified controls are actual controls (measuring something is NOT controlling it).
Step 5: Risk Treatment - Inherently Safe Design
- Requires engineers to adopt a critical thinking approach to challenging design assumptions using questions such as:
*Why are we doing this?
*Do we really have to perform this activity? If so, in this way?
*What is the aim?
*Can we eliminate, minimise, or substitute the hazardous material/activity?
*Can we moderate or simplify the process to reduce severity and improve detection and management of unwanted deviations?
Step 5: Risk Treatment - Hierarchy of Controls
- Elimination (most effective)
- Substitution
- Engineering Controls
- Administrative Controls
- PPE (least effective)
Step 5: Risk Treatment - Control Options
- Aim is to stay within safe operating/working conditions.
- Layers of Protection/Defense in Depth:
- Automated control systems that respond to unsafe situations (independent from worker).
- Activated to mitigate the consequences of unwanted event scenarios.
- Fast response of trained/skilled people to mitigate accident consequences.
- External public emergency personnel.
Step 5: Risk Treatment - What is a Control?
- A control is an object and/or human action that, of itself, will arrest or mitigate an unwanted event sequence.
- Sensors, training, alarms, and signage ALONE are generally not complete controls.
- A sensor, combined with an alarm AND an automated action OR an operator action IS a control.
- A traffic light combined with an operator response (i.e. driver stopping at a red light) IS A CONTROL
- A boom gate at a rail crossing is a control because: There is a measurement (oncoming trains) AND a decision (to halt road traffic) AND an action (lowering a physical barrier to block road traffic)
Step 5: Risk Treatment - Example Solutions
- Follow a systematic approach: first ISD followed by HOC.
- Sometimes there is a bit of overlap between ISD and controls
- Various ways to write it down clear/concise.
- Examples:
- Mechanical - moving vehicles or parts (Significant Risk):
- ISD: Front and rear cameras in trucks that cover blinds spots
- DID:
- Engineering controls: Design in walkways to separate human and vehicle traffic, Install bollards/barriers to protect walkways, Restrict Vehicle Speeds, Traffic light system to direct vehicle movements
- Administrative controls: (To be determined, could be driver training or route planning)
- PPE: (To be determined, could be high-vis clothing)
- Mechanical - moving vehicles or parts (Very High Risk):
- ISD: Spark free electronics/intrinsitically safe wiring, Front and rear cameras in trucks that cover blinds spots
- DID: (elimination, substitution, engineering, administrative, PPE) - Install bollards/barriers to protect walkways, Restrict Vehicle Speeds, Bund to capture and redirect spill to safe storage, LEL detection and shutdown system, Fire detection and mitigation system
- Mechanical - moving vehicles or parts (Very High Risk):
- ISD: Minimise slope of fill area, Engagement/tension sensor on coupling with interlock, Spark free electronics/intrinsitically safe wiring
- DID: (elimination, substitution, engineering, administrative, PPE) - Bund to capture and redirect spill to safe storage, Lower Expolosion Limit (LEL) dectection and shutdown system, Fire detection and mitigation system, Regular inspections of vehicles, Pre-start-up checks of flanges, joints, valves, connections to tanker, Pre-start check of condition of tanker, verification of alarms
- Petrol which is flammable and explosive:
- ISD: Consider minimising tank volume, Spark free electronics/intrinsically safe wiring
- DID: (add sub-headings were possible: elimination, substitution, engineering, administrative, PPE) - High level alarms and operator action, High level Safety Instrument System (SIS), LEL dectection and shutdown system Fire detection and mitigation system, Regular inspections of pipe work, Pre-start-up checks of flanges, joints, valves, connections to tanker , Pre-start check of condition of tanker, verification of alarms
- Petrol which is flammable and explosive:
- ISD: select non-corrosive pipe material, minimise joints in pipe work, use secure couplings
- DID: (add sub-headings were possible: elimination, substitution, engineering, administrative, PPE) - Phsyical barriers to protect pipework ,LEL dectection and shutdown system ,Fire detection and mitigation system, Regular inspections of pipe work, Pre-start-up checks of flanges, joints, valves, connections to tanker