Electrical Inspection, Testing & Documentation – Module 6 Detailed Notes
Pre-Work Survey: Before Any Electrical Inspection or Test
- Initial objective: Identify all conditions that could influence safety, compliance with BS 7671 and the success of subsequent tests.
- Core questions the inspector must answer:
- Which type of earthing arrangement (TN-S, TN-C-S, TT, IT) is employed?
- What is the maximum required disconnection time according to BS 7671 for the particular circuit and earthing system?
- Are the isolation and switching arrangements adequate, accessible and identifiable?
- What labels or notices (e.g.
- Main switch / isolator label,
- Circuit schedule,
- RCD test notice,
- Bonding labels,
- Warning notices for multi-earthing, PME etc.) are already present or still required?
- Is the measured or expected earth-fault loop impedance Z_s below the maximum permitted value given in BS 7671 tables?
- Is additional protection by RCD or RCBO mandatory (e.g. for socket-outlets ≤ 32\,\text{A}, buried cables < 50\,\text{mm} deep, special locations) or prudent because measured Z_s is borderline?
- Does the work fall within a special location (bathroom, swimming pool, medical location, agricultural, caravan, photovoltaic, EV charging, etc.) requiring further rules?
- What risks or hazards exist: access to live parts, moving machinery, moisture, confined space, lone working, vulnerable users, asbestos, combustible dust, working at height, etc.?
- Moral / legal duty of care: The inspector must ensure personal safety and the safety of others; failure may lead to electric shock, fire, prosecution or loss of licence.
- Always carry out SAFE ISOLATION before touching conductors:
- Identify the supply.
- Switch OFF.
- Lock off and place warning tags.
- Prove the instrument on a known source.
- Test the circuit is dead (phase–earth, phase–neutral, neutral–earth).
- Prove the instrument again.
- Dual working / buddy system recommended for higher-risk environments.
- Test equipment and leads must be GS38-compliant (shrouded connectors, finger guards, fused probes, CAT rating appropriate).
- Environment must not impair safety: adequate lighting, dry surface, secure footing, segregation from other trades.
Automatic Disconnection of Supply (ADS)
- Principal means of basic & fault protection in domestic and most commercial installations.
- Components:
- Protective earthing (earthing conductor, main earthing terminal).
- Protective equipotential bonding (main & supplementary bonding conductors).
- Automatic disconnection by protective devices (fuses, MCBs, RCBOs, RCDs) within required time if a fault drives exposed-conductive-parts above permissible touch voltage.
Continuity of Circuit Protective Conductors (CPCs) & Bonding
- Requirement: BS 7671 Regulation 643.2 – continuity of all protective conductors shall be verified.
- Definitions used in tests:
- Line conductor resistance = R_1.
- Neutral conductor resistance = R_n.
- Circuit protective conductor resistance = R_2.
- Typical conductors:
- CPC of a twin-&-earth final-circuit cable: copper, usually 1.5\,\text{mm}^2 (or same size as lives if smaller than 16\,\text{mm}^2).
- Main protective bonding: single-core, green-&-yellow, \ge 10\,\text{mm}^2 copper, linking MET to extraneous-conductive-parts (water, gas, oil, structural steel).
- Acceptable resistance limits for bonding conductors:
- Main bonding: \le 0.05\,\Omega between service point and MET.
- Supplementary bonding: \le 0.05\,\Omega between the two bonded parts.
- Adverse outcomes if continuity is absent: exposed metal may remain live during a fault, protective device may not operate → shock / fire risk.
Test Instrumentation
- Low-resistance ohmmeter (part of multifunction tester) applying typically 200\,\text{mA} test current.
- Must resolve changes of 0.01\text{–}0.05\,\Omega.
- Tester lead resistance should be null-zeroed or subtracted from readings.
CPC Continuity Test Methods
Method 1: "R1 + R2" (Short-Link Procedure)
- Purpose: Simultaneously confirms polarity, CPC continuity, and provides R1 + R2 for later Z_s determination.
- Steps (adapted to a lighting circuit example with Edison screw lampholder):
- Safely isolate the circuit being tested.
- At the distribution board, install a temporary link between the phase (line) conductor and CPC of the circuit under test.
- Go to each accessory (switch, lampholder, socket, junction box):
- With the circuit still isolated, place one tester probe on the earthing terminal, the other on the lampholder centre contact (or phase terminal of a socket).
- Switch ON local switches to include them in the test path.
- Record displayed resistance = R1 + R2 for that point.
- Remove the temporary link before re-energising.
- Compliance references: BS 7671 Regulations 643.2 and 643.6.
- Acceptable values: Derived from cable length & c.s.a. using R = \rho \dfrac{L}{A}; must be low enough that when added to external earth loop impedance Ze total Zs satisfies disconnection time tables.
Method 2: "Wander / Long-Lead" Method
- Used when a parallel earth path doesn’t exist yet (e.g. testing a single bonding conductor) or where linking is impractical.
- Steps:
- Attach one end of a long test lead to the MET or CPC at the consumer unit.
- Route the lead safely to the remote point (tap, radiator, accessory, second building, etc.).
- Measure resistance between the remote conductive part and the long lead return.
- Subtract the resistance of the long lead itself to obtain actual conductor resistance.
- Additional uses: circuit identification, polarity confirmation, live conductor continuity (when paired with phase identification bar or tone generator).
Using R1 + R2 to Predict Earth-Fault Loop Impedance Z_s
- Relationship: Zs = R1 + R2 + Ze
where Z_e is external earth impedance measured at the origin. - If calculated Z_s (or measured directly later by loop tester) ≤ tabulated maximum for the protective device and earthing system, ADS will operate within required time.
- Typical disconnection times:
- Final circuits ≤ 32\,\text{A} in TN systems: 0.4\,\text{s}.
- Distribution circuits or TT system: 5\,\text{s} (unless RCD provides faster cut-off).
- If Z_s is too high: options include reducing circuit length, increasing c.s.a., fitting RCD/RCBO, additional bonding, or re-designing earthing.
Continuity of Live Conductors (Line & Neutral)
- Live conductors must also be electrically continuous; breaks could produce overheating, arcing, or single-pole isolation hazards.
- Same ohmmeter and procedures as CPC continuity, ensuring correct polarity and inter-connections.
Ring Final Circuit Continuity (BS 7671 643.2.1-(ii))
- Construction: Twin conductors leave the MCB/RCBO, loop through each accessory, then return to the same terminals, forming three complete rings (line, neutral, CPC).
- Purpose of test: Detect broken rings or unauthorized inter-links that could overload cable segments.
- Instrument: Low-resistance ohmmeter capable of discerning changes of 0.05\,\Omega.
- Three-Step Regimen (only Step 1 covered in transcript – included here in full context for completeness):
- Step 1 – End-to-End Resistance
- Isolate, identify and disconnect all line, neutral and CPC conductors of the ring.
- Measure each loop separately:
• R1 (line), Rn (neutral), R_2 (CPC). - Expectations:
• R1 \approx Rn (same c.s.a.).
• R2 larger if CPC is smaller; for 2.5 mm²/1.5 mm² T&E, R2 \approx 1.67\,R_1.
- Step 2 – Cross-Connected (“Figure-of-Eight”) Test (implied)
- Join one end of line to the opposite end of neutral; measure resistances at every socket between the remaining open ends; values should be consistent (theoretical mean = \tfrac{R1+Rn}{4}).
- Step 3 – Repeat with Line-CPC Cross (verifies polarity & CPC integrity).
- Interpretation: Abnormal readings pinpoint breaks, interconnections, high-resistance joints or wrongly wired accessories.
Practical, Ethical & Regulatory Implications
- Document every reading on the Electrical Installation Certificate (EIC) or Minor Works Certificate; include test instrument serial numbers and calibration dates.
- Ethical responsibility: Accurate records enable future electricians to assess safety; falsification can lead to injury, death, legal action.
- Real-world relevance: Proper continuity and loop impedance ensure MCBs/RCDs trip fast enough to prevent fire, especially with modern high-fault currents from PME supplies.
Connections to Earlier & Wider Learning
- Builds on principles of Ohm’s Law, resistivity, and protective devices discussed in previous modules (e.g. Module 3 Cable Sizing & Module 4 Overcurrent Protection).
- Provides groundwork for forthcoming topics: Insulation Resistance, Polarity, Earth-Fault Loop Impedance measurement, RCD testing, Certification & Part P compliance.
- Acceptable bonding resistance: \le 0.05\,\Omega.
- Relationship: Zs = R1 + R2 + Ze.
- Typical ring final ratios: R2 \approx 1.67\,R1 for 2.5/1.5 T&E.
- Disconnection times (TN final circuits ≤ 32\,\text{A}): 0.4\,\text{s}; (distribution circuits): 5\,\text{s} unless RCD provides faster protection.
- Resistive calculation: R = \rho \dfrac{L}{A} (copper resistivity \rho \approx 17.2\times10^{-9}\,\Omega\,\text{m}).
Checklist for Documentation
- Record:
- Earthing arrangement type.
- Protective device ratings & types.
- Conductor sizes, materials, routes.
- Test instrument identifiers & calibration.
- All measured values: R1, R2, Rn, R1+R2, Ze, Z_s.
- Labels installed / updated.
- Deviations & remedial actions.
- Sign & date certificate; obtain client acknowledgment; retain copies for statutory period.