Note
0.0
(0)
Rate it
Take a practice test
Chat with Kai
undefined Flashcards
0 Cards
0.0
(0)
Knowt Play
Explore Top Notes
Organelles and Functions
Note
Studied by 68 people
5.0
(1)
Ideals and Types of Democracy
Note
Studied by 31 people
5.0
(1)
Simple Thunderstorm Hazards
Note
Studied by 6 people
5.0
(1)
NaOH Titration Flashcards
Note
Studied by 1 person
5.0
(1)
Chapter 20: Poverty and the Distribution of Income
Note
Studied by 21 people
5.0
(1)
LESSON 2:HUMAN RESOURCE PLANNING
Note
Studied by 69 people
5.0
(1)
Home
234- Burn and Velocity Charts
234- Burn and Velocity Charts
Burn Charts Overview
Essential agile tracking visuals;
always
appear on ACP exams.
Two main types:
Burn Up Chart
Burn Down Chart
Burn Up Chart
Tracks
work completed
over time.
Axes: X = iteration/sprint; Y = cumulative story-points finished.
Lines:
Scope line: total points; may rise if scope increases (e.g., 100 \rightarrow 120 points).
Progress line: points actually completed each iteration.
Reading tip: vertical value at any iteration = total points
done
.
Use when asked “How much work has been finished?”
Burn Down Chart
Tracks
work remaining
over time.
Axes: X = time units (days/sprints); Y = story-points left.
Lines:
Blue/ideal: planned burn rate.
Red/actual: real burn rate.
Reading tip: vertical value at any day = points
left to do
.
Use when asked “How much work is still outstanding?”
Velocity Chart
Shows team’s story-points completed per iteration.
Pattern typically stabilizes after several sprints (team “finds its groove”).
Average height of bars = team velocity.
Example: iterations level off near 16\text{–}17 points ➔ velocity \approx 17.
Planning use: select backlog items whose total points ≤ velocity for next sprint.
Common Exam Calculation
Given: average velocity = 18 points/iteration.
Backlog: 250 remaining points.
Required iterations = \lceil 250 / 18 \rceil \approx 14.
Each iteration lasts 1\text{–}4 weeks ➔ project duration estimate = 14 iterations × iteration length.
Exam Tips
Memorize: “Up = completed, Down = remaining.”
When a question mentions
showing progress done
➔ choose Burn Up.
When a question mentions
work left
➔ choose Burn Down.
Velocity questions often test: average calculation, iterations needed, or capacity planning.
Expect at least one scenario requiring interpretation of these charts without showing the actual graphic—recognize them by description.
Note
0.0
(0)
Rate it
Take a practice test
Chat with Kai
undefined Flashcards
0 Cards
0.0
(0)
Knowt Play
Explore Top Notes
Organelles and Functions
Note
Studied by 68 people
5.0
(1)
Ideals and Types of Democracy
Note
Studied by 31 people
5.0
(1)
Simple Thunderstorm Hazards
Note
Studied by 6 people
5.0
(1)
NaOH Titration Flashcards
Note
Studied by 1 person
5.0
(1)
Chapter 20: Poverty and the Distribution of Income
Note
Studied by 21 people
5.0
(1)
LESSON 2:HUMAN RESOURCE PLANNING
Note
Studied by 69 people
5.0
(1)