234- Burn and Velocity Charts
Burn Charts Overview
- Essential agile tracking visuals; always appear on ACP exams.
- Two main types:
- Burn Up Chart
- Burn Down Chart
Burn Up Chart
- Tracks work completed over time.
- Axes: X = iteration/sprint; Y = cumulative story-points finished.
- Lines:
- Scope line: total points; may rise if scope increases (e.g., 100 \rightarrow 120 points).
- Progress line: points actually completed each iteration.
- Reading tip: vertical value at any iteration = total points done.
- Use when asked “How much work has been finished?”
Burn Down Chart
- Tracks work remaining over time.
- Axes: X = time units (days/sprints); Y = story-points left.
- Lines:
- Blue/ideal: planned burn rate.
- Red/actual: real burn rate.
- Reading tip: vertical value at any day = points left to do.
- Use when asked “How much work is still outstanding?”
Velocity Chart
- Shows team’s story-points completed per iteration.
- Pattern typically stabilizes after several sprints (team “finds its groove”).
- Average height of bars = team velocity.
- Example: iterations level off near 16\text{–}17 points ➔ velocity \approx 17.
- Planning use: select backlog items whose total points ≤ velocity for next sprint.
Common Exam Calculation
- Given: average velocity = 18 points/iteration.
- Backlog: 250 remaining points.
- Required iterations = \lceil 250 / 18 \rceil \approx 14.
- Each iteration lasts 1\text{–}4 weeks ➔ project duration estimate = 14 iterations × iteration length.
Exam Tips
- Memorize: “Up = completed, Down = remaining.”
- When a question mentions showing progress done ➔ choose Burn Up.
- When a question mentions work left ➔ choose Burn Down.
- Velocity questions often test: average calculation, iterations needed, or capacity planning.
- Expect at least one scenario requiring interpretation of these charts without showing the actual graphic—recognize them by description.