Colorado Court of Appeals, Div. I; opinion by Judge Berman (Nov. 23 1983, reh’g denied Dec 15 1983; cert. granted Mar 26 1984).
Citation: 678 P.2d 1061; later reviewed in Tull v. Gundersons, Inc. (Colo. 1985).
Nature of suit: Contractor (Gundersons) seeks lost profits & consequential damages after owner (Ptarmigan Investment Co. et al.) breaches golf-course construction contract.
Plaintiff–Appellant: Gundersons, Inc. – S.D. corporation, 18 yrs experience building golf courses.
Defendants–Appellees: James H. Tull, H. McGraw, T. Peck, et al.; Ptarmigan Investment Co. (Colorado general & limited partnerships) plus related investors.
Trial court acknowledged breach but awarded only the 10 % retainage; denied lost-profit & consequential claims.
Gundersons appealed. Court of Appeals reversed & remanded: lost profits proven with reasonable certainty; two categories of consequential damages recoverable.
July 26 1979: Bid accepted; contract price 1,294,129.
Aug 6 1979: Work commences.
Aug 28 1979: Gun Barrel Mortgage agrees to finance (never consummated).
Aug 30 1979: AIA “Standard Form of Agreement” executed (date contract formed per trial court).
Nov 1979: ~1⁄3 of project complete; winter stoppage; payments to date 391,544 (10 % retainage withheld).
Mar 15 1980: Owner still unfunded; contractor suspends operations.
Action filed: breach of contract—claiming expectation interest (lost profits) + incidental/consequential losses (equipment leases, superintendent salary, mitigation bids).
Whether plaintiff proved lost profits with "reasonable certainty."
Whether trial court erred in denying consequential damages for:
a. Superintendent’s salary,
b. Long-term equipment lease payments,
c. Expenses incurred seeking substitute contracts.
Lost profits granted: contractor satisfied evidentiary burden.
Consequential damages: equipment-lease costs & mitigation expenses recoverable; superintendent salary not recoverable (avoidable loss).
Cause remanded for entry of appropriate awards.
Lost-profit recovery requires proof with “reasonable certainty”; speculative or remote figures disallowed (Lee v. Durango Music; Power Equipment v. Fulton).
Formula from Comfort Homes v. Peterson:
\text{Damages} = \text{Contract Price} - (\text{Payments Made} + \text{Cost to Complete})
Breach alone warrants at least nominal damages (General Ins. Co. v. Colo. Springs).
Purpose of damages: place non-breaching party where it would be but for breach (expectation interest).
Incidental & consequential losses also recoverable (UCC §2-715 rationale adopted in common-law cases).
Duty to Mitigate: injured party must use reasonable means to limit loss; reasonable mitigation costs themselves are compensable (Hoehne Ditch Co.).
• Prima facie: show payment; burden then shifts to defendant to prove unreasonableness (Hoehne standard).
President testified from 18 yrs experience; broke remaining work into discrete components (greens, tees, irrigation, cart paths, landscaping, etc.) using original supplier quotes.
Estimated cost to complete 600,000 \text{–} 609,923.
Historical margin: original bid built in ≈35\% profit over cost.
Calculation examples:
\text{Lost Profit} = 1,294,129 - 391,544 - 600,000 = 302,585
\text{or}~1,294,129 - 391,544 - 609,923 = 292,662 (≈34 % of remaining contract value).
Superintendent’s salary (Dec 1979–Mar 1980)
Retained in hope of future projects, not indispensable to Ptarmigan job.
Expense avoidable; failure to lay off = failure to mitigate → not recoverable.
Equipment lease payments
Long-term leases dedicated to Ptarmigan; Dec 1 1979–Mar 1980 payments unavoidable.
Distinguished from Uinta Oil (where equipment was purchased & depreciation avoided).
Recoverable to restore plaintiff’s position.
Mitigation bidding costs
Plaintiff presented invoices/receipts (travel, bid bonds, estimating) for pursuing alternate golf-course contracts.
Met prima facie burden; defendant offered no evidence of excessiveness → costs recoverable.
Comfort Homes: central precedent for construction-contract damages; formula applied.
General Ins. Co.: reaffirms that uncertainty as to amount does not bar recovery where breach & damage proven.
Hoehne Ditch: establishes burden-shifting framework on mitigation expenses.
Uinta Oil Refining: distinguishes recoverability of capital purchases vs. non-cancellable leases.
Contractors should maintain granular cost records; component breakdowns bolster "reasonable certainty."
Long-term equipment leasing can transfer breach risk to owner, if leases are job-specific & non-cancellable.
Employers must seriously consider layoffs or re-assignment to satisfy mitigation duty.
Owners must secure financing before contract execution; failure exposes them to full expectancy & consequential damages.
Upholding expectation damages incentivizes contractual reliability and economic efficiency.
Court respects corporate separateness (Gundersons vs. related Fairway Leasing) absent veil-piercing grounds—promoting predictability in closely-held ventures.
Contract price: 1,294,129
Payments received: 391,544 (≈30.3 % of contract).
Retainage rate: 10\%.
Cost-to-complete projections: 600,000 \text{–} 609,923.
Lost-profit range: 292,662 \text{ to } 302,585 (≈34-35 % margin).
Equipment-lease exposure period: 4 months (Dec 1979 – Mar 1980).
Lost profits demand reasonable certainty, not mathematical precision; detailed component estimates plus historical margins suffice.
Expectation measure: contract price minus (payments + avoided costs).
Consequential damages include unavoidable post-breach costs & reasonable mitigation expenses.
Duty to mitigate can both:
• bar recovery of avoidable losses (superintendent salary), and
• allow recovery of mitigation costs (bidding expenses).
Distinguishing between capital investments and non-cancellable leases affects damage entitlement.
Gundersons, Inc. v. Tull, 678 P.2d 1061 (Colo. App. 1983)
Comfort Homes, Inc. v. Peterson, 37 Colo.App. 516, 549 P.2d 1087 (1976)
General Ins. Co. v. City of Colorado Springs, 638 P.2d 752 (Colo. 1981)
Hoehne Ditch Co. v. John Flood Ditch Co., 76 Colo. 500, 233 P. 167 (1925)
Uinta Oil Refining Co. v. Ledford, 125 Colo. 429, 244 P.2d 881 (1952)
Lee v. Durango Music, 144 Colo. 270, 355 P.2d 1083 (1960)
Power Equipment Co. v. Fulton, 32 Colo.App. 430, 513 P.2d 234 (1973)