JM

Gundersons, Inc. v. Tull (1983) – Study Notes

Case Overview
  • Colorado Court of Appeals, Div. I; opinion by Judge Berman (Nov. 23 1983, reh’g denied Dec 15 1983; cert. granted Mar 26 1984).

  • Citation: 678 P.2d 1061; later reviewed in Tull v. Gundersons, Inc. (Colo. 1985).

  • Nature of suit: Contractor (Gundersons) seeks lost profits & consequential damages after owner (Ptarmigan Investment Co. et al.) breaches golf-course construction contract.

Parties
  • Plaintiff–Appellant: Gundersons, Inc. – S.D. corporation, 18 yrs experience building golf courses.

  • Defendants–Appellees: James H. Tull, H. McGraw, T. Peck, et al.; Ptarmigan Investment Co. (Colorado general & limited partnerships) plus related investors.

Procedural Posture
  • Trial court acknowledged breach but awarded only the 10 % retainage; denied lost-profit & consequential claims.

  • Gundersons appealed. Court of Appeals reversed & remanded: lost profits proven with reasonable certainty; two categories of consequential damages recoverable.

Chronology & Key Facts
  • July 26 1979: Bid accepted; contract price 1,294,129.

  • Aug 6 1979: Work commences.

  • Aug 28 1979: Gun Barrel Mortgage agrees to finance (never consummated).

  • Aug 30 1979: AIA “Standard Form of Agreement” executed (date contract formed per trial court).

  • Nov 1979: ~1⁄3 of project complete; winter stoppage; payments to date 391,544 (10 % retainage withheld).

  • Mar 15 1980: Owner still unfunded; contractor suspends operations.

  • Action filed: breach of contract—claiming expectation interest (lost profits) + incidental/consequential losses (equipment leases, superintendent salary, mitigation bids).

Issues on Appeal
  1. Whether plaintiff proved lost profits with "reasonable certainty."

  2. Whether trial court erred in denying consequential damages for:
    a. Superintendent’s salary,
    b. Long-term equipment lease payments,
    c. Expenses incurred seeking substitute contracts.

Holdings
  • Lost profits granted: contractor satisfied evidentiary burden.

  • Consequential damages: equipment-lease costs & mitigation expenses recoverable; superintendent salary not recoverable (avoidable loss).

  • Cause remanded for entry of appropriate awards.

Governing Legal Principles
  • Lost-profit recovery requires proof with “reasonable certainty”; speculative or remote figures disallowed (Lee v. Durango Music; Power Equipment v. Fulton).

  • Formula from Comfort Homes v. Peterson:
    \text{Damages} = \text{Contract Price} - (\text{Payments Made} + \text{Cost to Complete})

  • Breach alone warrants at least nominal damages (General Ins. Co. v. Colo. Springs).

  • Purpose of damages: place non-breaching party where it would be but for breach (expectation interest).

  • Incidental & consequential losses also recoverable (UCC §2-715 rationale adopted in common-law cases).

  • Duty to Mitigate: injured party must use reasonable means to limit loss; reasonable mitigation costs themselves are compensable (Hoehne Ditch Co.).
    • Prima facie: show payment; burden then shifts to defendant to prove unreasonableness (Hoehne standard).

Evidence Supporting Lost-Profit Award
  • President testified from 18 yrs experience; broke remaining work into discrete components (greens, tees, irrigation, cart paths, landscaping, etc.) using original supplier quotes.

  • Estimated cost to complete 600,000 \text{–} 609,923.

  • Historical margin: original bid built in ≈35\% profit over cost.

  • Calculation examples:
    \text{Lost Profit} = 1,294,129 - 391,544 - 600,000 = 302,585
    \text{or}~1,294,129 - 391,544 - 609,923 = 292,662 (≈34 % of remaining contract value).

Consequential-Damage Analysis
  1. Superintendent’s salary (Dec 1979–Mar 1980)

    • Retained in hope of future projects, not indispensable to Ptarmigan job.

    • Expense avoidable; failure to lay off = failure to mitigate → not recoverable.

  2. Equipment lease payments

    • Long-term leases dedicated to Ptarmigan; Dec 1 1979–Mar 1980 payments unavoidable.

    • Distinguished from Uinta Oil (where equipment was purchased & depreciation avoided).

    • Recoverable to restore plaintiff’s position.

  3. Mitigation bidding costs

    • Plaintiff presented invoices/receipts (travel, bid bonds, estimating) for pursuing alternate golf-course contracts.

    • Met prima facie burden; defendant offered no evidence of excessiveness → costs recoverable.

Relationship to Precedent & Doctrinal Connections
  • Comfort Homes: central precedent for construction-contract damages; formula applied.

  • General Ins. Co.: reaffirms that uncertainty as to amount does not bar recovery where breach & damage proven.

  • Hoehne Ditch: establishes burden-shifting framework on mitigation expenses.

  • Uinta Oil Refining: distinguishes recoverability of capital purchases vs. non-cancellable leases.

Practical Implications
  • Contractors should maintain granular cost records; component breakdowns bolster "reasonable certainty."

  • Long-term equipment leasing can transfer breach risk to owner, if leases are job-specific & non-cancellable.

  • Employers must seriously consider layoffs or re-assignment to satisfy mitigation duty.

  • Owners must secure financing before contract execution; failure exposes them to full expectancy & consequential damages.

Ethical / Philosophical Considerations
  • Upholding expectation damages incentivizes contractual reliability and economic efficiency.

  • Court respects corporate separateness (Gundersons vs. related Fairway Leasing) absent veil-piercing grounds—promoting predictability in closely-held ventures.

Numerical & Statistical References
  • Contract price: 1,294,129

  • Payments received: 391,544 (≈30.3 % of contract).

  • Retainage rate: 10\%.

  • Cost-to-complete projections: 600,000 \text{–} 609,923.

  • Lost-profit range: 292,662 \text{ to } 302,585 (≈34-35 % margin).

  • Equipment-lease exposure period: 4 months (Dec 1979 – Mar 1980).

Key Takeaways for Examination
  • Lost profits demand reasonable certainty, not mathematical precision; detailed component estimates plus historical margins suffice.

  • Expectation measure: contract price minus (payments + avoided costs).

  • Consequential damages include unavoidable post-breach costs & reasonable mitigation expenses.

  • Duty to mitigate can both:
    • bar recovery of avoidable losses (superintendent salary), and
    • allow recovery of mitigation costs (bidding expenses).

  • Distinguishing between capital investments and non-cancellable leases affects damage entitlement.

Principal Citations
  • Gundersons, Inc. v. Tull, 678 P.2d 1061 (Colo. App. 1983)

  • Comfort Homes, Inc. v. Peterson, 37 Colo.App. 516, 549 P.2d 1087 (1976)

  • General Ins. Co. v. City of Colorado Springs, 638 P.2d 752 (Colo. 1981)

  • Hoehne Ditch Co. v. John Flood Ditch Co., 76 Colo. 500, 233 P. 167 (1925)

  • Uinta Oil Refining Co. v. Ledford, 125 Colo. 429, 244 P.2d 881 (1952)

  • Lee v. Durango Music, 144 Colo. 270, 355 P.2d 1083 (1960)

  • Power Equipment Co. v. Fulton, 32 Colo.App. 430, 513 P.2d 234 (1973)