Exam - 230227
Question 1
- Critical Path Identification:
- CP = A-B-C-E-G-I = 26 days
- Crashing Procedure:
- Shorten activities on the critical path with the lowest crashing cost per day, prioritizing earlier activities in case of identical costs.
- Crashing Steps and Costs:
- C(2) - 1000 SEK (2 * 500)
- A(1) - 1000 SEK
- G(1) - 1000 SEK
- E(1) - 1500 SEK
- Total Crashing Costs:
- 4500 SEK
- Crashing Diagram Shape:
- The curve typically steepens as it approaches the minimum project duration due to increasing crashing costs.
- Managerial Use:
- Facilitates discussion on optimal crashing, focusing on 'knee points' to balance duration reduction and cost.
Question 2
- EVA Calculations (End of Day 4):
- PV = 1600 €
- EV = 1200 €
- AC = 1600 €
- CPI = EV/AC = 0.75
- SPI = EV/PV = 0.75
- Budget Estimation:
- Scenario 1 (Less Realistic): Total project costs = AC + (Original budget - EV)/CPI = 3467 €
- Scenario 2 (More Realistic): Total project costs = AC + (Original budget - EV)/1 = 3000 €
- SPI vs. CPM:
- SPI indicates delays (0.75 < 1).
- CPM shows the project is on schedule due to float in Activity B.
- EVA doesn't differentiate between critical and non-critical activities.
- Analytical Note to Sponsor (Scenario 2):
- Schedule deviation on non-critical activity, cost overrun due to one-off event.
- Forecast: Project duration = 7 days, Total project costs = 3000 €.
Question 3
- Payback Period Calculation:
- Payback Period = Total Investment / Annual Net Cash Flow
- Project 1:
- Total Investment = 20 MSEK + 6 MSEK = 26 MSEK
- Annual Net Cash Flow = 10 MSEK - 2 MSEK - 4 MSEK = 4 MSEK
- Payback Period = 26/4 = 6.5 years
- Project 2:
- Total Investment = 40 MSEK + 5 MSEK + 10 MSEK = 55 MSEK
- Annual Net Cash Flow = 10 MSEK
- Payback Period = 55/10 = 5.5 years
- Prioritization:
- Prioritize Project 2 for investment due to shorter payback period (5.5 < 6.5).
Question 4
- Top-Down Approach:
- Relies on past experience.
- Suitable when 100% accuracy is not essential.
- Bottom-Up Approach:
- Requires time and resource investment early on.
- Demands cooperation from key participants.
- Instrumental Approach to Benefits Management:
- Rational perspective on benefits management.
- Sequential process by project/organization.
- Emphasizes measurability, evaluation process, organizational change, and performance.
- Assumes proper implementation leads to reaping benefits.
- Does not account for social and political dimensions.