Note
0.0
(0)
Rate it
Take a practice test
Chat with Kai
Explore Top Notes
understanding community
Note
Studied by 56 people
5.0
(1)
Chapter 12 - Key Relationships
Note
Studied by 16 people
5.0
(2)
Ghost of Christmas Past
Note
Studied by 1 person
5.0
(1)
The pearl vocabulary, by John Steinbeck. All chapters (copy)
Note
Studied by 1 person
5.0
(1)
Chapter 1: Foundations of American Democracy
Note
Studied by 593 people
5.0
(10)
House + Home
Note
Studied by 8 people
5.0
(1)
Home
Exam - 230227
Exam - 230227
Question 1
Critical Path Identification:
CP = A-B-C-E-G-I = 26 days
Crashing Procedure:
Shorten activities on the critical path with the lowest crashing cost per day, prioritizing earlier activities in case of identical costs.
Crashing Steps and Costs:
C(2) - 1000 SEK (2 * 500)
A(1) - 1000 SEK
G(1) - 1000 SEK
E(1) - 1500 SEK
Total Crashing Costs:
4500 SEK
Crashing Diagram Shape:
The curve typically steepens as it approaches the minimum project duration due to increasing crashing costs.
Managerial Use:
Facilitates discussion on optimal crashing, focusing on 'knee points' to balance duration reduction and cost.
Question 2
EVA Calculations (End of Day 4):
PV = 1600 €
EV = 1200 €
AC = 1600 €
CPI = EV/AC = 0.75
SPI = EV/PV = 0.75
Budget Estimation:
Scenario 1 (Less Realistic): Total project costs = AC + (Original budget - EV)/CPI = 3467 €
Scenario 2 (More Realistic): Total project costs = AC + (Original budget - EV)/1 = 3000 €
SPI vs. CPM:
SPI indicates delays (0.75 < 1).
CPM shows the project is on schedule due to float in Activity B.
EVA doesn't differentiate between critical and non-critical activities.
Analytical Note to Sponsor (Scenario 2):
Schedule deviation on non-critical activity, cost overrun due to one-off event.
Forecast: Project duration = 7 days, Total project costs = 3000 €.
Question 3
Payback Period Calculation:
Payback Period = Total Investment / Annual Net Cash Flow
Project 1:
Total Investment = 20 MSEK + 6 MSEK = 26 MSEK
Annual Net Cash Flow = 10 MSEK - 2 MSEK - 4 MSEK = 4 MSEK
Payback Period = 26/4 = 6.5 years
Project 2:
Total Investment = 40 MSEK + 5 MSEK + 10 MSEK = 55 MSEK
Annual Net Cash Flow = 10 MSEK
Payback Period = 55/10 = 5.5 years
Prioritization:
Prioritize Project 2 for investment due to shorter payback period (5.5 < 6.5).
Question 4
Top-Down Approach:
Relies on past experience.
Suitable when 100% accuracy is not essential.
Bottom-Up Approach:
Requires time and resource investment early on.
Demands cooperation from key participants.
Instrumental Approach to Benefits Management:
Rational perspective on benefits management.
Sequential process by project/organization.
Emphasizes measurability, evaluation process, organizational change, and performance.
Assumes proper implementation leads to reaping benefits.
Does not account for social and political dimensions.
Note
0.0
(0)
Rate it
Take a practice test
Chat with Kai
Explore Top Notes
understanding community
Note
Studied by 56 people
5.0
(1)
Chapter 12 - Key Relationships
Note
Studied by 16 people
5.0
(2)
Ghost of Christmas Past
Note
Studied by 1 person
5.0
(1)
The pearl vocabulary, by John Steinbeck. All chapters (copy)
Note
Studied by 1 person
5.0
(1)
Chapter 1: Foundations of American Democracy
Note
Studied by 593 people
5.0
(10)
House + Home
Note
Studied by 8 people
5.0
(1)