Production Operations Management Notes
Optimum Cost-Time Schedule Template for Exam V
- Legend:
- MNGT 3340 Production Operations Management
- Alt Gr
- CCCL
- SID EF
- Project Duration: Represents the overall time required to complete the project.
- Direct Costs: Costs directly attributable to project activities (e.g., labor, materials).
- Indirect Costs: Costs not directly tied to specific project activities (e.g., overhead, administration).
- Total Costs: The sum of direct and indirect costs.
Cost-Time Schedule
- Duration of 12: Direct Costs = 1200, Indirect Costs = 1000, Total Costs = 2200
- Duration of 11: Direct Costs = 1250, Indirect Costs = 900, Total Costs = 2150
- Duration of 10: Direct Costs = 1300, Indirect Costs = 800, Total Costs = 2100
- Duration of 9: Direct Costs = 1380, Indirect Costs = 700, Total Costs = 2080
Crashing Template for Exam V
- You will need to print this slide more than one copy.
- Indicates this is a "crashing" template.
Crashing Example 1
- Initial State
- Total Direct Cost: 1200
- Critical Path: A-C-E-F
- Time: 12
- Activities Changed
- Crashing Activities (A)
- A Crashed by 1 unit, increasing the Direct Costs +50
- Calculation
- Original Cost: 1200
- New Cost: 1200 + 50 = 1250
- Time
- Total Costs
Crashing Example 2
- State
- Total Direct Cost: 1250
- Time: 11
- Path A-C-E
- Crashing Activities (A)
- A Crashed by 1 unit, increasing the Direct Costs +50
- Calculation
- Original Cost: 1250
- New Cost: 1250 + 50 = 1300
- Time
- Total Costs