KE

Spearfish City Council Meeting pt2

Budget and Financial Overview

  • Transparency and Conservative Approach: Appreciation was expressed for the bar graphs and the provided transparency, highlighting the direction and history of financial matters.

    • The approach is described as "conservative," meaning not projecting overly big things, but accepting significant events and improving where necessary.

Project Updates and Closures

Unspecified Project Closeout

  • Walkthrough Completion: The project walkthrough was completed on January\, 2.

  • Minor Item Resolution: A few minor tasks awaiting favorable weather conditions have been completed.

  • Warranty Bond: The necessary warranty bond has been received.

  • Project Closure: The project is now ready to be closed out.

  • Warranty Date: The warranty date is comfortably set for January\, 2 because the project was mostly complete by that time.

Fire Station 1 Renovations

  • Budget Correction: The project was initially budgeted at a higher rate for 2024.

  • Roof Repairs: The cost for roof repairs came in at approximately 23,009.52.

  • Fire Alarm Replacement: Substantial savings were observed in this area.

    • System Right-sizing: The previous fire alarm system was