Budget at Completion (BAC)
- Definition: The original, total approved budget for the project.
- Calculation: No specific formula; often a straightforward calculation based on project scope (e.g., \text{BAC} = \text{cost per unit} \times \text{number of units} ).
- Example: A building project with 20 stories at $1 million per story has a BAC of $20 million (20,000,000).
Planned Value (PV)
- Definition: The budgeted cost of work that should have been completed by a specific point in time.
- Represents: How much money worth of work should have been done.
- Calculation: PV = \text{Planned Percent Complete} \times \text{BAC}
- Example: If PV is $100, $100 worth of work should have been done.
- Finding Planned Percent Complete: If a project is planned for ten days and five days have passed, the planned percent complete is 50% (\frac{5}{10} = 0.5 = 50\%%).
Earned Value (EV)
*Definition: The amount of money worth of work actually completed.
- Importance: Critical for Earned Value Management; an incorrect EV calculation will propagate errors through many other formulas.
- Calculation: EV = \text{Actual Percent Complete} \times \text{BAC}
- Example: An earned value of $60 means $60 worth of work has actually been done.
- Difference from PV: PV is what should have been done, while EV is what actually was done. If PV is $40 and EV is $60, you've done $20 more worth of work than planned, which is a good thing.
Actual Cost (AC)
- Definition: The actual amount of money spent on the project to date.
- Calculation: No specific formula; it's the sum of all costs incurred.
Cost Variance (CV)
- Definition: The difference between the earned value and the actual cost. It indicates whether the project is under or over budget.
- Calculation: CV = EV - AC
- Interpretation:
- Positive CV: Under budget (good).
- Negative CV: Over budget (bad).
- Definition: A measure of the cost efficiency of the project.
- Calculation: CPI = \frac{EV}{AC}
- Interpretation:
- CPI > 1: Under budget (good).
- CPI = 1: On budget.
- CPI < 1: Over budget (bad).
Schedule Variance (SV)
*Definition: Schedule Variance is the difference between the amount of work we should have done versus the amount of work actually done
- Calculation: SV = EV - PV
*Interpretation
- Positive: good, ahead of schedule
- Zero: on schedule
- Negative: behind schedule
*Definition: The rate of how we are meeting the project schedule.
- Calculation: SPI = \frac{EV}{PV}
- Interpretation:
- SPI > 1: Ahead of schedule.
- SPI = 1: On schedule.
- SPI < 1: Behind schedule.
- Example: Somebody comes to you at 1.2, you're 20% ahead of schedule. So it comes to point eight, you are 20% behind schedule.
Estimate at Completion (EAC)
- Definition: A forecast of the total cost of the project upon completion, based on current spending.
- Purpose: To predict total project cost.
- Calculation: EAC = \frac{BAC}{CPI}
- Interpretation:
- EAC < BAC: Project is expected to finish under budget.
- EAC > BAC: Project is expected to finish over budget.
- Example:
- BAC = $1,000 and EAC = $1,100: Project is forecast to be $100 over budget.
Estimate to Complete (ETC)
- Definition: A forecast of how much more money is needed to complete the project.
- Calculation: ETC = EAC - AC
- Example: If EAC is $1,000 and AC is $900, the ETC is $100 (another $100 is needed).
Variance at Completion (VAC)
- Definition: The difference between the original budget and the new forecasted budget.
- Calculation: VAC = BAC - EAC
- Interpretation:
*Positive VAC: Project may end at or under budget
*Negative VAC: The amount of over budget you'll be at
- Definition: The performance level needed to finish the project within the budget.
- Calculation: TCPI = \frac{BAC - EV}{BAC - AC}
- Interpretation:
- TCPI < 1: Easier to complete within budget; project can perform at a lower efficiency.
- TCPI = 1: Current performance must be maintained to finish on budget.
- TCPI > 1: Harder to complete within budget; project must improve performance.
- Example:
- TCPI = 0.8: Only need to work 80% as hard to finish on budget.
- TCPI = 1.2: Need to work 20% harder to finish on budget.