Indirect Costs of Standby or Delay Caused to Contractors

Indirect Costs of Standby or Delay for Contractors

Overview

  • Discussion on calculating indirect costs associated with standby or delay caused to a contractor.

  • Responsibility of costs falls on the owner.

Cost Categories

  • Direct Costs: Costs allocated directly to the construction project, including:   - Superintendent Costs: On-site supervision.   - Equipment Costs: Expenses for machinery used at the site.   - Material Costs: Expenses for materials being installed.   - Trailer Costs: Expenses for project site offices or trailers.

  • Indirect Costs: General costs of doing business that are not directly tied to the construction project but are essential, including:   - Home Office Costs: Costs associated with managing the project, including:     - Receptionist salaries.     - Accountant salaries.     - Legal team salaries or legal costs.     - Office supplies (e.g., paper, pencils, Xerox machines).   

Indirect Cost Calculation

  • Indirect costs can be complicated to quantify.

  • The ECLI (Ecclesiastical Construction Offer) formula was established by a federal case for calculating these costs, often referenced as overhead costs.

Formula Definition
  1. Calculate Project Percentage of Total Revenue:    - Formula: extProjectPercentage=racextTotalContractSumextTotalBillingsext{Project Percentage} = rac{ ext{Total Contract Sum}}{ ext{Total Billings}}    - Example: For a project worth $1,000,000 and total billings of $80,000,000:      - extProjectPercentage=rac1,000,00080,000,000=0.0125ext{Project Percentage} = rac{1,000,000}{80,000,000} = 0.0125 or 1.25%.

  2. Calculate Job-Related Overhead:    - Formula: extJobOverhead=extTotalOverheadimesextProjectPercentageext{Job Overhead} = ext{Total Overhead} imes ext{Project Percentage}    - Example: If total overhead is $3,000,000:      - extJobOverhead=3,000,000imes0.0125=37,500ext{Job Overhead} = 3,000,000 imes 0.0125 = 37,500.

  3. Calculate Daily Overhead:    - Formula: extDailyOverhead=racextJobOverheadextContractTimeext{Daily Overhead} = rac{ ext{Job Overhead}}{ ext{Contract Time}}    - Example: If the planned work duration is 100 days:      - extDailyOverhead=rac37,500100=375ext{Daily Overhead} = rac{37,500}{100} = 375 per day.

  4. Calculate Unabsorbed Overhead Due to Delay:    - Formula: extUnabsorbedOverhead=extDailyOverheadimesextNumberofDaysDelayedext{Unabsorbed Overhead} = ext{Daily Overhead} imes ext{Number of Days Delayed}    - Example: If the contractor is delayed for 14 days:      - extUnabsorbedOverhead=375imes14=5,250ext{Unabsorbed Overhead} = 375 imes 14 = 5,250.

Eligibility for Overhead Claims

  • To qualify for claiming unabsorbed overhead:   - There must be a suspension of work that results in an increase in total contract time.

  • If a contractor has float in their schedule and can absorb the delay, they cannot claim these costs, as these costs are already accounted for in the original contract planning.

Practical Example

  • Given project:   - Project value: $1,000,000   - Total revenue during the period: $80,000,000   - Total overhead for the period: $3,000,000   - Planned duration: 100 days   - Delay: 14 days

  • Calculation yields:   - Total damages for delay: $5,250 based on the unabsorbed overhead during suspension.

Legal Precedents and Regulations

  • Eichele Case: A federal case that set the precedent for overhead calculation methods.

  • Post-Eichele, the U.S. government established regulations for federal projects applying the ECLI forms.

  • Ohio Case: Follows the Eicle damages formula in state courts but recognizes that some overhead costs may not directly benefit the project:   - Examples:     - Costs for parties thrown to entertain stakeholders.     - Donations to charities unrelated to the project.   - Such costs are excluded from the total overhead calculation, reducing the overhead applicable to the project.

General Overview for Calculation Use

  • Applicability: ECLI damages are specifically designed for situations where all work stops (suspensions).

  • In practice, even during ongoing work, contractors may use likely damages to estimate actual costs incurred due to project delays.

  • Caution against double counting overhead:   - During claims using actual costs, do not use ECLI Formula if also applying the total cost method, as costs are included in both methodologies leading to double-counting.

Important Notes

  • Always evaluate overhead claims critically, especially when they involve detailed support from the contractors regarding specific overhead allocation.