TOC: Prerequisite Tree & Transition Tree
- Tools used to determine why, what, and how to change, and how to sustain it.
- Goal Tree, Current Reality Tree, Evaporating Cloud, Negative Branch Reservation, Future Reality Tree, Prerequisite Tree, Transition Tree, Strategy & Tactics Tree.
Necessary vs. Sufficient Thinking
- Necessary: "In order to…., we must…"
- Sufficient: "If…., Then…"
Pre-Requisite Tree (PRT)
- Used to achieve 'the impossible'.
- Necessity structure (CRT and FRT are sufficiency structures).
- Shows the minimum requirements to proceed.
PRT Building Blocks
- Arrows connect IOs from bottom to top.
- Obstacles depicted by "STOP" signs.
- Intermediate objectives (IOs) are component tasks.
- Top of tree signifies outcome.
PRT Objective
- Construction is like peeling an onion.
- Appended to the FRT at the point of injection.
- Can be a stand-alone tool.
- Accomplishing component tasks realizes PRT’s objective.
- Reflect sequence or precedence.
- Enablers for achieving the real objective.
Obstacles
- Can include insufficient knowledge, lack of resources, restrictive laws, or human resistance.
- Should be worded as conditions, not needs.
Reading a PRT
- Top to bottom:
- In order to…[OBJECTIVE or IO], we need to …[IO] because…[OBSTACLE].
- Bottom to top:
- We must…[LOWER IO] in order to be able to…[UPPER IO] to overcome [OBSTACLE].
Building a PRT
- Define the purpose.
- List obstacles.
- Map the implementation order.
- Implement.
Define PRT Purpose
List Obstacles and IOs
- Verbalize obstacles and IOs.
- IOs indicate actions to nullify obstacles.
Map Implementation Order
- Determine order to accomplish IOs.
Transition Tree
- Step-by-step details of implementation (Goldratt’s original concept).
Transition Tree Structure
- Repeating structure of stated need, existing reality, and action to satisfy the need.
Modern Concept of PRT/TRT
- Robust PRT is adequate as a stand-alone tool.
- Easier to visualize implementation by appending PRTs to FRT.
Managing Change as a Project
- Critical Chain Project Management (CCPM) improves project success by:
- Scheduling to minimize resource contention.
- Eliminating fixed deadlines for tasks.
- Using time buffers.
- Discouraging multitasking.
Summary
- PRT helps identify, organize, and sequence tasks for injections in FRT.
- Exposes obstacles and provides details for transformation.
- Successful change depends on leadership and behavioral modification.