Spread Sheet Modeling – The process of entering the inputs and decision variables into a spreadsheet and then relating them appropriately, by means of formulas, to obtain the outputs.

 

Phase 1 of Analysis – Analyst tries to envision the possible outcomes from an investment.                                               -  Analyst prepares estimates and forecast.

Phase 2 of Analysis – Analyst details underlying sources of risk (identify value drives and                                                           uncertainty. Forensic valuation analysis).

                                    -Analyst seeks ways to mitigate risks and monitors throughout the life of                                                   the project (sensitivity of value to risks).

 

Flaw of Averages: The average model input does not always give the average model output.

                                    May occur when a firm oversimplifies reality by fixating on a single                                              number – the mean.

                                    To avoid this the firm must start dealing in probability distributions.

 

Sensitivity Analysis Results Provide Us: The possible outcomes for a particular range of values of a variable. It assumes the other variables remain static and provides no information on the probability of each outcome occurring.

·      Tool Needed: Monte Carlo Simulation.

·      Sensitivity Analysis: Shows the relative importance of each of the variables and how the value of the project changes in response to changes in the value of each variable.

·      Primary Purpose: Identify how sensitive a model’s output is to changes in its inputs.

·      Evaluates how changes in input variables affect the outcome of a model or system.

 

Monte Carlo Simulation

·      Simulations

o   Incorporate probabilities or uncertainties to determine possible outputs.

o   Provides a distribution of results rather than one finite answer.

o   Useful in determining possible outputs as well as the risk or sensitivity involved.

o   Require assumptions about the distributions of input variables.

o   Particularly useful in estimating the impact of risk and uncertainty in quantitative analysis and decision making.

·      Variables:

o   Many variables can be random/have probability distributions.

·      Simulation Settings

o   The model used should have “uncertain variables.”

o   Increasing the number of trials in a Monte Carlo simulation generally increases the accuracy of the results.

·      Monte Carlo simulation is different from a deterministic model because Monte Carlo incorporates randomness and probabilities to model scenarios.

 

Probability Distributions

·      Distributions

o   Uniform_(min, max) --- EQUALLY LIKELY

o   Triangular_(min, most likely, max)

o   Normal_(mean, standard deviation)

o   Histogram_(min, max, {p})

o   Discrete_({x, x}, {p, p})

·      Continuous vs Discrete

o   Many of the distributions that are used are continuous while only one is discrete.

o   Continuous means to have a range of possible values with any value within the range being used, while discrete have certain possibilities without variance. (Examples: uniform, triangular, histogram, and normal).

 

Basic Premise of Monte Carlo Simulation: a random sample has the same characteristics as the entire population. Based on statistical inference where a sample of the population is analyzed when it is impossible to analyze the entire population.

 

Goal of a Simulation: to determine the statistical distribution of a result.

 

Risk Analysis

·      Simulation Outputs

§  Standard Deviation – measures how spread out the distributions is and is often a useful description of risk.

§  Percentiles

§  Mean – average value.

§  Probabilities

§  Correlation: measures the strength and direction of a relationship between two variables. 0 is weak, -1 to +1

·      Corr_(input row, table range)

·      High vs. Low Risk

o   Simulations with lower standard deviations have lower risk.

o   Percentiles will give us a good look at the range of possible outcomes.

§  25th percentile tells us that 25% of the values are below it, and 75% are greater than it.

§  Higher percentiles value wise are better for the risk of the company.

o   Probability section of results is manual input to tell us <,>, = a certain number

·      Uncertainty

o   Nothing is absolute, everything has risk.

 

Risk Analysis Methods

·      Scenario Analysis: Broadens the horizons of DCF (discounted cash flow) forcing the analyst to think about the many different futures that are possible.

·      Sensitivity Analysis: Shows the relative importance of each of the variables and how the value of the project changes in response to changes in the value of each variable.

·      Simulation Models: Are mathematical representations of the project that incorporates the uncertainty, perform calculations, and record the results to determine statistical data.

·      Decision Trees: Graphical representations of the relationships between various decision alternatives available and their possible outcomes over time.

 

Simulation:

·      Simulation uses random numbers to drive the whole process.

·      Probability distributions for input variables are the building blocks of spreadsheet simulation models.

o   Spreadsheet vs Simulation Model difference = in a simulation model at least one of the input variable cells in a simulation contains random numbers.

 

 

NPV should be accepted if a project earns a positive NPV.

 

Business Investment Decisions Based on the Net Result of the forecasted investment costs and expected future revenues.

 

Multi-period models have uncertainties that unfold or evolve over time (stock prices, growth).

 

NET PRESENT VALUE (NPV)

 

Strategic Decisions = longer time horizons (quarters, years) mergers, long-term investments.

Operational Decisions= short time frames (days, weeks) production schedule, sales forecasting.

 

Deterministic – does not have uncertainty.

·      Amanda’s portfolio of adding $5,000 each year to stocks and bonds.

 

 

Net Cash Flow = Total Costs – Total Revenue

 

NPV =NPV(discount rate cell, net cash flow years cells)

            NPV(B10, B34:37)

                                    B10 = 7.5% discount rate

                       

 

With Correlation little 2 by 2 table prod cost x prod cost = 1

                                                            Prod cost x main cost = 0.8