AJBAN Solar PV Project Outage Plan Notes
Project Overview
- Project Number: AJPV-3
- Project Name: AJBAN Solar PV Independent Power Project
- Location: Ajban 400 kV Electrical Special Facilities (ESF)
- Outage Plan Duration: February 15, 2026 - April 15, 2026
- Document Date: April 17, 2025
OPGW Outage Works
- Circuit: DHMG 400kV OHL feeder (Bay reference: C01) and TWPS 400kV OHL feeder (Bay reference: C39)
- AJPV-3 Bays: DHMG bay #C15 and TWPS bay #C05 will be LILO (Line In Line Out).
- Objective: Energization of AJPV-3 by LILO of DHMG OHL and TWPS OHL.
Energization Stages of DHMG OHL and TWPS OHL
ESF Readiness:
- Date: February 15, 2026
- Purpose: Preparation for DHMG-TWPS OHL shutdown for outage.
OTDR for OPGW:
- Timeline: 3 weeks after outage date (March 8, 2026)
- Scope: DHMG - AJPV3 gantry and TWPS - AJPV3 gantry.
Fiber Optic Cable Splicing and Telecom Communication:
- Location: AJPV3 gantry
- Objective: Establish telecom communication up to LDC/ECC (Load Dispatch Center/Emergency Control Center) via DHMG or TWPS.
- Testing: End-to-End Telecom Test between Main Station (AJPV3) and LDC/ECC (3 days), witnessed by TT (presumably a testing team).
Telecom Communication Link Establishment:
- Date: March 15, 2026
- Scope: Connection between AJP3 to LDC & ECC.
SCMS Integration:
- Date: April 15, 2026
- Scope: AJP3 - Station level SCMS (Substation Control and Monitoring System) signals and commands integration with LDC.
- Verification: Internal testing/verification of handshake between AJP3 SCMS and LDC.
OHL Loop Connections:
- Dates: February 15, 2026 - April 15, 2026
- Scope: Complete OHL Loop in /Loop out connections for AJPV-3 DHMG bay #C15 and TWPS bay #C05.
Documentation and Energization Clearance:
- Dates: February 15, 2026 - April 19, 2026
- Activities: Documentation, energization checklist completion, and energization clearance acquisition.
Protection and Telecom Modification Works at Remote Ends
- Locations: DHMG & TWPS, TRANSCO HQ2 or ARC/TCC Building/ TCAMC and Unit-III Pumping Station (ETCC)/ ETCAMC.
1. DHMG SS (Substation):
- PTW (Permit to Work): Issued for 400kV DHMG SS by a Telecom competent person.
- Disconnection: Disconnect and isolate power / control cables and patch cards from existing telecom panels.
- Panel Replacement: Dismantle existing telecom panels and install new telecom panels.
- Cabling: Cabling and switch on 48VDC supply for new telecom panels.
- Pre-commissioning: Pre-commissioning checklist and internal test report.
- Reporting: Submit internal telecom test report to TRANSCO telecom for approval.
- Commissioning: Telecom panel Commissioning works and SAT (Site Acceptance Test) witness.
- RTU Text Changes: RTU (Remote Terminal Unit) Text Changes at 400kV DHMG SS.
- Bay Name Changes: Bay name changes at overall MIMIC's.
- Integration: Integration of Protection Relays to RTU including Telecom signals.
- Relay Settings: Modification / Final Settings and Scheme Checks of Main 1 & Main 2 Relays at 400kV DHMG SS.
- Protection Works: Protection related works & Control wiring modification works and Scheme Checks at remote ends.
- Relay Testing:
- Main 1 Relay Component testing and Final setting adoption and Testing-DHMG.
- Main 2 Relay Component testing and Final setting adoption and Testing-DHMAG.
- Protection Scheme Checks: Protection Scheme and trip logic checks.
- Bay Name Changes: Bay name changes at SCMS, FMS, LCC, GIS & Gantry areas (if required).
- FMS Works: FMS (Facility Monitoring System) works and integration with master stations.
- End to End Testing:
- Main -1 & Main -2 End to End Testing (Secondary Injection)-for Circuit DHMG-AJPV3.
- Protection End To End By Secondary Injection-DHMAG to AJP3.
- Final Trip Test: Relay Final Setting final Trip Test including AR (Auto Reclose) cycle test -DHMG to AJP3.
2. TWPS SS (Substation):
- PTW: PTW for 400kV TWPSSS Telecom System modification and Testing at 400kV TWPS SS by Telecom competent person.
- Disconnection: Disconnect and isolate power / control cables and patch cards from existing telecom panels.
- Panel Replacement: Dismantle existing telecom panels and install new telecom panels.
- Cabling: Cabling and Switch on 48VDC supply for new telecom panels.
- Pre-commissioning: Pre-commissioning checklist and internal test report.
- Reporting: Submit internal telecom test report to TRANSCO telecom for approval.
- Commissioning: Telecom panel Commissioning works and SAT witness.
- RTU Text Changes: RTU Text Changes at 400kV TWPS SS.
- Bay Name Changes: Bay name changes at overall MIMIC's.
- Integration: Integration of Protection Relays to Scms including Telecom signals.
- Relay Settings: Modification / Final Settings and Scheme Checks of Main 1 & Main 2 Relays at 400kV TWPS SS.
- Protection Works: Protection related works & Control wiring modification works and Scheme Checks at remote ends.
- Relay Testing:
- Main 1 Relay Component testing and Final setting adoption and Testing-TWPS.
- Main 2 Relay Component testing and Final setting adoption and Testing-TWPS.
- Protection Scheme Checks: Protection Scheme and trip logic checks.
- Bay Name Changes: Bay name changes at SCMS, FMS, LCC, GIS & Gantry areas (if required).
- FMS Works: FMS works and integration with master stations.
- End to End Testing:
- Main -1 & Main -2 End to End Testing (Secondary Injection)-for Circuit 1.
- Protection End To End By Secondary Injection-TWPS to AJP3.
- Final Trip Test: Relay Final Setting final Trip Test including AR cycle test TWPS to AJP3.
3. TRANSCO HQ2 or ARC/TCC Building/ TCAMC
- Telecom System modification and Testing at TRANSCO HQ2 or ARC/TCC Building/ TCAMC.
- Telecom Module configuration.
- Test end to end test between AJPV3 and TCAMC & ETCAMC.
4. Unit-III Pumping Station (ETCC)/ ETCAMC
- Telecom System modification and Testing at Unit-III Pumping Station (ETCC)/ ETCAMC.
- Telecom Module configuration.
- Test end to end test between AJPV3 ETCAMC.
Stakeholders
- End User: TRANSCO
- EPC Contractor: POWERCHISA, 华东勘测设计研究院有限公司 (HUADONG ENGINEERING CORPORATION LIMITED)
- ESF Contractor: SIEMENS
- Owner: AL AJBAN Solar Energy, العجبان للطاقة الشمسية
- Owner's Engineer: FICHTNER
- Transmission: TɅQAɅ طاقة لشبكات النقل
- Consulting Engineers: ENERGO CONSULT L.L.C.
Key Integrations
- 400kV DHMG integration to LDC
- 400kV TWPS integration to LDC
- Modified Signal Checks up to LDC & Related LDC Integration works