Operations & Post-Implementation Review
Go-Live Criticality
- “Go-live” is one of the most critical milestones for ERP success.
- Requires completion of core tasks before system activation.
Stabilization Window
- Period from Go-Live until issues/problems diminish (≈ 90 days).
- Failure case: FoxMeyer Drug collapsed during stabilization; sued SAP for 500 million.
Five Areas of Stabilization
- Go-Live Readiness
- ERP Training
- Stabilization
- Post-Production Support
- Knowledge Transfer
Go-Live Readiness
- Clarifies progress & unresolved issues prior to activation.
- Assess: infrastructure, development, configuration, data conversion, testing, training, communications, operations, user preparedness.
- Collect input from project teams, users, and team leaders for executive review.
ERP Training
- All users trained with real data/examples; essential transactions before Go-Live, full training may continue after.
- Trainers: vendor staff, in-house personnel, or third-party specialists; sessions onsite or virtual.
Stabilization Phase
- Begins when software is live, initial training done, critical data converted.
- Characterized by long hours, many issues, high anxiety.
- Common complications:
• Undocumented customizations
• Business-process reengineering impacts
• Parallel run with legacy system (labor-intensive & confusing)
• Reconciliation between new ERP & old system outputs
Post-Production Support
- Formal support plan is as vital as development activities.
- Focus areas: training, data validation, data correction, patches/fixes, new features/upgrades.
Key Post-Implementation Support Activities
- Training: Help desk handles daily user assistance & issue tracking.
- Data validation: Periodic checks confirm correct usage & data-entry processes.
- Data correction: Identify & fix conversion/interface errors.
- Patches & fixes: Report bugs to vendor; vendor reproduces in clean environment.
- New features/upgrades: Controlled change process keeps system aligned with evolving business.
Knowledge Transfer
- Must span all ERP life-cycle phases: Requirements, Build, Go-Live, Stabilization, Ongoing Support.
- Ensures organization can maintain & enhance system after vendor disengagement.