PLN-7 PLD Week 15 Webinar – Residual & Appraisal Recap + Assignment 2 Surgery

Session Context

  • Week 15 “PLN-7 PLD” webinar: final recap of the six-week block + open “surgery” on Assignment 2.

  • Two halves of the morning:

    • Summary of taught material (esp. Part 2 – Residual & Development Appraisal).

    • Live Q&A on assignment, common pitfalls, report-writing and technical issues.

Over-Arching Intellectual Road-Map

  • Purpose of recap: pull scattered weekly learning into one “single-page” mental model.

  • Cognitive science note: humans forget ≈ 90 % of a taught session; last-heard items dominate recall ⇒ structured summaries are essential.

The Residual Method – Core Skeleton

  • Basic mnemonic: A−B=CA - B = C where

    • AA = Gross Development Value (GDV)

    • BB = Gross Development Cost (GDC)

    • CC = Residual (land bid/profit depending on treatment).

  • Illustrative Forbury Place case:

    • GDV ≈ £100 m

    • GDC ≈ £65 m

    • Residual ≈ £35 m

  • “Residual” from residue = money left after everything else – normally the land bid.

De-compressing the GDV (-A- block)
  • GDV = capital value of completed scheme.

  • Two principal valuation tools utilised inside GDV:

    1. Comparable/Comparative – £/m² capital evidence (easiest for houses).

    2. Investment Method (dominant for UK commercial property): NI×YP=CVNI \times YP = CV

    • NINI = net income (i.e. market rent).

    • YP=1yYP = \frac{1}{y} where yy = yield (decimal).

    • Interpreted as “years’ purchase” (investor’s desired pay-back period).

  • Yield–YP inverse logic: lower yield → larger YP → investor happy with longer pay-back; high risk (high yield) → short YP.

  • Sub-cases when rent < market:

    • Term & Reversion (two YPs, second one deferred).

    • Hardcore & Layer (horizontal slicing; top-slice deferred).

    • Cash-flow/DCF for multi-let complexity (finger PV approach).

  • Rationale for always valuing as an investment: maximises GDV → maximises land bid; even owner-occupiers assume letting & sale to prove viability.

Breaking Down the GDC (-B- block)
  • Mnemonic “BFF DLS” (Big Fat Farmers Die Lonely & Sad):

    1. Build costs (site prep → foundation → superstructure → fit-out).

    2. Fees (professionals; ≈ 10 % of build).

    3. Finance (compound interest).

    4. Developer’s profit (only if land is unknown; omit if profit is target).

    5. Letting fees (agency % of headline rent).

    6. Sale fees (disposal agent ≈ 1–1.5 %).

    7. Purchaser’s costs (SDLT + legal + agent for buyer ≈ 6 %).

Finance Mathematics & Phasing
  • Core formula: Interest factor =(1+i)n−1=(1+i)^n - 1 (then apply to principal).

  • Layered finance stack:

    • Senior debt (LTV %, e.g. 65 %) – cheapest.

    • Equity (developer’s own money) – higher “opportunity cost”.

    • Mezzanine (gap) – most expensive, borrowed late/short.

  • Diagram logic: build-phase funding vs. post-practical-completion void funding (100 % bullet loan at higher rate).

  • WACC (Weighted Average Cost of Capital): ∑(w<em>i×r</em>i)\sum (w<em>i \times r</em>i) where w<em>iw<em>i = proportion, r</em>ir</em>i = rate, gives single blended interest rate.

Position of Finance Line
  • Items above finance get interest; items below are end-of-scheme cash-outs (profit, sale fees, etc.).

From Surplus to Land Bid
  1. Compute surplus C=GDV−GDCC = GDV - GDC.

  2. Remove site finance & acquisition costs using PV of £1: PV=1(1+i)nPV = \frac{1}{(1+i)^n}.

  3. Divide by (1 + acquisition %), e.g. 1.045, to reach net land price (bid headroom).

Expressing Developer’s Return
  • Profit on Cost (PoC) target ≈ 15–25 %.

  • Profit on Value (PoV) target ≈ 10–15 %.

  • Report both to expose different messages (cost efficiency vs. capital uplift).

Critiquing the Basic Residual

  • Mnemonic “RESIDUAL” (rules-of-thumb, estimation, subjectivity, ignorance, dynamic, use of BCIS, aggregated error, lack of change).

  • Key limitations: static snapshot; ignores S-curves of spend & debt; high sensitivity to inputs; crude contingencies for risk.

Risk Landscape

Risk Categories
  • Process/Execution

  • Valuation/Market input

  • Macro-Market (systematic)

Assessment Tools
  • Heat-maps, qualitative matrices

  • Sensitivity ±10 %

  • Scenario analysis

  • Monte-Carlo

Mitigation Menu (illustrative)
  • Fixed-price contracts

  • Advance material purchase (with caveats: storage, theft, weather).

  • Hedging interest rates or FX.

  • Pre-lets / forward sales.

  • Contingency allowances (selectively on build, finance, etc.).

Sensitivity Analysis – Mechanics & Communication

  • Step-set: change one variable ±10 %, rerun model, record new bottom line, compute % change vs. base.

  • Visualise: compact comparative table, spider graph, or tornado diagram.

  • Embed full residuals in appendices; highlight altered cell & new outcome.

Alternative Dynamic Approaches

Technique

Mechanics

Insight

Discounted Cash-Flow (DCF)

Year/quarter columns; PV each net flow at finance rate.

NPV view (value today).

Period-by-Period (P-b-P)

Real-time cash; compute interest period-lag; PV only final land line.

Debt/time profile ("rev-counter").

Basic Residual

Lump-sum proxy.

Fast first-pass, minimal data need.

  • Selection depends on project stage: early feasibility → residual; post-design → DCF/P-b-P.

Financial Gearing – “Bike Gears” Metaphor

  • Higher bank leverage → lower equity input → amplified return on developer’s capital, despite higher absolute cost.

Assignment 2 – Practical Guidance & FAQs

Task Structure
  1. Produce residual to establish developer profit figure.

  2. Perform ±10 % sensitivity on specified variables.

  3. Critically evaluate sensitivity as a risk-management tool.

Common Clarifications
  • Need two critiques in Task 1: (i) adequacy of derived profit, (ii) critique of residual method.

  • Finance lines: separate for (a) preliminaries, (b) build (50 % factor), (c) 75 % of fees, (d) void.

  • Purchaser’s costs: can be shown in GDV or GDC; ensure not double-counted.

  • Land price in model: if given as gross (inc. SDLT & finance) place at bottom; or reverse-engineer to show detail.

  • Contingency: normally on build; may add separate contingency lines if justified (finance, fees).

  • Word-count: 3 000 +10 % upper margin; brevity valued.

  • Embedding spreadsheet: paste as picture/table in body; full Excel in appendix or linked PDF.

  • Profit metrics: include both PoC & PoV ranges to support critique.

  • Task-3 “risk-management” scope: interpret broadly – client & adviser perspective; relate to sensitivity and alternative/ complementary tools.

Report Writing & Presentation Tips

  • Use clear headings, short paragraphs, bullet points, bold/italic restraint.

  • Provide “intro–body–conclusion” flow; restate instructions to show you understood brief.

  • Appendices for large tables; reference them in text (“see Appx 1”).

  • Include assumptions & caveats (Red-Book style) but scaled to early-stage advice.

  • Graphically flag key numbers (shading/highlight) for reader speed.

Live Q&A Nuggets Captured

  • Monthly interest factor example: 7 % annual → three-month factor (1.07)0.25−1≈0.017(1.07)^{0.25} -1 \approx 0.017 (1.7 %).

  • Lawyers’ conveyancing fee ≈ 1–1.5 % (context for purchaser’s costs).

  • Land bid backward calc: assume flat 5 % SDLT for simplicity per brief.

  • Going >10 % over word-limit → automatic penalty; no direct penalty for being concise.

Key Take-Away Mind-Map (One-Page Memory Jogger)

  • Formulae: GDV−GDC=ResidualGDV - GDC = Residual; NI×YPNI \times YP; (1+i)n−1(1+i)^n -1; PV=1(1+i)nPV = \frac{1}{(1+i)^n}; WACC=∑w<em>ir</em>iWACC = \sum w<em>i r</em>i.

  • BFF DLS order; finance sits mid-table.

  • Risk tools: sensitivity (±10 %), scenarios, Monte-Carlo, heat-map.

  • Target returns: PoC 15–25 %; PoV 10–15 %.

  • Critical lens: static, assumption-heavy, error aggregation → justify contingencies & dynamic analyses later.

  • Assignment mantra: clarity, completeness, concision.


“Residual is a lump hammer – indispensable for the first strike, but keep the precision chisels (DCF, P-b-P) ready for later rounds.”