Section 4 - Contracts

Basic Scheduling Terms and questions

Key Word

Definition

Example

Contract

A legally enforceable agreement between two parties.

A contractor agrees to build a road for $30 million.

Contract Management

Managing the agreement to protect profit, reduce risk, and receive payment.

Tracking payment claims and project delays.

Profit

Money remaining after expenses are paid.

Revenue of $100,000 minus costs of $80,000 = $20,000 profit.

Risk

The possibility that something could cause loss or damage.

A subcontractor fails to finish on time.

Cash Flow

The movement of money into and out of a business.

Receiving payment before paying suppliers.

Scope of Work

The specific work a contractor is required to complete.

Installing 500 streetlights.

Variation

A change to the original scope, cost, time, or requirements.

The client requests 100 additional streetlights.

Dispute

A disagreement between parties about their contractual rights or obligations.

The client refuses to pay for additional work.

Offer

A clear proposal to enter into an agreement.

A contractor offers to build a pavement for $1.2 million.

Acceptance

The other party agrees to the offer without changing its terms.

The client accepts the $1.2 million offer.

Consideration

Something of value exchanged between parties.

The contractor provides construction services; the client provides payment.

Intention

Both parties intend to create a legally binding agreement.

A company signs a commercial construction contract.

Capacity

The parties have the legal ability and authority to enter into the contract.

An authorized company representative signs the agreement.

Certainty of Terms

The contract is clear enough to understand and enforce.

The contract clearly identifies scope, price, deadlines, and responsibilities.

Principal / Client

The party that commissions and pays for the project.

A state government building a road.

Head Contractor

The company responsible for delivering the overall construction project.

A general contractor managing road construction.

Subcontractor

A specialist company hired to complete part of the work.

An electrical company installing streetlights.

Superintendent / Contract Administrator

A person who administers the contract and assesses matters such as claims.

Reviewing a contractor's payment claim.

Architect / Engineer

A professional who prepares designs, drawings, and specifications.

An engineer designing a bridge foundation.

Supplier

A company that provides materials or equipment.

A company supplying concrete or steel.

General Conditions

Standard rules used in many contracts.

Payment, delays, and variations.

Special Conditions

Project-specific changes or additional requirements.

A special payment deadline.

Attachments

Supporting documents that explain the project.

Drawings, specifications, and scope of work.

Lump Sum / Fixed Price

A fixed amount for completing an agreed scope.

$500,000 to construct a parking lot.

Schedule of Rates

Payment based on units of work completed.

$400 per meter of drainage installed.

Cost Reimbursable / Cost Plus

Payment of actual costs plus an agreed fee or margin.

Actual costs of $100,000 plus a 10% fee.

Target Cost

An agreed target budget where savings or overruns are shared according to the contract.

The parties share savings if the project costs less than the target.

Question 1: Why do contracts matter in construction?

Answer: Contracts create legally enforceable agreements between parties.

Explanation: Construction projects require many companies to work together. Contracts clarify responsibilities, payment, deadlines, risks, and procedures for changes or disputes.

Question 2: What is a contract?

Answer: A legally enforceable agreement that creates rights and obligations between parties.

Explanation: Both parties agree to specific terms, and those terms may be enforced through the legal system.

Question 3: What are the six elements of a contract?

Answer:

  1. Offer

  2. Acceptance

  3. Consideration

  4. Intention to create legal relations

  5. Capacity

  6. Certainty of terms

Explanation: These elements help establish whether an agreement is legally binding.

Question 4: Who are the buyer and seller in construction?

Answer: The buyer is the principal or client. The seller is the contractor.

Explanation: The client pays for the work, while the contractor provides the construction services.

Question 5: What is the flow-down effect?

Answer: The transfer of requirements and obligations from the client to the head contractor and then to subcontractors.

Explanation: This helps ensure that subcontractors understand and accept the responsibilities necessary to deliver the project.

Question 6: What are the four domains of contract management?

Answer:

  • Tendering

  • Procurement

  • Head-contract administration

  • Subcontract administration

Explanation: These four areas cover contract formation and contract administration, both upstream and downstream.

Question 7: What is the purpose of a construction program?

Answer: To show the sequence, timing, and duration of project activities.

Explanation: It helps coordinate work, identify critical-path delays, and support extension-of-time claims.

Question 8: What is a variation?

Answer: A change to the original contract scope, cost, time, or requirements.

Explanation: Variations allow the parties to formally manage changes and adjust the contract when appropriate.

Question 9: What is an extension of time?

Answer: An adjustment to the contractual completion date when the contractor is entitled to additional time.

Explanation: It protects the contractor from certain delays caused by events covered by the contract.

Question 10: Why is cash flow important?

Answer: Contractors must pay workers, suppliers, and subcontractors while waiting for client payments.

Explanation: A profitable project can still experience financial problems if payments arrive too late.

Question 11: What is back-to-back risk transfer?

Answer: Passing relevant head-contract obligations and risks to subcontractors through their contracts.

Explanation: This helps prevent the head contractor from accepting obligations that cannot be managed or recovered from the subcontractor.

Question 12: Why must additional work be documented?

Answer: To establish the scope, authorization, price, and time impact of the change.

Explanation: Written documentation reduces misunderstandings and supports payment claims.

Question 1

What is the main purpose of a construction contract?

A. To eliminate all construction risks.

B. To guarantee that every project finishes early.

C. To establish legally enforceable rights and obligations between parties.

D. To replace project management.

Explanation: A contract defines responsibilities, payment, scope, deadlines, and procedures for managing changes and disputes.

Question 2

Which of the following is an element of a legally enforceable contract?

A. Construction equipment.

B. A project photograph.

C. Consideration.

D. A site meeting.

Explanation: Consideration means something of value is exchanged between the parties.

Question 3

What is the flow-down effect?

A. The client reduces the contract price.

B. The head contractor passes relevant requirements to subcontractors.

C. The subcontractor terminates the contract.

D. The project finishes ahead of schedule.

Explanation: Flow-down helps ensure subcontractors accept relevant responsibilities and obligations.

Question 4

Which contract model requires the contractor to complete both design and construction?

A. Construct Only.

B. Cost Plus.

C. Construction Management.

D. Design and Construct.

Explanation: Under Design and Construct, the contractor generally manages both the design and construction within the agreed scope.

Question 5

What is a payment claim?

A. A request to terminate the contract.

B. A request to change the project design.

C. A formal request for payment for work completed.

D. A report about subcontractor defects.

Explanation: Payment claims allow contractors to request payment according to the contract's payment mechanism.

Question 6

What is the purpose of a construction program?

A. To calculate employee salaries.

B. To replace the contract.

C. To plan and communicate the sequence and timing of project activities.

D. To eliminate the need for subcontractors.

Explanation: The program helps coordinate activities and supports delay and extension-of-time claims.

Question 7

What should a contractor do before performing additional work requested by the client?

A. Complete the work immediately.

B. Wait until project completion.

C. Document and obtain the required variation approval.

D. Ask the subcontractor to pay for it.

Explanation: Written approval helps establish the scope, price, and time impact of additional work.

Question 8

What is the main purpose of procurement?

A. To prepare the final project report.

B. To terminate subcontractors.

C. To select and contract with suitable subcontractors and suppliers.

D. To replace the client.

Explanation: Procurement obtains the resources and services needed to deliver the project at appropriate value and risk.

Question 9

Why should subcontractors be monitored after signing their contracts?

A. Because the head contractor has no responsibilities.

B. Because subcontractors always fail.

C. Because the head contractor remains accountable for delivering the project.

D. Because written contracts are unnecessary.

Explanation: Poor subcontractor performance can affect the head contractor's schedule, costs, quality, and obligations to the client.

Question 10

Which action best protects a contractor's profit?

A. Ignoring contract conditions.

B. Accepting every client request verbally.

C. Focusing only on the lowest price.

D. Managing scope, payment, variations, risks, and subcontractors effectively.

Explanation: Effective contract management protects entitlements and helps prevent unnecessary costs and financial losses.

Contract

A legally enforceable agreement.

Agreement to build a warehouse for $1 million.

Contract Management

Managing the agreement throughout the project.

Tracking claims, changes, and obligations.

Contract Formation

Creating and signing the contract.

Negotiating the price and scope.

Contract Administration

Managing the contract after signing.

Monitoring deadlines and payments.

Principal

The client who commissions and pays for the work.

A government agency.

Head Contractor

The company responsible for the overall project.

A general construction company.

Subcontractor

A company hired to complete part of the work.

An electrical contractor.

Scope of Work

The work that must be completed.

Installing 200 windows.

Tendering

Preparing and submitting an offer to the client.

Quoting $500,000 for construction.

Procurement

Selecting and contracting with suppliers or subcontractors.

Obtaining three concrete quotations.

RFQ

Request for Quotation.

Asking suppliers to price steel materials.

WBS

Work Breakdown Structure; divides work into smaller packages.

Separating a building project into electrical, plumbing, and concrete packages.

Cash Flow

Money entering and leaving a business.

Receiving client payments and paying workers.

Payment Claim

A formal request for payment.

Claiming $100,000 for completed work.

Variation

A change to the original contract.

Adding another floor to a building.

Extension of Time

Additional contractual time for completion, when entitled.

A qualifying delay moves completion by two weeks.

Liquidated Damages

A contractually specified amount for certain breaches, often late completion.

$1,000 per day of qualifying delay.

Security

Financial protection under a contract.

Retention or a bank guarantee.

Retention

Money withheld from payments as security.

The client holds 5% of each payment.

Insurance

Protection against specified losses.

Public liability insurance.

Back-to-Back Contract

A subcontract aligned with relevant head-contract obligations.

A subcontractor accepts the required completion date.

RFI

Request for Information.

Asking the engineer to clarify a drawing.

Qualification

An assumption, exclusion, or condition attached to an offer.

The price excludes temporary fencing.

Contract Departure

A proposed change to the client's contract terms.

Requesting 20-day payment terms instead of 45 days.

Critical Path

Activities that determine the project's earliest completion date.

A delayed foundation delays the entire building.

Float

Time an activity can be delayed without delaying project completion, based on the schedule.

An activity has three days of available float.

Dispute

A disagreement about contractual rights or obligations.

The client disputes a variation claim.

Back Charge

A cost charged to a subcontractor when contractually justified.

Recovering the cost of correcting defective subcontractor work.

Non-Conformance

Work that does not meet required standards or specifications.

Concrete fails to meet the specified strength.

Termination

Ending a contract according to its terms or applicable law.

A contract ends following a serious breach.