Comprehensive Project Planning and Trade Execution Study Guide
Fundamentals of Project Planning
A project plan is an essential management document that outlines all tasks to be completed within a project framework, clearly defining how each component fits into the overall workflow. It serves as an operational baseline to monitor execution, timing, task durations, task placement, and responsibility assignments.
Core Functions and Purpose
Task Identification: Formally defines and documents every specific task that must be undertaken to achieve project completion.
Temporal Scheduling: Specifies exact start dates, finish dates, and duration windows for each task.
Dependency and Sequencing Mapping: Maps out the strict logical sequence and order in which tasks must occur, highlighting critical interdependencies between distinct work items.
Workflow Overlap Analysis: Identifies which tasks can occur concurrently (in parallel) versus those that require strict linear completion.
Role Assignment: Designates the specific person, trade, or role responsible for executing each task.
Resource and Dependency Allocation: Regulates task allocation to guarantee that prerequisite dependencies are completely finished before dependent downstream tasks commence.
Governance and Monitoring Requirements
To maintain project control, a designated Project Manager (or equivalent supervisory role) must continuously monitor and manage the project plan. This governance ensures that:
Tasks are executed according to specified quality and procedural guidelines.
Schedules, critical path milestones, and overall timelines are strictly adhered to.
Financial resources and budgets are kept within approved limits.
Comprehensive Project Plan Specification
The structured project plan details all sequential steps, prerequisites (Work Prior to), and post-execution requirements (Work After) across eleven critical project roles.

Trade and Role Specifications (Sequencing 1 – 6)
1. Client
Sequencing Order: 1
Task: Consultation with the designer to produce kitchen design and to sign contract.
Work Prior to:
Confirm local council building rules.
Organise finances.
Work After:
Consultation during project as needed.
Pay fees.
Final site inspection for defects.
Completion sign off.
2. Designer / Project Manager
Sequencing Order: 2
Task: Design kitchen; Project management.
Work Prior to:
Consult with client and all other trades to organise install of kitchen as per design requirements, standards, and codes.
Work After:
Trades begin work on site.
Designer/Project Manager regularly visits site and communicates with trades and specialists.
Manages timeframe and budget.
3. Electrician
Sequencing Order: 3
Task: Install all electrical work and fittings.
Work Prior to:
All electrical outlets and connections finalised in plan.
Isolate all power to exposed cables and new work areas so all other trades can work safely.
Work After:
Rough in of services after carpenter, then fit out of GPO’s (General Purpose Outlets), switches, and appliances.
When all other work is complete, power to be switched back on.
4. Plumber
Sequencing Order: 4
Task: Install all plumbing/gas pipe work and fittings.
Work Prior to:
All plumbing/gas outlets and connections finalised in plan.
Disconnect water and gas so other trades can work safely.
Work After:
Rough in after carpenter, then fit out taps and waste.
Connect gas to appliances.
When all other work is complete, reconnect water.
5. Carpenter
Sequencing Order: 5
Task: Open walls and build structural support for pantry, cool room, and window.
Work Prior to:
All structural work finalised in plan.
Site to have been made safe by electrician and plumber.
Work After:
Electrician and plumber rough in.
Plasterer sheets walls.
6. Plasterer
Sequencing Order: 6
Task: Install plasterboards on walls and ceilings.
Work Prior to:
Carpenter completes structural work.
Electrician and plumber complete all rough in work.
Work After:
Painting is completed.

Trade and Role Specifications (Sequencing 7 – 11)
7. Electrician / Refrigeration Technician
Sequencing Order: 7
Task: Install cool room.
Work Prior to:
All structural work finalised on plan.
Structural work and all rough in work complete.
Measurements confirmed with check measure.
Work After:
Connect electrical and plumbing.
Temperature control and refrigeration system connected.
8. Painter
Sequencing Order: 8
Task: Prepare and paint surfaces (walls, architraves, skirting, cornice, doors).
Work Prior to:
All colours finalised on plans.
Carpenter completes structural work.
Rough in of all services.
Plasterer sheets walls.
Work After:
Install of cabinetry.
Install of flooring.
Install of splashback.
Paint touch up where required at end of work.
9. Cabinetmaker
Sequencing Order: 9
Task: Supply and install kitchen.
Work Prior to:
Kitchen design finalised in plan.
Walls finished.
Electrical and plumbing roughed in.
Measurements confirmed with check measure.
Work After:
Benchtop checkmeasure and install.
Flooring installed.
Kickboards installed.
Splashback checkmeasure and install.
Power and water reconnected.
Paint touch up where required at end of work.
10. Flooring Installer
Sequencing Order: 10
Task: Install vinyl floor.
Work Prior to:
Flooring finalised on plan.
Work After:
Install kickboards and edging finished to match other surfaces, glazing install, and paint touch ups.
11. Glazier
Sequencing Order: 11
Task: Supply and install splashback.
Work Prior to:
Kitchen design finalised in plan.
All other work complete including cabinetry and benchtop install.
Work After:
Rangehood installed.
GPO’s connected.
Paint touch up.
Five-Week Master Execution Schedule
The master execution schedule spans 5 calendar weeks (from Monday 24-Mar-25 through Friday 25-Apr-25) mapped across daily working slots.

Detailed Daily Task Breakdown
Week 1 (24-Mar-25 to 28-Mar-25)
Mon 24-Mar-25:
Client: Site meeting
Designer / Project Manager: Site meeting
Electrician: Isolate power
Plumber: Isolate water/gas
Carpenter: Demo & Openings
Tues 25-Mar-25:
Carpenter: Demo & Openings
Wed 26-Mar-25:
Carpenter: Demo & Openings
Thu 27-Mar-25:
Carpenter: Framework
Fri 28-Mar-25:
Carpenter: Framework
Sat 29-Mar-25 & Sun 30-Mar-25: Weekend (No scheduled trade activity)
Week 2 (31-Mar-25 to 04-Apr-25)
Mon 31-Mar-25:
Electrician: Rough in
Plumber: Rough in
Tues 01-Apr-25:
Plasterer: Sheeting
Wed 02-Apr-25:
Plasterer: Sheeting
Thu 03-Apr-25:
Plasterer: Sheeting
Fri 04-Apr-25:
Electrician / Refrigeration Technician: Install panels
Sat 05-Apr-25 & Sun 06-Apr-25: Weekend (No scheduled trade activity)
Week 3 (07-Apr-25 to 11-Apr-25)
Mon 07-Apr-25:
Painter: Paint walls etc.
Tues 08-Apr-25:
Painter: Paint walls etc.
Wed 09-Apr-25:
Painter: Paint walls etc.
Thu 10-Apr-25:
Cabinetmaker: Cabinetry install
Fri 11-Apr-25:
Cabinetmaker: Cabinetry install
Sat 12-Apr-25 & Sun 13-Apr-25: Weekend (No scheduled trade activity)
Week 4 (14-Apr-25 to 18-Apr-25)
Mon 14-Apr-25:
Client: Site meeting
Designer / Project Manager: Site meeting
Cabinetmaker: Cabinetry install
Tues 15-Apr-25:
Cabinetmaker: Cabinetry install
Wed 16-Apr-25:
Cabinetmaker: Cabinetry install
Glazier: Check (Check measure)
Thu 17-Apr-25:
Cabinetmaker: Cabinetry install
Flooring Installer: Vinyl flooring
Fri 18-Apr-25:
Flooring Installer: Vinyl flooring
Sat 19-Apr-25 & Sun 20-Apr-25: Weekend (No scheduled trade activity)
Week 5 (21-Apr-25 to 25-Apr-25)
Mon 21-Apr-25:
Electrician: Fit off
Cabinetmaker: Kickboard
Tues 22-Apr-25:
Electrician: Fit off
Glazier: Install
Wed 23-Apr-25:
Plumber: Fit off
Glazier: Install
Thu 24-Apr-25:
Painter: Touch ups
Fri 25-Apr-25:
Client: Site meeting
Designer / Project Manager: Site meeting
Sat 26-Apr-25 & Sun 27-Apr-25: Weekend (No scheduled trade activity)