Concrete Measurement and Estimation Notes
Converting Measurements for Concrete
- Concrete companies sell concrete by cubic yard.
- Common measurements:
- Roof and floor slabs, slabs on grade, pavement, sidewalks: volume calculated using length, width, and thickness in feet.
- Conversion: 1 cubic yard = 27 cubic feet.
Handling Irregular Shapes
- Irregularly shaped items can be broken down into smaller, regular areas to facilitate easier calculations.
- Calculate volumes of smaller areas and combine for the total volume.
Measurement Techniques
- Volume of footings, columns, beams, and girders:
- Determined by multiplying linear footage by cross-sectional area.
- Items' volumes are calculated in cubic feet and then converted to cubic yards.
- When estimating footings for irregular shapes, only include corners once.
Estimation Best Practices
- Highlight portions of the footing taken off on architectural plans.
- Footings generally extend behind foundation walls, thus the length is greater than the wall length.
- Do not deduct holes smaller than 2 square feet.
Waste Allowance
- Waste percentages:
- 5% for footings, columns, beams.
- 10% for slabs.
- Best practice: account for waste when estimating quantities.
Procedure for Estimating Concrete Requirements
- Review specifications for concrete needs (footings, slabs, walkways).
- Specifications impact price (e.g., stronger concrete requires more cement).
- Identify concrete types based on:
- PSI (strength), color, admixtures, curing methods.
- Review drawings to ensure all items are covered in specifications. Contact the architectural engineer if specifications are missing.
- Calculate concrete quantities based on drawings, checking for different footing sizes under different walls.
- For continuous footings:
- Dimensions: 3 ft 2 in width, 1 ft thickness.
- Total linear feet of different widths calculated and totaled:
- A: 39 ft 10 in
- B: 34 ft 4 in
- C: 14 ft 10 in
- Example calculations lead to 10,68 cubic feet total volume.
- Convert cubic feet to cubic yards: 10.68 / 27 = 39.6 cubic yards.
- Adding waste for total order: 39.6 + 5% = 41.6 cubic yards.
Drilled Piers
- Drilled piers may require casing for stability, especially in loose soil or high water tables.
- Types of casing include heavy-duty cardboard tubes or steel casings.
- The depth of drilling determines the foundation stability.
Calculating Foundation Walls
- Similar process as footings, but specific dimensions vary and respect the foundation wall shape.
- Do not double-count corners when measuring perimeter.
Rebar Estimation
- Calculate using lengths for vertical and horizontal bars around footings and walls, ensuring coverage per engineering specs:
- Lapping adds approximately 5%-18% to the estimate depending on the size of the bar.
Summary of Concrete Estimations
- Estimation summary should cover total quantities for:
- Footings
- Foundation walls
- Spread footings
- Concrete beams
- Slabs on grade
- All labor and material costs included.
Waste Factors for Rebar
- Waste for precut bars can be less than 1%, while cut and bent bars may be as high as 10% based on field conditions.
- Rebar is often estimated based on concrete calculations.
Importance of Accurate Measurement and Calculation
- Always rely on precise measurements from plans.
- Highlight areas properly to avoid missed estimations or waste. Display calculations transparently to ensure justification for quantities ordered.
Final Notes
- Remember to communicate with engineers for clarifications.
- Understand the type of reinforcement necessary based on structural demand.