SPM-week4
Software Project Planning
Step Wise Overview
Step 0: Select Project
Decide if the project is worth undertaking.
Step 1: Identify Project Objectives
Define project objectives and practical measures for effectiveness.
Establish a project authority to ensure unity of purpose.
Identify stakeholders and their interests; modify objectives based on stakeholder analysis.
Set up communication methods among parties involved.
Step 2: Identify Project Infrastructure
Understand the project's relationship with strategic planning.
Determine installation standards and procedures.
Identify project team organization.
Step 3 to 10: Remaining Steps
Analyze project characteristics.
Identify products and activities.
Estimate effort for activities.
Identify activity risks.
Allocate resources.
Execute plan and review publicized plan.
Lower-level planning for activities.
Project Planning Significance
Project planning is crucial at the beginning of the software project process.
Recognize uncertainties in project plans due to:
Project complexity
Project size
Understanding of project/system
Changes in requirements
Project Plan Components
Statement of Work (SOW):
Detailed descriptions of work products and personnel involved.
Resource List:
Capture all necessary resources (hardware, software, services).
Work Breakdown Structure (WBS):
Breakdown of project into manageable sections.
Project Schedule:
Timeline detailing duration, dependencies, and critical activities.
Risk Plan:
Identification and management of potential risks.
Estimating an Effective Plan
Avoid obsession with estimation; be flexible with shifts in requirements due to iterative approaches.
Project Planning Differences
Planning: Identify activities without specific dates.
Estimating: Determine size and duration of activities.
Scheduling: Define specific dates, relationships, and allocated resources.
Inputs and Outputs of Project Planning
Inputs:
Project Charter, Software Requirements, Standards, Development Process.
Outputs:
Project Plan covering time, cost, scope, quality, schedule, budget, and quality management plan.
Life Cycle Model Definition
Projects require tailored approaches based on:
Development, enhancement, maintenance characteristics.
Familiarity with various models is advantageous.
Life Cycle Framework Development:
Familiarize with various models.
Analyze project criteria and establish minimum phases and deliverables.
Requirements Analysis
Requirements categorize user-requested functions/features. Key considerations include:
Clarity of requirements
Timeliness of defining requirements
Need for proof of concept or demonstration.
Selecting a Life Cycle Model
Evaluate project characteristics against potential life cycle models:
Waterfall, Prototype, Spiral, RAD based on defined requirements and user engagement.
Project Team Criteria
Assess team characteristics before selecting life cycle models to ensure successful project completion.
User Community Engagement
Understand user representative availability and expertise levels in system definition.
Project Schedule Development
Link tasks to resources effectively via a comprehensive schedule.
Risk Planning
Compile and mitigate a risk plan, addressing:
Team member input and brainstorming.
Estimation of risk probabilities.
Characteristics of Risk:
Risk involves uncertainty of occurrence and potential loss.
Risk Plan Example
Illustrates the assessment of specific risks, team member involvement, and actionable responses to mitigate identified risks effectively.