Comprehensive Site Punch List and Switchgear Operational Notes
General Site Progress and Inspection Status
- Building Inspector: The building inspector failed to show up for the scheduled site inspection.
- Gutter Installation: Gutters have been successfully installed on both the interior and exterior, and stitched together.
- Punch List Progress: The project punch list has been reduced from 64 total items down to 24 items, representing a reduction of roughly 32 of all outstanding issues.
Signage, Penetrations, and VCC Dependencies
- Research Signs: Outstanding; awaiting response and updates from VCC.
- Penetrations: Awaiting location specs from VCC.
- 4th Floor Exterior Sign: Pending final clearance/specifications from VCC.
- Site Monument Sign: Wiring is stubbed up and prepped. Work is paused until VCC provides final location confirmation or installs a concrete pad.
- Trellis and Track Lighting:
- Trellis lighting installation remains incomplete.
- Track lighting is currently located off-site in a storage container in Sacramento.
- Track lighting applies exclusively to the 1st Floor.
Lighting Fixtures and Controls
- 1st Floor Lobby Lighting:
- Installation of the 6–inch lighting fixtures is complete.
- Crew must return to install the 4–inch lighting fixtures, which are currently in progress.
- Lighting Control (Item #11): The lighting control system is not yet installed.
- Pool Patio Stone Veneer Gate Exit Signs:
- Wiring is stubbed off while awaiting gate setup by the gate subcontractor.
- Two additional weather-rated exterior exit signs are required due to design additions.
- The gate subcontractor must tack up a backplate for sign mounting.
Switchgear Mechanics and Field Learning Strategy
- Breaker Standoff Components:
- Breaker standoffs consist of a metal bracket attached to the rear of the circuit breaker.
- One leg mounts to the switchgear bussing, while the opposite side slides directly into phase connections (Phase A, Phase B, and Phase C).
- Switchgear Mastery Protocol:
- Print gear submittals from inactive or un-energized jobs (such as the Vacaville project site).
- Keep printed submittal sets inside the service vehicle for reference during site visits.
- Physically open and inspect switchgear prior to energization to understand component connections and develop quick field workarounds.
Power Distribution, Breakers, and Lockout/Tagout
- Generator Feeder Installation:
- Feeders arrive on Wednesday.
- Installation is scheduled for Thursday, coordinated with Noel using the wire tugger.
- 175 A Breakers:
- Two 175A breakers are required for the system.
- One breaker was supplied by Chase, but the second breaker has been missing for 4 months.
- Tate is searching office inventory to locate the missing second breaker.
- Standoff brackets must be supplied by Joe.
- PTAC Circuits (Item #21):
- All standard installations are complete, but one additional 2–pole 15A breaker is required to support four PTAC units.
- Main Switchboard (MSB) Lockout/Tagout (Item #22):
- Four locks were retrieved and lockout/tagout kits were located.
- All switchgear inside the main electrical room and on the MSB is locked down.
Infrastructure, Conduits, and Room Progress
- Car Charger Infrastructure (Item #6):
- The 1st Floor pass-through is verified complete.
- The 2–inch conduit for car chargers is not in place, though the gutter is installed.
- Main Infrastructure Piping (Item #24):
- Gutters are fully installed, placing work at approximately the half-way mark.
- Remaining scope requires running 2–inch conduit to the main Christie box.
- Total remaining effort involves a maximum of 2 days of piping (underground outside, inside to car chargers, main supply can, and lighting control) prior to pulling wire.
- 1st Floor Lecture Rooms MSP / ATS:
- Automatic Transfer Switch (ATS) isolation ("freeing the ATS") is incomplete.
- Standoffs are being ordered by Joe for the ATS, Elevator 1, and Elevator 2 breakers.
- 1st Floor Medical Electrical Room (Item #14):
- Outstanding and incomplete.
- Water Heater Room:
- Grounding and bonding (Item #8) is incomplete.
- Entry is pending. A plumber is required on site for 1 day to orient the thin water heaters so electrical connections can be finalized.
- Guest Rooms and Wall Finishes (Item #23):
- 4th Floor and 3rd Floor electrical work is complete as far as possible, pending wallpaper installation in hallways and approximately 10 rooms on the 3rd Floor.
- 2nd Floor and 1st Floor allow cover plate installation, but select walls are still missing wallpaper.
- Project Stakeholders & Roles:
- Charlie & Eric: On-site electrical management and coordination.
- Joe: Ordering breaker standoffs for ATS and Elevators 1 & 2.
- Tate: Office management, searching for missing 175A breaker.
- Chase: Provided the single 175A breaker.
- Noel: Assisting with wire tugger for generator feeder installation.
- VCC: General contractor / client responsible for signage specs, penetrations, and monument pad.
- Personal Outings:
- Fishing trip scheduled for Saturday with D and D Sportfishing operating out of Richmond.