Comprehensive Site Punch List and Switchgear Operational Notes

General Site Progress and Inspection Status

  • Building Inspector: The building inspector failed to show up for the scheduled site inspection.
  • Gutter Installation: Gutters have been successfully installed on both the interior and exterior, and stitched together.
  • Punch List Progress: The project punch list has been reduced from 6464 total items down to 2424 items, representing a reduction of roughly 23\frac{2}{3} of all outstanding issues.

Signage, Penetrations, and VCC Dependencies

  • Research Signs: Outstanding; awaiting response and updates from VCC.
  • Penetrations: Awaiting location specs from VCC.
  • 4th Floor Exterior Sign: Pending final clearance/specifications from VCC.
  • Site Monument Sign: Wiring is stubbed up and prepped. Work is paused until VCC provides final location confirmation or installs a concrete pad.
  • Trellis and Track Lighting:
    • Trellis lighting installation remains incomplete.
    • Track lighting is currently located off-site in a storage container in Sacramento.
    • Track lighting applies exclusively to the 1st Floor.

Lighting Fixtures and Controls

  • 1st Floor Lobby Lighting:
    • Installation of the 6–inch6\text{--inch} lighting fixtures is complete.
    • Crew must return to install the 4–inch4\text{--inch} lighting fixtures, which are currently in progress.
  • Lighting Control (Item #11): The lighting control system is not yet installed.
  • Pool Patio Stone Veneer Gate Exit Signs:
    • Wiring is stubbed off while awaiting gate setup by the gate subcontractor.
    • Two additional weather-rated exterior exit signs are required due to design additions.
    • The gate subcontractor must tack up a backplate for sign mounting.

Switchgear Mechanics and Field Learning Strategy

  • Breaker Standoff Components:
    • Breaker standoffs consist of a metal bracket attached to the rear of the circuit breaker.
    • One leg mounts to the switchgear bussing, while the opposite side slides directly into phase connections (Phase A\text{Phase A}, Phase B\text{Phase B}, and Phase C\text{Phase C}).
  • Switchgear Mastery Protocol:
    • Print gear submittals from inactive or un-energized jobs (such as the Vacaville project site).
    • Keep printed submittal sets inside the service vehicle for reference during site visits.
    • Physically open and inspect switchgear prior to energization to understand component connections and develop quick field workarounds.

Power Distribution, Breakers, and Lockout/Tagout

  • Generator Feeder Installation:
    • Feeders arrive on Wednesday.
    • Installation is scheduled for Thursday, coordinated with Noel using the wire tugger.
  • 175 A Breakers:
    • Two 175 A175\,\text{A} breakers are required for the system.
    • One breaker was supplied by Chase, but the second breaker has been missing for 4 months4\text{ months}.
    • Tate is searching office inventory to locate the missing second breaker.
    • Standoff brackets must be supplied by Joe.
  • PTAC Circuits (Item #21):
    • All standard installations are complete, but one additional 2–pole 15 A2\text{--pole } 15\,\text{A} breaker is required to support four PTAC units.
  • Main Switchboard (MSB) Lockout/Tagout (Item #22):
    • Four locks were retrieved and lockout/tagout kits were located.
    • All switchgear inside the main electrical room and on the MSB is locked down.

Infrastructure, Conduits, and Room Progress

  • Car Charger Infrastructure (Item #6):
    • The 1st Floor pass-through is verified complete.
    • The 2–inch2\text{--inch} conduit for car chargers is not in place, though the gutter is installed.
  • Main Infrastructure Piping (Item #24):
    • Gutters are fully installed, placing work at approximately the half-way mark.
    • Remaining scope requires running 2–inch2\text{--inch} conduit to the main Christie box.
    • Total remaining effort involves a maximum of 2 days2\text{ days} of piping (underground outside, inside to car chargers, main supply can, and lighting control) prior to pulling wire.
  • 1st Floor Lecture Rooms MSP / ATS:
    • Automatic Transfer Switch (ATS) isolation ("freeing the ATS") is incomplete.
    • Standoffs are being ordered by Joe for the ATS, Elevator 11, and Elevator 22 breakers.
  • 1st Floor Medical Electrical Room (Item #14):
    • Outstanding and incomplete.
  • Water Heater Room:
    • Grounding and bonding (Item #8) is incomplete.
    • Entry is pending. A plumber is required on site for 1 day1\text{ day} to orient the thin water heaters so electrical connections can be finalized.
  • Guest Rooms and Wall Finishes (Item #23):
    • 4th Floor and 3rd Floor electrical work is complete as far as possible, pending wallpaper installation in hallways and approximately 10 rooms10\text{ rooms} on the 3rd Floor.
    • 2nd Floor and 1st Floor allow cover plate installation, but select walls are still missing wallpaper.

Key Contacts and Personal Outings

  • Project Stakeholders & Roles:
    • Charlie & Eric: On-site electrical management and coordination.
    • Joe: Ordering breaker standoffs for ATS and Elevators 11 & 22.
    • Tate: Office management, searching for missing 175 A175\,\text{A} breaker.
    • Chase: Provided the single 175 A175\,\text{A} breaker.
    • Noel: Assisting with wire tugger for generator feeder installation.
    • VCC: General contractor / client responsible for signage specs, penetrations, and monument pad.
  • Personal Outings:
    • Fishing trip scheduled for Saturday with D and D Sportfishing operating out of Richmond.