Decision Analysis: Uncertainty, Risk, and Expected Value of Perfect Information
Decision-Making Environments and Criteria Under Uncertainty
Three Environments of Decision Making
- Decision Making Under Uncertainty: Scenarios or states of nature are known, but their probabilities of occurrence are completely unknown.
- Decision Making Under Risk: States of nature are known, and explicit probabilities can be assigned to each state.
- Decision Making Under Certainty: The exact state of nature that will occur is known with 100% confidence.
Objective Function and Payoff Definitions
- Payoffs in decision tables represent net profit, which incorporates both revenues and expenses.
- Because payoffs are modeled as profit, the general objective across rules under uncertainty is to maximize outcomes.
- If the performance metric were strictly measured in terms of cost rather than profit, all decision rules would be inverted to minimize outcomes.
Decision Criteria Under Uncertainty
- Maximax Criterion (Optimistic Perspective):
- Assumes that the best possible state of nature will occur for whichever decision alternative is selected.
- Procedure: Identify the maximum payoff for each alternative, then select the alternative corresponding to the maximum of those maximum payoffs.
- Example Result: Selecting the alternative to construct a large plant, as its maximum potential outcome exceeds all other alternatives.
- Maximin Criterion (Pessimistic Perspective):
- Assumes that the worst-case scenario will materialize for each decision alternative.
- Procedure: Identify the minimum payoff for each alternative, then choose the alternative that maximizes these minimum outcomes (the best of the worst).
- Example Result: Selecting the alternative to do nothing. Given worst-case payoffs such as -\\text{\\$180,000}, -\\text{\\$20,000}, and \\text{\\$0}, the maximum of these worst outcomes is \\text{\\$0} (doing nothing).
- Equally Likely / Laplace Criterion:
- Assumes all potential states of nature have an equal probability of occurrence.
- Procedure: Calculate the arithmetic mean outcome for each alternative across all states of nature, and choose the alternative with the highest expected average.
Decision Making Under Risk
Core Assumptions of Risk Models
- Probabilities assigned to states of nature must sum exactly to 1:
- States of nature must be mutually exclusive (no overlap between distinct scenarios) and collectively exhaustive (encompassing every possible state that can occur).
Expected Monetary Value (EMV)
- Definition: The weighted average payoff for an alternative, where weights are the probabilities of the respective states of nature.
- General Mathematical Formula:
- Relationship to Equally Likely Criterion: The equally likely approach is a special case of where each scenario probability .
Empirical Application: Plant Construction Decisions
- State Probabilities:
- Favorable Market Probability:
- Unfavorable Market Probability:
- Probability Validation:
- Alternative Payoff Calculations:
- Large Plant: EMV_{\\text{Large}} = (0.6 \\times \\text{\\200,000}) + (0.4 \\times -\\text{\\48,000}) = \\text{\\120,000} - \\text{\\19,200} = \\text{\\$48,000}
- Small Plant: EMV_{\\text{Small}} = (0.6 \\times \\text{\\90,000}) + (0.4 \\times \\text{\\25,000}) = \\text{\\$52,000}
- Do Nothing: EMV_{\\text{Do Nothing}} = (0.6 \\times \\text{\\0}) + (0.4 \\times \\text{\\0}) = \\text{\\$0}
- Optimal Decision Under Risk: The Small Plant alternative is selected because it yields the maximum of \\text{\\$52,000}.
Expected Value of Perfect Information (EVPI)
Conceptual Framework
- Information regarding future states of nature typically carries a acquisition cost.
- Expected Value of Perfect Information () measures the maximum amount a decision-maker should logically pay to obtain perfect forecasts prior to choosing an alternative.
- calculates the expected gain realized from eliminating all risk and uncertainty.
Mathematical Definition and Calculation
- Expected Value with Perfect Information (EVwPI):
- The expected return achieved if the decision-maker knows with certainty which state of nature will occur before choosing the optimal action for that state.
- Formula:
- Expected Value of Perfect Information (EVPI):
- Formula:
Plant Construction EVPI Calculation
- Best Payoff in Favorable Market: Construct Large Facility (\\text{\\$200,000})
- Best Payoff in Unfavorable Market: Do Nothing (\\text{\\$0})
- Expected Value with Perfect Information: EVwPI = (0.6 \\times \\text{\\200,000}) + (0.4 \\times \\text{\\0}) = \\text{\\$120,000}
- Expected Value of Perfect Information: EVPI = \\text{\\120,000} - \\text{\\52,000} = \\text{\\$68,000}
Economic Decision Rules for Purchasing Information
- Upper bound threshold: The absolute maximum price to pay for perfect information is \\text{\\$68,000}.
- Information Cost Scenario A (\\text{\\$30,000}):
- Decision: Purchase the information.
- Justification: Information cost (\\text{\\$30,000}) is less than (\\text{\\$68,000}), yielding an expected net benefit of \\text{\\$38,000}.
- Information Cost Scenario B (\\text{\\$80,000}):
- Decision: Reject the information offer.
- Justification: Information cost (\\text{\\$80,000}) exceeds (\\text{\\$68,000}), which would reduce overall expected monetary gain.
Comprehensive Application: Event Location Planning Under Weather Risk
Problem Definition and Parameters
- Decision Alternatives: Outdoor Event, Indoor Event
- States of Nature: Sunny Weather (), Rainy Weather ()
- Probability Check:
- Payoff Structure:
- Outdoor Event under Sunny Weather: \\text{\\$10,000}
- Outdoor Event under Rainy Weather: -\\text{\\$4,000}
- Indoor Event under Sunny Weather: \\text{\\$6,000}
- Indoor Event under Rainy Weather: \\text{\\$5,000}
Step-by-Step Expected Monetary Value (EMV) Calculations
- for Outdoor Event: EMV_{\\text{Outdoor}} = (0.7 \\times \\text{\\10,000}) + (0.3 \\times -\\text{\\4,000}) = \\text{\\7,000} - \\text{\\1,200} = \\text{\\$5,800}
- for Indoor Event: EMV_{\\text{Indoor}} = (0.7 \\times \\text{\\6,000}) + (0.3 \\times \\text{\\5,000}) = \\text{\\4,200} + \\text{\\1,500} = \\text{\\$5,700}
- Base Choice under Risk: Select Outdoor Event (EMV = \\text{\\$5,800}).
Step-by-Step EVwPI and EVPI Calculations
- Best Decision per State of Nature:
- If Sunny: Select Outdoor Event (Payoff = \\text{\\$10,000})
- If Rainy: Select Indoor Event (Payoff = \\text{\\$5,000})
- Expected Value with Perfect Information: EVwPI = (0.7 \\times \\text{\\10,000}) + (0.3 \\times \\text{\\5,000}) = \\text{\\7,000} + \\text{\\1,500} = \\text{\\$8,500}
- Expected Value of Perfect Information: EVPI = EVwPI - \\max(EMV) = \\text{\\8,500} - \\text{\\5,800} = \\text{\\$2,700}
Final Decision Analysis
- Optimal base alternative under risk: Outdoor Event (EMV = \\text{\\$5,800}).
- Maximum willingness to pay for a perfect weather forecast: \\text{\\$2,700}.