Talia is cool.
16265 Construction Technology 2
Week 1
Regulatory Implementation and Construction Concepts
Local Government (LG)
Sets land use zoning (residential, industrial, commercial)
Controls: building size, setbacks, overshadowing, stormwater
Powers under the Environmental Planning and Assessment Act
National Construction Code (NCC):
Mandatory building regulation (10 building classes)
LG administers; focus - performance outcomes
Focus: Volume 1
Principal Certifying Authorities (PCAs):
Health & Amenity: weatherproofing, noise, light, ventilation
Safety: fire, egress, structural integrity, services
Sustainability: energy + water
Compliance
Principal Certifying Authorities (PCA)
LG or accredited certifier
Issue construction/compliance certificates
Ensure NCC + local compliance
Inspect at critical stages
NCC & Reference Documents
Australian Standards: only mandatory when NCC referenced them
Provide descriptive details (materials, processes)
Best practice ≠ DTS (demand to satisfy) (higher quality, costlier)
F2P2: prevent water penetration (behind fittings, into cavities)
F2D2: gives BTS methods to comply
Multi-Residential Concepts
Strata ownership: group land + structure, private units
Compartmentalisation: fire/noise separation via party walls/floors
SOU: sole occupancy unit
Types:
Townhouses/row houses → 2 storey, common walls, state-titled
Apartments → multi-storey, shared fire egress + carparks (main focus)
Site Establishment & Materials Handling
Aim: efficient + safe material movement
Storage: compounds, sheds, basements, floor areas
Tall buildings → loading platforms essential
Plan crane/truck/pump circulation
Problems
Limited space
Delivery vs crane coordination
Prefer just-in-time delivery
Need cranes/hoists
Cranes
Week 2
Machine Type/Selection
Detailed Excavation
Elements excavated: pad footings, piers, pile caps, strip footings, stormwater/services, crane & joist foundations
Dewatering
Water Table = soil saturated by groundwater.
Needed to stabilise soil → prevent collapse.
Methods:
Well Points → small tubes + vacuum pump; used in silts/sands; effective to ~6m depth
Wells → borehole with submersible pump; for more permeable soils
Horizontal Drainage → trenches with perforated pipe + pump (for surface water)
Remediation
Consultant testing → classify material
Contaminated soil removed, leaving VENM only (under geotech supervision)
Removal & Disposal
Cartage of soil via bogies or trucks & dogs
Truck type depends on disposal option + site conditions
Shoring and Piling
Shoring: supports/retains soil to prevent collapse (temporary)
Piling: supports footings or forms retaining walls (e.g., diaphragm walls)
Reinforced concrete piles with shotcrete infill
Alternative to blockwork basements
Cost: ~$800/m² (vs $500/m² for shoring) but provides permanent retaining wall
Process (before bulk excavation):
Drill pile holes
Place reinforcing
Pour concrete (piles extend below floor for cantilevering)
Shotcrete infill wall between piles
Week 3
Concrete Properties
Durability: hardens with age
Shrinks slightly
Small dimensional variation (not fired)
Appearance: plain but uniform
Masonry
Advantages: flexible small units, easy to construct
Blocks (hollow): strong when reinforced; weak unreinforced, esp. Under horizontal loads
Reinforcing Steel
Codes:
“N” = normal ductility
Deformed bars (ribs) = main reinforcing, 500MPa
Round bars “R” (smooth) = ligatures, cages, 250MPa
Example: N16-400 → 16mm diameter, 400mm spacing
Other terms:
Splice = overlap between bars
Cogs/hooks = bends for anchorage & load transfer
Recycling in Masonry
Blocks up to 30% lighter
Aggregate replaced with bottom ash (coal furnaces) + slag sands (steel by-product)
Cement partly replace with slagment (steel furnace paste)
Reduces use of natural river aggregates and sands
Mortar Joints
Functions: bedding, load transfer, bond strength
Requirements:
Accurate batching
Washed sands (avoid brickies mix → shrinkage)
Hollow blocks laid with face shell bedding (no web mortar)
Joint Finishes:
Grouting Cores
Methods: hand hoppers of pump nozzle
Preparation: clean cores, provide clean-out openings, cool with water in hot weather
Pouring rules: <3m per lift, 30 min apart if >2.4m
Specs:
Strength: min 12MPa (prefer 20MPa)
Cement: >300kg/m3
Aggregate: 10mm coarse gravel
Consistency: flowable, surrounds reinforcement fully
Control Joints
Purpose: prevent cracks from shrinkage, thermal movement, footing settlement, hogging/sagging
Locations: changes in wall height/thickness, junctions, door/roof slabs, straight walls (special blocks available)
Gravity Wall Systems
Features: free draining, flexible, cost effective, suits most soils
Can be upgraded with soil reinforcement for taller/stronger walls
Construction process:
1. Place aggregate leveling pad
2. Lay blocks with reinforcement + backfill
Week 4
Context
Basements are common in multi-unit residential buildings for underground parking
Typically constructed with concrete block walls and poured in-situ concrete columns on strip and pad footings
The suspended ground floor slab acts as a diaphragm, resisting horizontal forces on basement walls from ground and hydrostatic pressure
Pier and Pile Cap
Distributes load from the concrete block pier to the bored on-ground pile
Strip Footings
Support engaged blade columns on the perimeter wall
Constructed with reinforced, core-filled concrete blocks
Include infill-slab, column, and isolation joint
Blockwork Detail
Reinforced, core-filled concrete block construction
Strip footing supports the wall
Wet wall and retaining wall required
Clear load path from wall → strip footing
Isolation joint separates infill slab from main structure
Used for infill/on-grade slabs
Separates concrete slab from adjoining structures to prevent restraint
Allows vertical and horizontal movement due to time or temperature changes
Filled with compressible cellular materials
Basement Walls - Strength and Waterproofing
Must ensure structural integrity and waterproofing
Hydrostatic pressure from groundwater creates high loads and potential leakage
Similar to an in-ground pool in reverse (water outside pressing inward)
Early Decisions on Hydrostatic Load
Wet wall construction - soil is tight against wall; must resist moisture pressure
Separate retaining wall - built outside the main building; takes the hydrostatic load, protecting the basement wall
General Issues
Wet walls require:
Waterproofing, sub-soil drainage, structural design
Goal: drain or shed groundwater to reduce hydrostatic pressure
On sloped sites, the building may act as a dam to upstream water
Civil and hydraulic engineers assist with drainage design
Three Fundamentals of Wet Wall Systems
Structural Adequacy: resist hydrostatic pressure, earth pressure, and superimposed loads
Relieve Hyostatic Pressure: ensure drainage paths and load relief
Waterproofing: continuous, impervious membrane or drainage system to divert water
Selecting Wet Wall Retaining Systems
Based on cost vs performance & durability (No NCC requirement for durability)
Consider:
NCC performance requirements
Amount of water expected on site
Water table height & variability
Use of basement:
Habitable: must be fully waterproofed
Non-inhabitable: minimal waterproofing acceptable
Site Factors
Rainwater run-off and drainage capacity
Soil type: sand drains better than clay
Water table height vs basement depth
Habitable vs Non-Habitable Spaces
Paint-On Liquid Membranes
Requires careful application (avoid thin or missed areas)
Used for low-risk areas:
Low-risk basements, balconies, planter boxes, retaining walls, water tanks
Self-Adhesive Sheet Membranes
More consistent than paint-on-types
No heating required
Uniform thickness ensures quality
Used for mid to high-performance: basements, retaining walls, ramps
High Performance (Risk Level 1) – Sealed/Tanking Systems
For high-risk conditions (constant hydrostatic pressure)
Features:
Thicker, robust membranes (resist pinholes)
Continuous “skin” around entire structure
Enhanced detailing at joints and wall-floor junction
Protection from sulphates in groundwater
Comprehensive sub-soil drainage
Drainage layer under floor slab
Multiple agricultural drains
Drainage cells/logs + geotextiles (prevent clogging) n
Protective layers (fibre cement, foam, screed)
Torch-On Membranes
Typical for high-performance applications (tanking systems)
Best option but required skilled installation to heat-weld seams
Must include protection from damage and ensure adequate drainage
Used for:
High-performance basements, lift pits, car parks, roofs, landscaped/green roofs
Week 5
Introduction
In multi-residential buildings, sound insulation often governs the choice of construction system more than fire resistance
Sound: everyday comfort issue
Fire: protection against extreme events
Goal: economically satisfy both fire and acoustic performance within a single construction solution
Steps in Choosing a Construction System (NCC Framework)
Define NCC Building Classification & Compliance Pathway
Determine the class of building (e.g. Class 2 apartments)
Identify the basis for compliance (Deemed-to-Satisfy, Performance Solution, etc)
Establish the arrangement of Sole Occupancy Units (SOUs)
Sole Occupancy Units (SOU)
Arrangement of SOUs affect both fire and sound performance
Walls, floors and ceilings are critical
SOU Configurations
Side-by-side units → wall performance important
Stacked vertically → floor/ceiling performance important
Adjoining other spaces (corridor, stair, etc) → fire & acoustic separation required
Note: even internal SOU walls/floors may need fire-rating if they support fire-rated elements above
Define Sound Performance Requirements
Governed by NCC Vol 1 - Section F, Part F7 (Sound Transmission and Insulation)
Performance Requirements F7P1: controls sound transmission through walls, floors, and ceilings between SOUs
Deemed-to-Satisfy Provisions
Specify minimum sound insulation values (Rw + Ctr) for separating elements
Key Steps:
Identify which walls/floors bound SOUs
Understand sound measurement and rating terms
Select a system that meets or exceeds NCC minimum requirements
Sound Insulation Strategies
Add Mass: heavier elements (concrete, masonry) block sound
Isolate sides: use double-stuf or cavity wall construction
Absorb sound: fill cavities with mineral wool or similar material
Seal penetrations: close gaps around services with acoustic sealant or expanding foam
For Windows and Doors
Weak points for noise leakage
Use:
Thicker or double glazing
Acoustic sealant between wall and frame
Gaskets around openable parts
Solid-core doors for better sound resistance
Define Fire Performance Requirements
Main Objectives
Safeguard occupants during fire events
Enable safe evacuation
Facilitate emergency services access
Prevent fire spread between buildings
Protect the building from structural failure
Determine Fire Resistance Requirements
NCC Type of Construction (C2)
Type A – Highest protection:
Structure must withstand full burnout
Type B – Moderate protection:
Partial structural protection
Type C – Lowest protection
Basic separation only (typically Class 1-2)
Some concessions apply (eg sprinklers)
Fire Resistance Level (FRL)
Expressed as structural adequacy / integrity / insulation (in minutes)
Eg.
60 / 60 / 60 → all 3 properties required for 60min
– / 60 / – → only integrity needed for 60 min
Structural adequacy: element can carry load
Integrity: stops flames/smoke/gases
Insulation: limits temperature rise on the unexposed side
Other Fire Considerations
Non-combustible materials often required for external walls (Type A & B)
Smoke-proof walls for large buildings or long corridors
Roof ceilings resistance against early fire spread
Shafts (lifts, garbage chutes, services) need special detailing
Fire isolated stairs for evacuation routes
Merging Sound and Fire Requirements
Final System must meet both performance criteria
Typically achieved by selecting tested manufacturer systems that:
Are NCC-Compliant
Have certificated for FRL and acoustic ratings (Rw + Ctr)
Manufacturers provide detailed tested system data to ensure compliance
Week 6
Introduction
Most common floor systems in multi-unit residential buildings
Advantages: good noise/fire insulation, thermal mass, high strength, termite resistance, widely available, cost-effective
Disadvantages: labour-intensive (formwork), slower than prefab systems
Concrete: strong in compression, weak in tension/shear → steel added to resist tension
Load Behaviour
One-way Slab
Spans in one direction between walls
Bottom steel resists tension; top steel for shrinkage/temperature
Two-way slabs
Spans in two directions (nearly square panels)
Bottom steel both ways (shorter span first); top steel for shrinkage control
Reinforcing Types
Simple span
Between to support; tension at bottom → steel at slab base
Continuous span
Over multiple supports; reverse bending at supports → extra top steel
Cantilever
Overhangs support; tension at top → reinforcement at top face
Shrinkage & Temperature Steel
mesh/fabric on top of slab
Controls cracks from shrinkage and thermal movement
More steel needed for long slabs
Punching Shear (at Columns)
Localised failure where column pushes through slab
Prevented with extra reinforcement, drop panels, or shear heads
Week 7
Brick Materials
Clay bricks - fired in kilns, expand after firing (‘E’ = expansion coefficient)
Expansion joints every 6-12m to prevent cracking
Concrete bricks - moulded, steam-cured; shrink slowly as they dry
Calcium-silicate bricks - low-strength, porous, mostly obsolete
Avoid mixing clay (expanding) and concrete (shrinking) in one wall
Sustainability Implications
Old brick firing: charcoal/coal → pollution
Modern bricks: gas or electric kilns → cleaner but every-intensive
Concrete bricks use cement (high embodied energy)
Both brick types have high embodied energy but long life → reuseable/recyclable
Damp Proof Course (DPC)
Stops rising damp and salt attack
Common: polyethylene; tougher: bitumen-coated aluminium
Install 150mm above ground, allow sight wall projection
Cavity Walls
Two skins: of brick with an air gap and wall ties
Outer skin: weather protection, aesthetics
Inner skin: load-bearing, often rendered
Cavity: prevent moisture transfer, adds insulation
Limit height to one storey; ensure flashings, weep holes, clean cavity
Avoid using conduits/pipes in cavity
Flashings
Prevent water entry around windows, doors, roofs, chimneys
Must drain to outer wall through weep holes
Fragile - inspect before covering; longer laps = better performance
Brick and Mortar Properties
Durability: exposure grade for marine zones; general purpose elsewhere
Absorption lower = better resistance to damp
Expansion: up to 2mm/m; allow joints for growth
Mortar:
Use GP/GB cement, clean sand/water
Lime improves workability
Avoid dishwashing liquid or excess additives
Mortar Classes (C:L:S)
Wall Ties
Tie skins together; resist tension/compression; stop water bridging
Spacing: 600mm centres (300mm near openings)
Embodiment: 50mm min
Classes: light → heavy; R1 - R5 for durability
Movement Joints
Expansion / control joints: handle brick growth + thermal change
Typically 10mm gaps with foam and mastic
Slip joints: between brick walls & concrete slabs to allow horizontal movement
Articulation joints: isolate wall panels to manage footing movement - often near corners, doors, windows
Lintels
Support masonry above openings
Engage ≥ 50mm each side (100mm for large spans)
Prop until mortar cures
Flat bar = non-load bearing; angle bar = bearing
Brickwork Practice
Set-out: maintain bond (overlap pattern) & gauge (course height)
Bond: eg stretcher bond, ~230mm brick + 10mm joint
Gauge: ~86mm per course (brick + joint)
Trowel work: butter ends (“perpends”), keep plumb & level
Scaffolding: adds cost/time - use efficiently
Labour rates: 1 bricklayer ~ 750 bricks/day (ideal)
Handling & Delivery
Delivered on pallets or slings, unloaded by crane
Distribute to sun-stacks near work area
Keep materials consistent (same sand/cement batches)
Week 8
Cross Laminated Timber (CLT)
Large solid timber panels (e.g., 12 m × 2.4 m × 180 mm)
Made of wide planks (≈ 250 mm) glued in alternating layers (cross-laminated)
Used for walls, floors, and roofs in mid-rise timber buildings
Panelisation & Installation Process
3D model → reverse-engineered to individual panels (panelisation)
Panels cut by CNC machine → labelled and sequenced for install
Delivered just-in-time for crane lifting and install
Wall-to-floor joints: brackets; wall-to-wall: long self-drilling screws
Floors pulled tight using clamps
Screed Over CLT Floors
Used to improve acoustic performance
Material: gypsum/polymer concrete; 30-50mm thick. 30-40kg/m2
Pumped self-levelling screed preferred
Adds weight-affects floor and stud design
Next Generation: Post & Plate Construction
Ideal for 4–8 storey buildings (residential, commercial, institutional)
No beams → cleaner ceiling; free underfloor service space
Posts can be exposed (offices) or hidden (apartments)
CLT floor plate thickness governs span
Steel shear plate/post head = key connection
Focus: “Design for Manufacturing & Assembly (DfMA)”
Work breakdown: 35% waste, 45% indirect, 20% direct
Week 9
NCC Requirement
FP 1.4 Weatherproofing: Roofs/external walls must prevent water that causes unhealthy, dangerous or damp conditions
Exemptions: Classes 7–8 (no need), garages, sheds, open stands, open-deck carparks
Biggest failure cause: Inadequate pitch/fall.
NCC DTS Roof Coverings (F1.5)
Concrete or terracotta tiles, fibre-cement, metal, or plastic sheet roofing—all per relevant AS standards
NCC on balcony and terrace waterproofing DTS:
KEY DESIGN POINTS
General Issues
Waterproofing = high risk trade → small defects = leaks
Falls: 1 : 100 min, 1 : 60 better
Flat roofs / balconies act like shallow pools; outlets crucial
Penetrations (vents, balustrades) are weak points
Deemed-to-Satisfy standards for external above-ground membranes
AS 4654.1 & 4654.2
Deemed-to-satisfy standards for external above-ground membranes
Fitness for Purpose
Membrane must:
Be compatible with adjacent materials
Bridge cracks/irregularities
Contain water (bathtub effect)
Resist UV, movement, chemicals, and abrasion
Last the life of the finish
Design Principles
Apply membrane to substrate, not tile screed
Always provide falls to drain outlets
No ponding
Protect from UV/mechanical damage
Include slip-sheet/sound-layer where needed
DETAILING
Drained Cavity (Best Practice)
Flat usable surface, concealed drains, serviceable membrane
Higher falls possible, no-step thresholds, easy maintenance
Substances
Insitu concrete = best (two-way falls possible)
Precast = needs topping slab
Timber = avoid in wet zones; flexible membrane essential
Falls
1:80 – 1:100 typical
Tile size and screed thickness affect drainage
Accessibility may limit falls
EXPOSURE DESIGN
Exposed (>3 storeys or ridgeline) → set-downs ≥ 100 mm, overflow pipes, weep holes @ 600 mm max
Sheltered (<9 m, screened) → reduced detailing pressure
Flashings ≥ 150 mm up cavity, sealed laps, proper sealants
EFFLORESCENCE CONTROL
Caused by salt/lime migration from saturated tile beds
Minimise via: positive substrate fall, stop water entry, penetrant sealer, waterproof adhesives
MEMBRANE PROTECTION
Prevent construction & service damage using: drainage cells, geotextile fabric, pavers, tiles, or rubber mats
Types of Membrane
Membrane Flexibility (AS 4654.1)
Terminations & Penetrations
Seal and cap leading edges to prevent water behind membrane
Use reglets (cast-in, formed, or cut rebates)
Cappings: metal flashings or liquid coatings
Surface finishes: screed + tile, pavers, or decking
Alternative Systems
Crystalline admixtures (e.g., Contec C1): Grow crystals to block pores; cheaper but need careful detailing. Can self-heal small cracks (~1 mm).
Avoid complex joints or poorly controlled concrete.
Week 11
Purpose
Enable access, movement between storeys and emergency egress
BCA regulates exits under Section A - Access and Egress
Stairways as Exits (BCA Definition)
Any element providing egress to a road/open space
internal/external stairway
Ramp
Fire-isolated passageway
Doorway to road/open space
Horizontal exit
Design Requirements
Number of stairways: must allow all occupants to evacuate safely
Width: sufficient for safe evacuation
Fire isolation: depends on:
Building classification
Fire safety systems
Number of connected storeys
Governed by NCC Section D – Access and Egress
Stair Materials
Choice depends on fire-isolation needs
Concrete common: non-combustable, durable under fire exposure
Other materials: steel, timber (non-fire-isolated stairs only)
Purpose of Render
Provide smooth, decorative finish on masonry/concrete
Improve water resistance (not waterproof)
Improve sound insulation (thicker coats)
Common in apartments and commercial facades
Render Composition
Substrate Preparation
Clean, key the surface, remove dust/grease
Dampen wall before application to improve adhesion
Application & Coats
1-2 coats depending on substrate & conditions
Each coat ≤ 15mm thick
3 days drying between coats
Keep render damp during curing to prevent cracking
Alternative & Acrylic Renders
Acrylic render: flexible, thin (3–6 mm), adheres to smooth surfaces
High-build acrylic: forms elastic, waterproof, low-maintenance barrier; bridges cracks and resists CO₂/chemical attack
Render Strength & Compatibility
Match strength to substrate:
Too strong → cracking along mortar joints
2nd coat must be equal or weaker than 1st
Decorative Finishes
Control Joints
Control where cracking occurs due to drying or movement
Achieved via saw cut, tooled groove or joint bead
Located at:
Substrate joints
Changes in material
Large wall areas
Metal Lathe Reinforcing
Applied over weak areas or full walls
Prevents cracking and improves render strength
Curing and Protection
Prevent rapid drying – causes shrinkage cracks
Keep render damp for 3 days; cover with clear plastic sheeting to restrain moisture