145- Control Scope, Schedule Cost
Keeping Projects on Track: Scope, Schedule, and Budget
Three Essential Processes
- Three key processes for daily project execution:
- Staying on Scope
- Staying on Schedule
- Staying on Budget
- Each day, compare team's work against the project plan to assess:
- Scope: Are they doing the correct work?
- Schedule: Are they spending the appropriate time (not too long or too short)?
- Cost: Are they spending the correct amount of money (not too much or too little)?
Core Processes: Controlled Scope, Schedule, and Cost
- These processes share similar inputs, tools, and outputs.
- Understanding their specific functions is crucial.
1. Controlled Scope
- Ensuring the work remains within the defined scope.
- Comparing planned work against actual work completed.
- Planned Work: Sourced from the Project Management Plan.
- Actual Work: Derived from Work Performance Data.
- Process:
- Observe the work being done (Work Performance Data).
- Review the plan to see what should be done.
- Identify any discrepancies between planned and actual work.
2. Controlled Schedule
- Mirrors the controlled scope process but focuses on time.
- Comparing planned work duration against actual work duration.
- Planned Work: Comes from the schedule baseline in the Project Management Plan.
- Actual Work: Captured in the Work Performance Data (how long tasks took).
- Example:
- Plan: Painting a room should take two days.
- Reality: It took 1.5 days or 3 days.
3. Controlled Cost
- Similar concept, focused on budget.
- Comparing planned costs against actual expenditures.
- Planned Cost: Derived from the cost baseline in the Project Management Plan.
- Actual Work: Reflected in Work Performance Data (actual money spent).
- Example:
- Plan: Spending should be 200.
- Reality: 250 was spent, indicating over budget.
- Objective: Maintain work within the three baselines by identifying variances between planned and actual results.
Controlled Scope: In Detail
- Monitoring project and product scope status.
- Managing scope changes.
- Scope Creep: Uncontrolled expansion of scope without adjusting time or cost; to avoid scope creep, submit a change request to assess and approve scope additions, then update the plan with appropriate cost and time changes.
- Objective: Identify differences between planned and actual work.
- Updating the project baseline (especially the scope baseline) when changes are approved.
- Inputs
- Project Management Plan (Planned Work)
- Work Performance Data (Actual Work)
- Tools
- Variance Analysis: Analyzing the variance between planned and actual work.
- Determining the degree of variance in performed work related to scope.
- Example: Planned to paint the wall white, but it was painted off-white or glossy instead of flat.
- Identifying the cause of the variance.
- Determining corrective or preventive actions.
- Analyzing trends over time.
- Outputs
- Work Performance Information: Reports whether the project is on or off scope.
- Change Requests: Used to bring the work back on plan.
- Plan Updates: Update scope to incorporate changes, which usually leads to time and cost increases.
Controlled Schedule: In Detail
- Monitoring project status to update the project schedule and manage changes to the schedule baseline.
- Maintaining the schedule baseline.
- Comparing work results against the plan to determine if the project is on schedule.
- Assessing the project's current status and how it was reached.
- Inputs
- Project Management Plan
- Work Performance Data (actual time spent on work)
- Tools and Techniques
- Critical Path Method
- Applying leads and lags
- Crashing and fast-tracking
- Performance Reviews: Measuring variance from the actual end date to the planned end date.
- What-if Scenario Analysis
- Project Management Information System (PMIS)
- Resource optimization (resource leveling, leads and lags, fast tracking, and crashing)
- Outputs
- Work Performance Information: Reports how far ahead or behind schedule the project is.
- Schedule Forecasts: Predicting future schedule performance.
- Change Requests: Needed if the project is significantly off schedule.
Controlled Costs: In Detail
- Monitoring project status to update project costs and manage changes to the cost baseline (keeping the project on budget).
- Identifying cost variances.
- Any budget increases must be approved through the Perform Integrated Change Control (PIC) process via a change request.
Earned Value Management (EVM)
- A series of formulas used to monitor budget status; critical for the Project Management Institute (PMI).
- EVM Includes:
- Memorizing and Understanding Formulas.
- Interpreting the results of formulas (e.g., CPI of 0.6 and SPI of 1.2).
- Inputs
- Project Management Plan (planned spending)
- Work Performance Data (actual spending)
- Funding Requirements (total funds needed)
- Tools
- Earned Value Management (EVM) Techniques
- Variance Analysis: How far on or off budget are you
- Trend Analysis: How far is the project going
- Reserve Analysis: Are reserves being utilized
- To-Complete Performance Index (TCPI): EVM Formula
- Outputs
- Work Performance Information: Reports difference between planned and actual spending.
- Cost Forecasts: Predicts total project cost at completion (EVM Formula).
- Change Requests: Needed if more funds are required.
Daily Vigilance
- These three processes must be performed daily.
- Continuously monitor budget, schedule, and scope.
- Investigate any deviations to determine their root cause.