Construction Project Development & Contract Fundamentals
Construction Project Development Notes
Module Information
Module: Construction Project Development
Course: CM 4306 – Building Construction Contract
Instructor: Vinny Kaushal, Ph.D., P.E., Associate Professor of Instruction, Department of Civil Engineering, University of Texas at Arlington
Development & Construction Process: Project Origin
A project typically originates from an unfulfilled need by a Developer, Owner, or Governmental Agency.
Common Needs Include:
To make money (profit generation).
Need for a new or larger office facility, or expansion of an existing one.
Requirement for a new or larger facility to accommodate new technology.
Development of new schools, roads, bridges, or other infrastructure.
Upgrades to existing infrastructure.
Development Phases
Before design and construction, projects undergo several critical development phases:
Marketing Studies: Assessing market demand and viability.
Feasibility Studies: Evaluating the practicality and potential success of a project, encompassing:
Programming: Defining the project's functional requirements and spaces.
Conceptual Estimates: Initial cost approximations.
Proformas: Financial projections to assess profitability.
Site Selection: Involves a thorough assessment of potential sites:
Entitlements: Obtaining necessary legal rights and approvals for development.
Phase I Environmental Studies: Initial environmental assessment to identify potential contamination.
Soil Investigation: Geotechnical studies to understand subsurface conditions.
Selection of Consultants
A project requires a diverse team of consultants, broadly categorized into Design Teams and Specialty Consultants.
Design Teams:
Architect: Leads the overall design and aesthetic.
Engineers: Specializations include:
Civil Engineer
Structural Engineer
Mechanical Engineer
Electrical Engineer
Plumbing Engineer
Acoustical Engineer
Landscape Architect: Designs outdoor spaces.
Interior Designer: Plans and designs interior spaces.
Specialty Consultants:
Waterproofing
Environmental
Curtain Wall
Commissioning (ensuring systems operate as intended)
Green Building/LEED (Leadership in Energy and Environmental Design)
Permitting
Accessibility
Construction Team:
Construction Manager
General Contractor
Estimating personnel
Green Building Team:
LEED® Accredited Professional
Commissioning Agent
Other Project Participants
Beyond the core consultant teams, numerous other parties are involved:
Super Subs: Major subcontractors with significant scopes of work.
Government Agencies – Authority Having Jurisdiction (AHJ): Entities with legal control over building codes, zoning, and permits.
Subcontractors/Sub-subcontractors: Perform specialized work packages.
Manufacturers, Suppliers, Product Representatives: Provide materials and equipment, and technical support.
Testing & Inspection Agencies: Ensure quality and compliance for a range of elements:
Soil
Environmental
Concrete
Waterproofing/Sealants
Quality control
Steel frame
Welding
Torque (e.g., structural connections)
Owner’s Representative: Represents the owner's interests and manages the project on their behalf.
Facility Manager: Oversees the operation and maintenance of the completed facility.
Specifications: Detailed written requirements for materials, equipment, and workmanship.
Construction Contract Administration: Managing the contractual obligations throughout construction.
Contractor, Construction Manager, Project Manager, Superintendent, Project Engineer, Risk Manager: Key personnel on the construction side.
Facility Life Cycle (Modules Perspective)
The project involves a continuous life cycle, which can be broken down into distinct modules:
Module : Project Conception – The initial idea and needs identification.
Module : Design – Development of plans and specifications.
Module : Construction Documents – Detailed drawings and specifications for construction.
Module : Project Delivery – The method chosen to execute the project.
Module : Construction (Procurement) & Negotiating – The actual building process and contract negotiations.
Module : Facility Management – Ongoing operation and maintenance of the completed structure.
Module : (Implied) – Often relates to end-of-life, renovation, or future expansions, tying back to the cycle.
Renovations of Existing Facilities
When renovating, a thorough evaluation of the existing facility is crucial:
Site: Access, subsurface conditions, drainage, parking, zoning compliance, and existing utilities.
Function: Adequacy of current spaces for intended new use.
Structural: Integrity and capacity of the existing structural system.
Envelope: Condition of the roof, walls, windows, and sealants.
Environmental: Presence of hazardous materials or environmental concerns.
Systems: Evaluation of HVAC, Plumbing, Electrical, Fire Alarm, Fire Protection, Life Safety, and Accessibility systems.
Design & Document Phases
The design progresses through several stages, often aligned with AIA (American Institute of Architects) classifications:
Conceptual (Schematic per AIA):
Focuses on the program, basic plans, and elevations.
Schematic (Design Development per AIA):
Defines the size, shape, and primary materials for the project.
Construction Documents (CDs) (same per AIA):
Comprises detailed drawings and specifications used for the actual construction of the facility.
Design & Contract Development Progress
Design documents evolve in stages, typically measured by completeness:
. Conceptual: Often starts as a