Electrical Construction Work Progress and Emergency Power Off Implementation
Administrative Updates and Scheduling
Inspection Status:
The recent building inspection went well and was successful.
Written confirmation will be sent via email to confirm details with Tate.
Personnel Schedule and Leave:
Charlie will be off work for on Tuesday and Wednesday to attend his sister's wedding in Kirkwood.
Details on Kirkwood location:
Located in a remote, outdoor environment.
Recognized as the farthest southern ski resort in the Sierra Nevada mountain range.
Charlie is driving a Toyota Camry to the event.
Mobile phone reception in Kirkwood is known to be spotty; project emails will be checked once cellular service is re-established.
Detailed Task Status Updates (Items 1 to 10)
Task Items , , and :
No progress has been made; work remains unstarted.
Task Item :
No work has been conducted on the slides.
Task Item :
Rooms on the and floors have not been started.
Delay Factors: High trade congestion on site. Both plumbing and HVAC crews were working inside the rooms simultaneously, preventing electrical access.
Ongoing Work: Electrical crews spent the shift pulling wire and terminating electric vehicle (EV) car chargers outside the rooms.
Task Item :
No progress made.
Task Item (Water Heater Bonding):
Current Status: In progress.
The bonding conductor was pulled down into the Main Switchboard (MSB), terminated, and torqued.
Remaining Work: Tying up the opposite end, which requires a crimper tool. Targeted for completion on Wednesday (the ).
Task Items and (Monument Signs):
Work is the responsibility of external contractors.
Concrete has not yet been poured for the sign bases.
Task Item (First Floor Electrical Room):
Current Status: In progress.
The main lighting control panel was positioned and mounted today by Roberto.
Remaining Work: Chases must be installed from can to can along with interconnect wiring.
Target Schedule: Pipe can-to-can and pull all interconnect wire into the lighting control panel by Wednesday.
Detailed Task Status Updates (Items 11 to 21)
Task Item (Generator):
The generator unit has been set and pulled into place.
Remaining Work: Wire termination at the Automatic Transfer Switch (ATS) and termination at the generator unit.
Schedule: Final terminations scheduled for completion by Wednesday, allowing multiple tracking items to be crossed off by Thursday.
Standoffs and Hardware:
A new set of picks for the standoffs was delivered to Chris.
Poolside Trellis Lighting: Work remains incomplete.
Track Lighting and Items and :
Track lighting and items and fall under the scope of VCC.
Task Item (Elevator Standoffs):
Chris is fabricating/installing standoffs specifically for the elevators under item , which are distinct from structural standoffs.
Task Item (West Side Gate):
Structural gate work on the West Side is complete.
Electrical installation for item is scheduled to commence shortly.
Task Item (Exterior Weatherproof Exits):
Chris has officially placed the order for the additional exterior weatherproof exit signs.
Task Item (Breakers):
The required circuit breaker is currently backordered.
Task Item :
Current Status: In progress.
Daily Field Operations Summary and Emergency Power Off (EPO) Integration
Summary of Completed Work Items:
EV Car Chargers: Pulled car charger supply circuits on both the North and South sides to the main panel.
Exterior & Interior Terminations: Assembled/made up the Christie unit on the exterior while completing interior panel terminations.
Lighting Control Piping: Roberto positioned the lighting control enclosure and is actively piping conduit can-to-can.
Generator Emergency Power Off (EPO) / E-Stop Addition:
Scope Modification: Addition of a remote Generator Emergency Power Off (EPO) / Emergency Stop (E-stop) control.
Functional Purpose: Provides an external emergency shut-off switch located remotely from the generator to allow manual shutdown during emergency events (such as a fire).
Plan Status: Confirmed to be present on the original construction drawings; no change order is required as it is standard across generator installations.
Labor Estimate: Required labor is estimated at for .
Installation Procedure:
Existing conduit is already in place at the location.
Mount and secure a section of metal strut.
Install, mount, and wire the emergency stop push-button unit onto the strut.
Material Requirements: Emergency stop push-button device.