Site Management Planning

Part 1: The Construction Team → Task 1: Initial project meeting

Key participants

The key participants in the initial project meeting would include:

  • Client or client representative

  • Project manager

  • Site manager

  • Contracts manager

  • Architect or design consultants

  • Health and safety representative

  • Key subcontractors (i.e. structural, electrical and plumbing contractors.)

The above participants are important to ensure that all stakeholders understand the project scope, construction programme, safety requirements and their responsibilities before construction begins.

Location

Because there is no site office established at this current stage of the project, the meeting will take place at the contractor’s office.

The main contractor’s office provides a suitable professional environment where the project drawings, the specs and contract documents can be reviewed together by the project team mentioned above.

Time

The meeting will take place during the pre-construction phase, immediately after the contract has been awarded and before site establishment begins.

Holding the meeting at this stage has multiple benefits, first it ensures that the project team can confirm the construction programme, secondly, it confirms the responsibilities and finally, ensures the correct site management procedures before any construction activities start.

Documentation required

The following documents are required for the meeting:

  • Construction drawings

  • Project specifications

  • Contract documents

  • Construction programme

  • Health and safety plan

  • Building consent documentation

  • Risk assessments.

  • Site management plan

  • Traffic management plan

Having these documents allows the project team to review the project requirements, confirm construction sequencing and ensure compliance with the NZBC and the HSWA 2015

Purpose of meeting

This meeting’s purpose is to make sure that the personal mentioned above clearly understand the scope of the project, construction schedule, safety requirements and communication procedures before construction begins.

The meeting establishes coordination between the project team, clarifies responsibilities and identifies potential risks that may affect the construction process, and it also establishes accountability between the team.

This meeting is also critical for the site manager to ensure that site establishment activities, safety planning and subcontractor coordination are clearly understood before construction work begins.

Agenda Items

The meeting agenda will include:

  • Introduction of the project team

  • Confirmation of roles and responsibilities

  • Review of project drawings and specifications

  • Discussion of the construction programme and key milestones

  • Confirmation of health and safety procedures

  • Discussion of site access and delivery logistics

  • Communication procedures between stakeholders

  • Identification of potential project risks or constraints.

Follow-up actions

After the meeting, meeting minutes will be issued to all stakeholders to confirm the decisions, responsibilities and agreed actions.

The project manager and site manager will then finalise the construction programme and coordinate with the subcontractors. They will then complete safety documentation and begin preparing for site establishment.

Regular project coordination or site meetings will then be scheduled regularly to monitor progress and address issues to ensure the project remains aligned with the construction programme.