4. Lecture 4 - Mixed - Multi Model - Singleton Method
Manufacturing 3: Review of Lecture 3
Performance Measures
Define performance measures for manufacturing processes.
Line Balancing
Use the Kilbridge and Wester method to balance a production line.
Apply the Ranked positional weight method to balance a line.
Course Structure
Course Outline
Introduction
Plant Layout
Design and Scheduling of Flow Process Systems
3.1 Line Balancing
3.2 The Kilbridge and Wester Method
3.3 The Ranked Positional Weight Method
3.4 More Complex Situations – Mixed Model and Multi Model
Layout for Batch Production – Singleton’s Method
Scheduling
Computer Assisted Production Planning
Just-in-Time Systems
Synchronous Production Systems and Theory of Constraints
Digital Manufacturing and Work Measurement
Learning Outcomes
Session Objectives
Understand the difference between multi-model and mixed-model assembly lines.
Balance a composite line.
Apply Singleton’s method to a sequencing problem.
The Ideal Production System
A smoothly flowing stream with many tributaries and no pools, dams, or other accumulations.
Mixed Model Production
Mixed Model Production is the practice of assembling several distinct models of a product on the same assembly line.
The objective is to smooth demand on upstream workcenters, manufacturing cells or suppliers and thereby reduce inventory, and eliminate changeovers.
It also eliminates difficult assembly line changeovers.
Assembly Line Balancing – Complex Situations
Assembly lines organized for a single product can be very efficient.
Consumer pressure leads to a limited variability being permitted in industry.
Economics usually dictates that the variation in product specification is not so significantly different from the base product as to justify a separate assembly line.
Handling Limited Variability
Assume the same assembly line is used; how then is the limited variability in product specification handled?
If essentially the same work stations are used but necessitate re-tooling and different set-ups, then a multi-model assembly line is used.
If roughly the same workstations are used without necessitating significant re-tooling etc. but the inclusion of a relatively small number of additional workstations or the by-passing of a few others, then a mixed-model assembly line is used.
Multi-Model Assembly Lines
Assembly lines can handle the production of two or more products consecutively on the assembly line.
The major problems associated with organisation and control relate to:
Balancing the line where all products are accounted
The order in which the products to be launched on to the assembly line
This sequence will directly influence the efficiency of the assembly line.
The sequence should seek to equalise the loading on workstations and prevent localised bottlenecks and/or shortage of work on other workstations.
Batch production economics
Batch sizes to be produced relate to the holding costs and setup costs for the product concerned
The order in which products are manufactured
Minimize setup costs between products
Mixed-Model Assembly Lines
Assembly lines can handle the production of two or more products concurrently on the assembly line
The major problems associated with organisation and control relate to:
Balancing the line where all products are accounted
The complexity of balancing a mixed model assembly line depends greatly on the similarity or otherwise between the work element constituency of the different products
If there is significant similarity between the products, then the line balancing process will produce similar workstation specifications for the products if they are each considered independently
Balancing Loss
So the balancing loss will be small irrespective of which product is being produced
However, if there are significant differences in the work element requirements of the products then the previous approach will not work efficiently
Composite Product Requirement
In this case it is more appropriate to combine the work element requirements of all products to achieve a composite product requirement for a given period of time
The line balancing process then proceeds on the basis of the data for this composite requirement
Worked Example: Composite Balancing Problem
Consider Assembly line for Model A
Required production rate for Model A = 200/week
Elements used in Model A: 0, 1, 2, 3, 4, 5, 6, 7, 8, 9, 10
Worked Example: Composite Balancing Problem
Consider Assembly line for Model B
Required production rate for Model B = 100/week
Elements used in Model B: 1, 3, 4, 7, 8, 9, 11, 12, 13, 14, 15, 16, 17, 18
Class Exercise
Task
Balance the Line for a WS time of 40 hours (1 week)
Steps
Combine both precedence diagrams into a single precedence diagram
Create a composite Balancing line table
Balance the line
Worked Example: Combine Precedence Diagrams
Elements used in Models A and B
Worked Example: Step 2
Create a Composite Balancing Line Table
The table will provide details of the weekly work requirement for each element taking into account the contributions made by one or both models
In this way a positional weight can be calculated for the composite situation based on a week's production
Worked Example – Step 2
Element No | Element Duration (hr) | Model A Req. Per week | Model B Req. Per week | Total Req. Per Week | Total Time Per Week (hr) | Positional Weight |
|---|---|---|---|---|---|---|
0 | 0.32 | 200 | 0 | 200 | 64 | |
1 | 0.10 | 200 | 100 | 300 | 30 | |
2 | 0.20 | 200 | 0 | 200 | 40 | |
3 | 0.05 | 200 | 100 | 300 | 15 | |
4 | 0.10 | 200 | 100 | 300 | 30 | |
5 | 0.23 | 200 | 0 | 200 | 46 | |
6 | 0.20 | 200 | 0 | 200 | 40 | |
7 | 0.05 | 200 | 100 | 300 | 15 | |
8 | 0.32 | 200 | 100 | 300 | 96 | |
9 | 0.10 | 200 | 100 | 300 | 30 | |
10 | 0.30 | 200 | 0 | 200 | 60 | |
11 | 0.10 | 0 | 100 | 100 | 10 | |
12 | 0.15 | 0 | 100 | 100 | 15 | |
13 | 0.17 | 0 | 100 | 100 | 17 | |
14 | 0.08 | 0 | 100 | 100 | 8 | |
15 | 0.07 | 0 | 100 | 100 | 7 | |
16 | 0.13 | 0 | 100 | 100 | 13 | |
17 | 0.20 | 0 | 100 | 100 | 20 | |
18 | 0.13 | 0 | 100 | 100 | 13 |
element duration x total reg. per week
eg. 0.32 x200
element only A
element split
element only B
Complete the PW Column
Work out Positional weights for each work element
Hint PW for Work Element 18 = 13hr
Worked Example – Finished Composite Balancing Line Table
Element No | Element Duration (hr) | Model A Req. Per week | Model B Req. Per week | Total Req. Per Week | Total Time Per Week (hr) | Positional Weight |
|---|---|---|---|---|---|---|
0 | 0.32 | 200 | 0 | 200 | 64 | 411 |
1 | 0.10 | 200 | 100 | 300 | 30 | 463 |
2 | 0.20 | 200 | 0 | 200 | 40 | 347 |
3 | 0.05 | 200 | 100 | 300 | 15 | 292 |
4 | 0.10 | 200 | 100 | 300 | 30 | 277 |
5 | 0.23 | 200 | 100 | 200 | 46 | 307 |
6 | 0.20 | 200 | 0 | 200 | 40 | 246 |
7 | 0.05 | 200 | 100 | 300 | 15 | 125 |
8 | 0.32 | 200 | 100 | 300 | 96 | 206 |
9 | 0.10 | 200 | 100 | 300 | 30 | 110 |
10 | 0.30 | 200 | 0 | 200 | 60 | 167 |
11 | 0.10 | 0 | 100 | 100 | 10 | 157 |
12 | 0.15 | 0 | 100 | 100 | 15 | 142 |
13 | 0.17 | 0 | 100 | 100 | 17 | 125 |
14 | 0.08 | 0 | 100 | 100 | 8 | 61 |
15 | 0.07 | 0 | 100 | 100 | 7 | 53 |
16 | 0.13 | 0 | 100 | 100 | 13 | 46 |
17 | 0.20 | 0 | 100 | 100 | 20 | 20 |
18 | 0.13 | 0 | 100 | 100 | 13 | 13 |
Class Exercise
Task: Balance the Line for a WS time of 40hours
Steps
Combine both precedence diagrams into a single precedence diagram
Create a composite Balancing line table
Balance the line
Process Step by Step
We will go through the process step by step:
Lets balance the line for a workstation time of 40hours
Use the following table and a blank page to write down procedure
Workstation | Element | Total Time Per Week (hr) | Time Remaining (hr) |
|---|
Step 3: Balance the Line
Examine the hours required for each element per week
If a normal 40hour week is assumed, it can be seen that work elements 0, 5, 8 and 10 require more than 40 hour capacity per week
one workstation does not have the capacity -
need more workstations
Step 3: Balance the Line – Increasing Capacity
Examine the hours required for each element per week
If a normal 40hour week is assumed, it can be seen that work elements 0, 5, 8 and 10 require more than 40 hour capacity per week
It is thus necessary to increase their capacity by multiplying by an integer value i.e. doubling their capacity
So for these workstations, instead of assuming there is a 40hour week capacity there is an 80 hour per week capacity
When this happens it will be indicated by an extra workstation being added
Workstation 1
Remember: 40hr Workstation time
Options 0, 1, and 11
Choose element 1 for WS 1 based on Positional Weight
Remaining WS time = 40-30=10hr
Next Choose element 11 as it fits within 40hr limit for WS
Workstation | Element | Total Time Per Week (hr) | Time Remaining (hr) |
|---|---|---|---|
1 | 1 | 30 | 10 |
1 | 11 | 10 | 0 |
Workstation 2
Options 0, 12, and 3
Element 0 has Largest Positional Weight – Choose it
Element 0 time is 64hours which is more than 40hours per station
Double Workstation capacity to 80hours (now becomes WS 2 and 3)
16hours spare therefore Element 3 can slot into workstation 2 and 3
Workstation | Element | Total Time Per Week (hr) | Time Remaining (hr) |
|---|---|---|---|
1 | 1 | 30 | 10 |
1 | 11 | 10 | 0 |
2,3 | 0 | 64 (80 cap) | 16 |
2,3 | 3 | 15 | 1 |
Class Exercise
Complete the assigning of elements to workstations
Calculate balancing loss and line efficiency
Workstation | Element | Total time per week | Time remaining hr |
|---|---|---|---|
1 | 1 | 30 | 10 |
1 | 11 | 10 | 0 |
2, 3 | 0 | 64 80 cap | 16 |
2, 3 | 3 | 15 | 1 |
4 | 2 | 40 | 0 |
5, 6 | 5 | 46 80 cap | 34 |
Calculating Balancing Loss and Efficiency
Balancing Loss = \frac{\text{Total time}}{\text{#Workstations x Workstation Time}} = \frac{569}{15 \times 40} = 5.2 \%
Efficiency =
Mixed-Model Assembly Lines - Model Launching
Note that production volumes indicate that model A has twice the production of model B.
So this has to be reflected in the way that the different products are launched on the assembly line.
For instance, if a sequence such as: AAAAAAAAAABBBBBAAAAAAAAAABBBBB ………. is used, it will obviously tend to induce temporary bottlenecks at some workstations and shortage of work at others.
It would be better to have a launching sequence of: AABAABAABAABAABAABAABAABAABAAB ……….. to induce a more integrated mixing in the assembly line.
Suggested Model Layout
A diagram showing various workstations in a line with queues between them, indicating work input and output.
Tutorial 1 - Question 3
Composite Line Balancing
SINGLETON’S METHOD
Each product might superficially have different machine sequences and be manufactured in different volumes.
However there might be an underlying natural sequence of machines that might not be immediately obvious.
Singleton’s method attempts to detect this underlying sequence – if there is one!
Worked Example: Determine the Optimum Production Line Layout
For the following 8 Machine 7 Product setup
Product | Machine Sequence | Volume (units/week) |
|---|---|---|
A | 2 – 3 – 7 – 1 | 20 |
B | 6 – 7 – 4 – 8 – 5 | 40 |
C | 6 – 4 – 7 | 40 |
D | 2 – 3 – 4 – 5 – 7 – 1 | 60 |
E | 7 – 2 – 6 – 5 – 1 | 50 |
F | 6 – 3 – 8 – 5 – 7 | 30 |
G | 2 – 4 – 8 – 7 | 20 |
There are 8! (40320) possible line layouts (or orderings of the 8 machines).
Cross Chart
Example “from 2 – 3” there are 20 + 60 units
From Machine | To Machine | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
|---|---|---|---|---|---|---|---|---|---|
1 | |||||||||
2 | 80 | 20 | |||||||
3 | 60 | 20 | |||||||
4 | 50 | 90 | |||||||
5 | 30 | 40 | |||||||
6 | |||||||||
7 | |||||||||
8 | |||||||||
Arbitrary Ordering of Machines |
Singleton’s Method:
Describes the position of a machine requirement in a sequence by placing it on a scale and fix the position on the scale by its position in the sequence.
Also weight according to the relative production volume.
Combine all such requirements for a machine by superimposing on the same diagram (for a machine).
SINGLETON’S METHOD – Procedure
Step 1: List the Percentile Centre Points of the number of machines
Step 2: Fill in the Singleton’s table and calculate mean and standard deviations for each machine
Step 3: Order machines in order of increasing means
Step 4: Look for backtracking and finalise layout
SINGLETON’S METHOD
Step 1: List the Percentile Centre Points of the number of machines
These mathematical relationships are used to calculate the mean and standard deviations
Number of Machines | Position | 1st | 2nd | 3rd | 4th | 5th | 6th | 7th |
|---|---|---|---|---|---|---|---|---|
3 | 16.67 | 50 | 83.33 | - | - | - | - | |
4 | 12.5 | 37.5 | 62.5 | 87.5 | - | - | - | |
5 | 10 | 30 | 50 | 70 | 90 | - | - | |
6 | 8.33 | 25 | 41.6 | 58.31 | 74.97 | 91.63 | - |
SINGLETON’S METHOD
Step 1: Example: Percentile Centre Points for 3 machines i.e. n=3
Number of Machines (n) | Position | 1st | 2nd | 3rd | 4th | 5th | 6th | 7th |
|---|---|---|---|---|---|---|---|---|
3 | 16.67 | 50 | 83.33 | - | - | - | - | |
4 | 12.5 | 37.5 | 62.5 | 87.5 | - | - | - | |
5 | 10 | 30 | 50 | 70 | 90 | - | - | |
6 | 8.33 | 25 | 41.6 | 58.31 | 74.97 | 91.63 | - | |
In all working out keep to 2 d.p.!!!
SINGLETON’S METHOD
Class Exercise: Calculate the Percentile Centre Points for 7 machines i.e. n=7
Number of Machines (n) | Position | 1st | 2nd | 3rd | 4th | 5th | 6th | 7th |
|---|---|---|---|---|---|---|---|---|
7 | 7.14 | 21.43 | 35.71 | 50.00 | 64.29 | 78.57 | 92.86 |
SINGLETON’S METHOD
Step 1: List the Percentile Centre Points of the number of machines
Step 2: Fill in the Singleton’s table and calculate mean and standard deviations for each machine
Step 3: Order machines in order of increasing means
Step 4: Look for backtracking and finalise layout
SINGLETON’S METHOD
Step 2: Calculate mean and standard deviations for each machine in turn
SINGLETON’S Table (Machine 1)
Product | CP (i) | Weighting (ii) | (i) X (ii) (iii) | (i) X (i) (iv) | (iv) X (ii) (v) |
|---|---|---|---|---|---|
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F | |||||
G |
SINGLETON’S METHOD
Step 2: Fill in the Singleton’s table and calculate mean and standard deviations for each machine
Establish 1st product on machine 1, i.e. Product A
There are four machines for Product A, therefore CP for Product A at position 4 for n=4 machines is 87.5
SINGLETON’S Table (Machine 1)
Product | CP (i) | Weighting (ii) | (i) X (ii) (iii) | (i) X (i) (iv) | (iv) X (ii) (v) |
|---|---|---|---|---|---|
A | 87.5 | (20) 2 | 175 | 7656.25 | 15312.5 |
All values are multiples of ten so removed o to simplify calculations
SINGLETONS METHOD
Step 2: Fill in the Singleton’s table and calculate mean and standard deviations for each machine
Establish next product on Machine 1 i.e. Product D
There are six machines for Product D, therefore CP for Product D at position 6 for n=6 machines is 91.63
SINGLETON’S Table (Machine 1)
Product | CP (i) | Weighting (ii) | (i) X (ii) (iii) | (i) X (i) (iv) | (iv) X (ii) (v) |
|---|---|---|---|---|---|
A | 87.5 | (20) 2 | 175 | 7656.25 | 15312.5 |
SINGLETONS METHOD
Step 2: Fill in the Singleton’s table and calculate mean and standard deviations for each machine
Establish next product on Machine 1 i.e. Product D
There are six machines for Product D, therefore CP for Product D at position 6 for n=6 machines is 91.63
SINGLETON’S Table (Machine 1)
Product | CP (i) | Weighting (ii) | (i) X (ii) (iii) | (i) X (i) (iv) | (iv) X (ii) (v) |
|---|---|---|---|---|---|
A | 87.5 | (20) 2 | 175 | 7656.25 | 15312.5 |
D | 91.63 | (60) 6 | 549.78 | 8396.06 | 50376.36 |
SINGLETON’S METHOD
Step 2: Fill in the Singleton’s table and calculate mean and standard deviations for each machine
Establish next product on Machine 1 i.e. Product E
There are five machines for Product E, therefore CP for Product E at position 5 for n=5 machines is 90
SINGLETON’S Table (Machine 1)
Product | CP (i) | Weighting (ii) | (i) X (ii) (iii) | (i) X (i) (iv) | (iv) X (ii) (v) |
|---|---|---|---|---|---|
A | 87.5 | (20) 2 | 175 | 7656.25 | 15312.5 |
D | 91.63 | (60) 6 | 549.78 | 8396.06 | 50376.36 |
SINGLETON’S METHOD
Step 2: Fill in the Singleton’s table and calculate mean and standard deviations for each machine
Establish next product on Machine 1 i.e. Product E
There are five machines for Product E, therefore CP for Product E at position 5 for n=5 machines is 90
SINGLETON’S Table (Machine 1)
Product | CP (i) | Weighting (ii) | (i) X (ii) (iii) | (i) X (i) (iv) | (iv) X (ii) (v) |
|---|---|---|---|---|---|
A | 87.5 | (20) 2 | 175 | 7656.25 | 15312.5 |
D | 91.63 | (60) 6 | 549.78 | 8396.06 | 50376.36 |
E | 90 | (50) 5 | 450 | 8100 | 40500 |
SINGLETON’S METHOD
Step 2: Fill in the Singleton’s table and calculate mean and standard deviations for each machine
Work out Mean and SD from data
SINGLETON’S Table (Machine 1)
Product | CP (i) | Weighting (ii) | (i) X (ii) (iii) | (i) X (i) (iv) | (iv) X (ii) (v) |
|---|---|---|---|---|---|
A | 87.5 | (20) 2 | 175 | 7656.25 | 15312.5 |
D | 91.63 | (60) 6 | 549.78 | 8396.06 | 50376.36 |
E | 90 | (50) 5 | 450 | 8100 | 40500 |
2 d.p.
2 d.p.
SINGLETON’S METHOD
Class Exercise:
Split into 7 equal groups and work out the mean and standard deviations for:
Machine 2 - 8
SINGLETONS METHOD
Step 1: List the Percentile Centre Points of the number of machines
Step 2: Fill in the Singleton’s table and calculate mean and standard deviations for each machine
Step 3: Order machines in order of increasing means
Step 4: Look for backtracking and finalise layout
SINGLETON’S METHOD
Step 3: Order machines in order of increasing means
Summary of Results Table
Note “rank in order of ascending means”
Machine | Mean | σ | Position |
|---|---|---|---|
1 | 90.37 | 1.28 | |
2 | 16.67 | 9.58 | |
3 | 28.64 | 4.69 | |
4 | 45.29 | 4.88 | |
5 | 70.55 | 11.58 | |
6 | 24.17 | 17.62 | |
7 | 58.58 | 30.25 | |
8 | 61.67 | 8.74 |
SINGLETON’S METHOD
Step 3: Order machines in order of increasing means
Summary of Results Table
Initially sequence should be in order
Machine | Mean | σ | Position | Revised |
|---|---|---|---|---|
1 | 90.37 | 1.28 | 8th | |
2 | 16.67 | 9.58 | 1st | |
3 | 28.64 | 4.69 | 3rd | |
4 | 45.29 | 4.88 | 4th | |
5 | 70.55 | 11.58 | 7th | |
6 | 24.17 | 17.62 | 2nd | |
7 | 58.58 | 30.25 | 5th | |
8 | 61.67 | 8.74 | 6th |
SINGLETON’S METHOD
Step 3: Order machines in order of increasing means
Initially sequence should be in order of increasing means
Machine | Mean | σ | Position | Revised |
|---|---|---|---|---|
1 | 90.37 | 1.28 | 8th | |
2 | 16.67 | 9.58 | 1st | |
3 | 28.64 | 4.69 | 3rd | |
4 | 45.29 | 4.88 | 4th | |
5 | 70.55 | 11.58 | 7th | |
6 | 24.17 | 17.62 | 2nd | |
7 | 58.58 | 30.25 | 5th | |
8 | 61.67 | 8.74 | 6th |
Superimpose Workflow
Now superimpose workflow on production line
Example flow – Product A – (2 – 3 – 7 – 1)
SINGLETONS METHOD
Step 1: List the Percentile Centre Points of the number of machines
Step 2: Fill in the Singleton’s table and calculate mean and standard deviations for each machine
Step 3: Order machines in order of increasing means
Step 4: Look for backtracking and finalise layout
SINGLETONS METHOD
Solution Steps
Step 4: Look for backtracking and finalise layout
SINGLETONS METHOD
Step 4: What about “backtracking”
Superimpose back flow of work i.e. Product D
Product D path (2 – 3 – 4 – 5 – 7 – 1)
SINGLETONS METHOD
Step 4: What about “backtracking”
*