PMBOK Guide Sixth Edition Summary Notes

PROJECT INTEGRATION MANAGEMENT

  • Overview: Unifies processes and activities across the project lifecycle. Accountability rests solely with the project manager.

  • Develop Project Charter: Formally authorizes the project and grants authority to the project manager. Inputs include business documents (Business Case, Benefits Management Plan) and agreements.

  • Develop Project Management Plan: Consolidates subsidiary plans into a baseline. Once baselined, changes require formal change control.

  • Direct and Manage Project Work: Leading the execution of activities and implementing approved changes.

  • Manage Project Knowledge: Leveraging existing and creating new knowledge. Distinguishes between explicit knowledge (codified) and tacit knowledge (personal/context-based).

  • Monitor and Control Project Work: Tracking progress against performance objectives via data analysis (Trend, Variance, Root Cause).

  • Perform Integrated Change Control: Reviewing, approving, and managing changes to deliverables and documents. Often utilizes a Change Control Board (CCB).

  • Close Project or Phase: Finalizing all activities, archiving information, and releasing resources.

PROJECT SCOPE MANAGEMENT

  • Scope Definition: Includes Product Scope (features/functions) and Project Scope (work to deliver features).

  • Collect Requirements: Determining stakeholder needs. Uses tools like Context Diagrams and Prototyping.

  • Create WBS: Hierarchical decomposition of total work into Work Packages. Follows the 100%100\% rule (total work at lower levels rolls up to the top).

  • Scope Baseline: Consists of the Project Scope Statement, WBS, and WBS Dictionary.

  • Validate Scope: Formal acceptance of completed deliverables by the customer.

  • Control Scope: Monitoring status and managing changes to prevent Scope Creep.

PROJECT SCHEDULE MANAGEMENT

  • Precedence Diagramming Method (PDM): Links activities via four relationships: FS, FF, SS, SF.

  • Estimating Durations: Uses Analogous (top-down), Parametric (statistical), or Three-Point Estimating (Triangular: t<em>E=(t</em>O+t<em>M+t</em>P)/3t<em>E = (t</em>O + t<em>M + t</em>P) / 3).

  • Critical Path Method (CPM): Identifies the longest path with zero total float, determining the minimum project duration.

  • Schedule Compression:

    • Crashing: Adding resources to shorten duration for least incremental cost.

    • Fast Tracking: Performing sequential activities in parallel.

PROJECT COST MANAGEMENT

  • Earned Value Management (EVM):

    • Planned Value (PV): Budget for scheduled work.

    • Earned Value (EV): Value of work actually performed.

    • Actual Cost (AC): Cost incurred for work performed.

    • Variances: CV=EV−ACCV = EV - AC; SV=EV−PVSV = EV - PV.

    • Indices: CPI=EV/ACCPI = EV / AC; SPI=EV/PVSPI = EV / PV.

  • Estimate at Completion (EAC): Forecasting the total cost based on current performance (e.g., EAC=BAC/CPIEAC = BAC / CPI).

  • Cost Baseline: Time-phased project budget excluding management reserves.

PROJECT QUALITY MANAGEMENT

  • Core Concept: Prevention is preferred over inspection. Quality (conformance) vs. Grade (technical characteristics).

  • Manage Quality: Translating the plan into executable activities (Quality Assurance).

  • Control Quality: Verifying deliverables meet standards. Uses Control Charts, Check Sheets, and Statistical Sampling.

  • Cost of Quality (COQ): Conformance costs (Prevention, Appraisal) vs. Nonconformance costs (Internal/External Failure).

PROJECT RESOURCE MANAGEMENT

  • Team Development: Following the Tuckman Ladder (Forming, Storming, Norming, Performing, Adjourning).

  • Conflict Management: Five techniques: Withdraw, Smooth, Compromise, Force, and Collaborate.

  • Responsibility Assignment Matrix (RAM): Often represented as a RACI chart (Responsible, Accountable, Consult, Inform).

PROJECT RISK MANAGEMENT

  • Identify Risks: Finding individual and overall project risks.

  • Qualitative Analysis: Prioritizing risks via Probability and Impact Matrix.

  • Quantitative Analysis: Numerical modeling using Monte Carlo Simulation, Decision Trees, and Tornado Diagrams.

  • Strategies for Threats: Escalate, Avoid, Transfer, Mitigate, Accept.

  • Strategies for Opportunities: Escalate, Exploit, Share, Enhance, Accept.

PROJECT PROCUREMENT MANAGEMENT

  • Contract Types:

    • Fixed-Price: Firm Fixed Price (FFP), Incentive Fee (FPIF).

    • Cost-Reimbursable: CPFF, CPIF, CPAF.

    • Hybrid: Time and Material (T&M).

  • Source Selection: Criteria include capability, cost, and technical expertise.

PROJECT STAKEHOLDER MANAGEMENT

  • Engagement Levels: Unaware, Resistant, Neutral, Supportive, Leading.

  • Stakeholder Analysis: Categorizing by Power, Interest, Influence, or Impact using grids or the Salience Model.