ATHENA WORK PROGRESS REPORT.
ATHENA POWER CHATISGARH ARNI ENGINEERING T PVT LTD WORK PROGRESS REPORT
1. BELT CONVEYOR 2B
Water removal work almost completed.
Old idler removed; new idler fixing work completed.
Dismantled 2 nos. of paddle feeders for maintenance.
All pulleys dismantled for lagging purposes.
Drive part dismantled for overhauling.
Take-up guide wheels overhauled.
Motor overhauling completed.
Required Spares:
New gear box, pulleys
Take-up unit accessories
Proper area lighting
Nut & bolt sizes: 16x50, 20x120, 22x100
/
2. BELT CONVEYOR 3B
All pulleys dismantled for lagging.
Gear box dismantled and overhauled; awaiting oil seal to finalize.
Pulley erection and alignment completed except for tail pulley.
Idler and deck plate fixing work completed.
Self-adjustment carrying idler frame overhauling completed.
HT motor overhauling ongoing.
Ready for belt laying.
Required Spares:
2 nos. of tail pulleys
Gear box oil seal
Scoop coupling accessories: hose pipe, oil cooler motor, radiator
Take-up accessories
3. BELT CONVEYOR 4 A/B
All pulleys dismantled for lagging.
Gear box dismantled; overhauling almost finished; waiting for oil seal.
Idler and deck plate fixing completed.
Self-adjustment frames overhauling completed.
All pulley erection work done.
Motor overhauling ongoing.
Required Spares:
Gear box oil seal
Skirt box accessories: clamp, skirt rubber
Nut bolts: 16x50, 20x120, 22x100
Self-adjustment frame spring
Deck plates (sizes: 1014x1500, 750x1500)
4. BELT CONVEYOR 5A/B
All pulleys dismantled for lagging.
Gear box dismantling and overhauling completed; awaiting seal.
All pulley erection and alignment completed.
Idler and deck plate erection completed.
Belt laying work completed; 2 nos. of belt joint works done.
Required Spares:
Gear box oil seal
Skirt box accessories: side clamp, skirt rubber, back plate
Take-up unit accessories: wire rope, bull dog clamp
Fluid coupling fusible plug
5. BELT CONVEYOR 15
All pulley dismantle work completed.
Conveyor technological structure alignment work ongoing.
Idler and frame erection halted due to lack of deck plate and nut bolts.
Crusher house side gear box dismantled and overhauled; awaiting oil seal.
Scoop coupling dismantled and cleaned.
Pulley erection and alignment: 7 of 9 completed.
Required Spares:
Deck plate, self-adjustment frames, seal plate
Drive house side new gear box & scoop coupling
Impact idlers
Nut bolts: 7000 nos. (16x50); nut bolts: 20x120, 22x100; washers: 7000 each (plain/spring)
6. REVERSIBLE BELT CONVEYOR 2
All pulley dismantle work completed.
Idler erection work completed.
Gear box overhauling completed; oil seal needs replacement.
Chute nut bolt tightness work done.
Motor overhauling completed.
Belt laying work completed.
Required Spares:
Gear box oil seal
Skirt box accessories
Take-up unit accessories
7. CRUSHER 1/2/3/4
All crushers dismantled.
Rust cleaning work done.
Rotor freeness work completed.
Nut and bolt tightness work done.
Hammer balancing inspection completed (found okay).
Required Spares:
Scoop accessories, oil cooler pump, temperature sensor, multidisc.
8. TRANSFER TOWER 4 TO 9
All pulley removal work completed.
All gear boxes dismantled for oil seal replacement.
Self-adjustment frame overhauling ongoing.
90 nos. of LT motors overhauled; coal sampler motor overhauling completed.
9. UTILITY
Electrical hoist inspection completed.
Spare report for all hoists submitted to MBPL.
Sump pump overhauling completed; awaiting bearing for smooth operation.
Conclusion
Thank you for watching. Aret Engineering T Pvt. Ltd.