Practice and Management Notes
Normal Duration and Cost
Normal Duration: Represents low-cost, realistic, efficient methods for completion under normal working conditions using standard resources and methods.
Normal Cost: Represents the cost associated with completing the activity within the Normal Duration. This cost includes:
Labour costs for workers needed to complete the activity in the Normal Duration.
Material costs for the standard materials required.
Equipment costs for the typical equipment needed for the activity.
Schedule Compression/Crashing
Reasons for Accelerating a Project:
"Imposed deadlines" set by the Client.
A specific budget set by the Client to expedite the completion date due to higher profits from using the completed project.
Very high overhead costs!
Finishing early means—to the contractor—starting another job earlier and, thus, making more profit.
Unforeseen delays: After starting construction and completing a certain percentage of the project, the contractor realizes that the project is behind schedule.
Terminology:
Also called Schedule Compression
Schedule Crashing
Time-Cost Trade-Off
Project Cost-Time Optimisation
Accelerating a project means shortening the normal duration of the project schedule.
Direct vs. Indirect Costs
Direct Costs:
Commonly represent labour, materials, equipment, and sometimes subcontractors.
Assigned directly to a work package and activity.
Indirect Costs:
Generally represent overhead costs such as supervision, administration, consultants, and interest.
Cannot be associated with any particular work package or activity.
Cost-Time Trade-Off Analysis
Plot the total direct, indirect, and overall project costs for each of these durations on a cost-time graph. What is the optimum cost-time schedule for the project? What is this cost?
Maximum Crash Time and Cost Slope
Maximum Crash Time: The maximum amount of time that an activity can realistically be shortened.
Crash Cost Per Time Unit/Cost Slope: Represents the additional cost incurred per unit of time reduction for a specific activity through crashing. It reflects the cost of employing extra resources, overtime.
Crash Duration: The shortest possible time an activity can realistically be completed in.
Crash Cost: The direct cost for completing an activity in its crash time.
Example Calculation:
Activity A
Normal Duration = 10
Normal Cost = $400
Crash Duration = 5
Crash Cost = $800
Maximum Crash Time = 5
Cost Slope = \frac{$800 - $400}{10 - 5} = $80 per unit of time
Project Crashing Steps
Draw the Network and Identify the Critical Path!
Determine Project Normal Duration.
Determine Project Normal Cost (Direct & Indirect).
Identify activities Crash Duration; Crash Cost; Maximum Crash Time; and Crash Cost/Time Unit.
Start Crashing Schedule and find total direct costs; Indirect Cost and Overall project cost for selected project durations.
Start accelerating the project by shortening the longest / critical path!
Identify the least expensive activity on the critical path to accelerate!
Identify the cost for the current project duration!
Check the critical path!
Identify the least expensive activity on the critical path!
Identify the cost for the current project duration!