S2 PMP
Session 2 Welcome and Introductions
- Greeting and welcome to session two of the prototype minimum viable product beta testing.
- Feedback is highly valued for ongoing improvements.
- Project is adaptive; features, functions, and capabilities are added based on learning and priority.
- There are 21 participants, 19 excluding the speakers.
Wins and Shout-Outs
- Applications reviewed are considered genius, with impressive careers, service, and sacrifices.
- Specific shout-outs to Franklin, Sonia, Kevin, Hunter, and Mark for their applications.
- Commitment, project management experience, and progress are celebrated.
- Appreciation for Brian's communication regarding Skillsoft (Percipio) access.
- Cohort 34 or cohorts with expired Percipio access should receive an alumni benefits email.
- If issues persist, contact Emily or Patty for Percipio access support.
- Two videos related to step eight are in production: one about the PMP exam and another on accessing Percipio resources. They will be available along with the session replay.
Accountability Polls
- First poll: Application approval status.
- 50% of participants have applications approved (up from 46% last week).
- Two are awaiting results.
- Some have completed but not yet submitted.
- Some are in progress.
- Second poll: Completion of weeks one and two assignments.
- 65% have completed the assignments.
- 35% are working on them.
Session Objectives and Approach
- Goal: Teach to the test by offering exam insights and strategies.
- Aim: Prepare participants for the exam by focusing on critical analysis of questions, not just curriculum re-teaching.
- Request: Continued live participation.
- Beta test goal: Determine an achievable number of questions per session.
Agenda
- Four-factor analysis for approaching questions
*Study aids for a better outcome on the exam - Organizational structures (projectized, matrix, functional, PMOs)
- Strategic alignment and business documents
- Types of business value
- Organizational change management frameworks
- Compliance review
Analyzing PMP Exam Questions: Four Factors
- PMP Approach:
- Identify the project management approach (agile, predictive, hybrid) relevant to the question.
- Understanding the approach is critical because certain tools and techniques are specific to each approach.
- Process/Lifecycle Stage:
- Determine where the project is in its lifecycle (initiating, planning, executing, monitoring & controlling, closing).
- Knowing the stage helps determine which documents and information are available.
- Area of Focus:
- Identify the primary focus area of the question (scope, schedule, cost, quality, procurement, risk, communications).
- Not all information in the question is relevant; discern what's important.
- Relevant Information:
- Extract the necessary details from the question to answer, ignoring any distractors.
Keywords for Project Management Approaches
- Predictive Approach:
- Detailed plan, stability focus, change control.
- Fixed scope, sequential phases, low uncertainty.
- Examples: construction.
- Adaptive (Agile) Approach:
- Rapidly changing requirements, iterative, incremental delivery.
- Flexible scope, high uncertainty, customer collaboration.
- Examples: software development projects
- Hybrid Approach:
- Combines predictive and agile elements.
- Benefits from both approaches based on project needs
- Example: Rolling wave planning
Lifecycle Stage Keywords
- Initiating:
- Feasibility study, business case, identify stakeholders.
- Project charter, high-level scope, initial risk assessment.
- Planning:
- Detailed requirements, WBS, schedule and budget development.
- Resource planning, communication plan, risk management plan.
- Executing:
- Directing and managing project work, implementing plans.
- Managing resources, communication, and stakeholder engagement.
- Monitoring & Controlling:
- Tracking progress, managing changes, identifying and addressing issues.
- Variance analysis, performance reporting.
- Closing:
- Finalizing deliverables, obtaining formal acceptance, transitioning deliverables.
- Archiving documents, lessons learned, release resources.
Agile Lifecycle Clues
- Sprint Planning:
- User stories, sprint backlog, commitment, sprint goal.
- Daily Scrum:
- Impediments, progress updates, collaboration.
- Sprint Execution:
- Self-organizing teams, continuous improvement, working software.
- Sprint Review:
- Demo, stakeholder feedback, inspect and adapt.
- Sprint Retrospective:
- Lessons learned, process improvement, team dynamics.
Question 1
- Scenario: Rapidly changing requirements. User stories for a sprint completed.
- Question: What is the most probable next step?
- Correct Answer: Agile sprint demo.
- Explanation: The context of rapidly changing requirements indicates an agile approach, and presenting a demo is the next step.
Question 2
- Scenario: A construction project is nearing completion. All major deliverables have been verified and client accepted with formal acceptance. Concern about transitioning the deliverables.
- Question: What is the next process that needs to be completed?
- Correct Answer: Predictive closing.
- Explanation: The scenario involves verification, client acceptance, and transitioning deliverables.
- All are elements of the “Closing” phase in a predictive project.
Key Areas of Focus
- Traditional approach (PMBOK 6th edition):
- Integration, Scope, Schedule, Cost, Quality, Resources, Communications, Risk, Procurement, Stakeholder
- Agile (PMBOK 7th edition):
- Stakeholder, Team, Planning, Project Work, Delivery, Measurement, Uncertainty.
- It is important to determine which area of focus is linked to the specific question.
Identifying Relevant Information
- Key: Ignore information that is irrelevant to the question's focus.
- Longer questions often contain distractors.
Question 3
- Scenario: Team cannot determine the dependencies of the tasks when planning the project. The project manager knows that the activity duration estimates.
- Question: What methodology best helps the project?
- Correct Answer: Network presidents Diagramming.
- Explanation: The question is on techniques to display activity sequences.
- risk register lists all risks related to the project.
- activities list does not identify the interdependence.
- WBS shows work broken down into work packages, but does not extend to the task level.
Organizational Structures
- A key point is to know the reporting structure so you can identify potential issues.
- Pay special attention to the relationships between employees.
Question 4
- Scenario: A project manager reviews reporting structures where team members report to both a functional manager and a project manager.
- Question: What is this reporting structure called?
- Correct Answer: Matrix.
- Explanation: A dual reporting structure is a characteristic of a matrix organization.
Question 5
- Multiple team configuration with some agile and predictive elements.
- Question: This can be defined as what type of an arrangement?
- Correct Answer: Composite.
- Explanation: The integration of multiple methods would be considered a composite form.
Key Comparison of Organizational Structures
- Functional: Hierarchical, project team dedicated to the function, work driven by specialized expertise.
- Projectized: Team reports to the project manager, focus on project objectives, high autonomy.
- Matrix: Team reports to both functional manager and project manager, resource sharing, balanced authority, often has competing priorities.
- Composite: Combines different organizational structures, adapts to project needs, complex.
Project Management Offices
- PMOs can range from support, to controlling, to directive.
- The specific type of PMO dictates how projects are planned and managed.
Question 6
- Scenario: Project managers are supported with best practices and templates.
- Question: What best describes this approach?
- Correct Answer: Supportive.
- Explanation: Providing resources to others in a non-intrusive method is considered supportive.
Question 7
- Scenario: PMO provides direction to team members.
- Question: What best describes this PMO?
- Correct Answer: Directing.
- Explanation: If a project team is receiving direction, that is indicative of a directing type of PMO.
The PMO Maturity Model
- Agile Center of Excellence: Focused on Agile principles and practices, supports Agile teams, promotes Agile adoption, governance of Agile Methodology framework.
- Supportive: Coaching, mentoring, templates, best practices, low oversight.
- Controlling: Controlling templates and guidelines, adherence to reporting requirements.
- Directive: Has control of all investment dollars and project resources, dictates how projects will be implemented.
Strategic Alignment
- A strategy can be aligned using project key results.
Question 8
- Scenario: Company needs to improve operational effectiveness for success. The project is supposed to reflect alignment with the strategic vision of the company.
- Question: What is the first action the project manager should use?
- Correct Answer: OKRs.
- Explanation: Focus on long term results and operational effectiveness.
* Objectives and Key Results (OKRs) are about the project's results and are therefore the answer.
* critical chain speaks only to project duration.
* Quality audit speaks to the compliance of deliverables
* Identifying KPIs focuses on performance and process in flight.
Question 9
- Scenario: Team requires assistance and input to enhance the project.
- Question: What is the best technique to address this?
- Correct Answer: Stretch Goals.
- Explanation: This best describes encouraging team members.
* benchmarking measures what is typically considered industry standard.
* SMART goals focus goals on what is specifically attainable.
Strategic Order of Operations
- A particular order of operations exists for proper strategic alignment:
- Mission and vision --> Strategic Initiatives --> Portfolios --> Programs and Projects --> Key Performance Indicators.
- Note: The order of operations matters.
Question 10
- Scenario: Project manager is working on the requirements
- Question: What are inputs that would not be included in establishing project goals?
- Correct Answer: Multiple Choice (Not specified)
- Explanation: You would not include business case because it happens after.
Business Value
- It is important to recognize what drives market share and product share increases.
- It can be difficult to establish or pinpoint what is the main success driver.
Question 11
- Scenario: Project driving more market share and brand awareness.
- Question: What action should the project manager take?
- Correct Answer: Strategic value.
- Explanation: Improved value refers to brand recognition.
Question 12
- Scenario: Project completed with analysis of both tangible and intangible assets.
- Question: What should be conducted to best define these types of measures?
- Correct Answer: Cost benefit analysis.
- Explanation: This represents the proper cost benefit analysis to be conducted.
Organization and Change management
*Organizations and people can sometimes be resistant to necessary change.
Business Value and Document Types
- Both tangible and intangible benefits should be identified.
Question 13
- Scenario: Fear of change due to uncertainty.
- Question: Method to address the issue.
- Correct Answer: Adkar.
- Explanation: This involves change resistance.