PM formulas
Formulas for the Exam
The following formulas are essential for the PMP certification exam:
Terminology and Formulas
Budget at Completion (BAC)
Description: The original total approved budget for the project.
Formula: None; it's the initial budget.
Planned Value (PV)
Description: The authorized budget planned for the work scheduled to be completed by a specific point in time.
Formula:
Earned Value (EV)
Description: The measure of the work actually completed expressed in terms of the authorized budget for that work.
Formula:
Actual Cost (AC)
Description: The total costs actually incurred (direct and indirect) in accomplishing the work up to a given point in time.
Formula: None; it's the actual amount spent.
Cost Variance (CV)
Description: The difference between the earned value and the actual costs. A positive value is favorable (under budget).
Formula:
Cost Performance Index (CPI)
Description: A measure of the cost efficiency of budgeted resources. A value greater than 1 is favorable (under budget).
Formula:
Schedule Variance (SV)
Description: The difference between the earned value and the planned value. A positive value is favorable (ahead of schedule).
Formula:
Schedule Performance Index (SPI)
Description: A measure of schedule efficiency. A value greater than 1 is favorable (ahead of schedule).
Formula:
Estimate at Completion (EAC)
Description: A forecast of the total cost of the project upon completion.
Formula:
Estimate to Completion (ETC)
Description: The expected cost needed to finish all the remaining project work.
Formula:
Variance at Completion (VAC)
Description: A projection of the amount of budget surplus or deficit at the end of the project.
Formula:
To-Complete Performance Index (TCPI)
Description: The calculated cost performance that is needed to be achieved with the remaining resources in order to meet a specified management goal.
Formula: